The Work of Excavation

To give a comparison by the use of figures of the remarkable progress made, I will say that about six months ago I took up the report of the Canal Commission and I found that in the previous month the amount of debris excavated for that one month exceeded 4,000,000 of cubic yards, this tremendous output being a complete answer to the criticisms of the opponents of canal construction.

In order to give a mental picture of the type of canal, let us take an imaginary trip through the canal proper. It will be forty-two miles from shore to shore. In addition to this there will be an excavation out in Limon bay on the eastern side, and in Panama bay on the western side, of about four miles on either side, in order to reach deep water.

Supposing that we are sailing down through Limon bay, which is a small bay at the bottom of the Caribbean sea, on one of our American battleships. We first enter the canal which leads from the bay up into the shore toward Gatun dam, and this section of the canal will be 500 feet wide and 40 feet deep at low water level. This channel penetrates through the mud banks and land about four miles, when it encounters Gatun dam. Gatun dam must be surmounted through the agency of locks, which have been previously described.