Russo-Turkish War

In the opinion of one English military critic, what short lines were made in the Franco-German War "were neither so speedily constructed nor so successful in result as to encourage the idea that lines of any length could be made during a campaign"; but a different impression is to be derived from the story of what was accomplished in the same direction in the Russo-Turkish War of 1877-78.

Russia planned her campaign against Turkey in the hope and expectation that it would be short, sharp and decisive. She started her mobilisation in good time, that is to say, in November, 1876, although she did not declare war until April 24, 1877. Making the mistake, however, of despising her foe, she anticipated no serious opposition from the Turks, but expected, rather, to paralyse them by a rapid advance, have a triumphal march to Constantinople, secure the desired safeguards for the Christians in Turkey, and see the war over before the end of the summer.

One reason why Russia specially desired to bring the campaign to so early a conclusion lay in the deficient and precarious nature of the rail communication. Under a convention which had been agreed to with Rumania on April 16, 1877, Russia was to have a free passage for her troops through that country. She was, also, to have the use of the Rumanian railways and of all their transport facilities. But the only line then running through Rumania was one that went from Galatz, on the Russo-Rumanian frontier, to Bucharest, and thence (with a branch to Slatina) to Giurgevo, on the Danube, where it connected with a Bulgarian line from Rustchuk, on the south of the river, to Varna, the Turkish base of supplies on the Black Sea. Not only was the Rumanian railway system thus limited in extent, but the lines had been indifferently constructed, they were badly maintained, and they had an inadequate personnel together with an insufficiency both of rolling stock and of terminal facilities. Still further, the fact that the Russian railways had a broader gauge than the railways of Rumania (among other European countries) caused great delay in the transfer, at the frontier, from the one system to the other, not alone of 200,000 men, but of the 850 field and 400 siege guns, of the ammunition, and of much other material the troops required to take with them. The alternative to dependence on the railway was a resort to roads impassable in wet weather.

What really caused the Russian plans to miscarry, however, was the obstinate defence of Plevna by Osman Pasha, who took up his position there on July 19, subjected the Russians to successive repulses, and did not capitulate until December 10, the siege costing the Russians 55,000 men and the Rumanians 10,000.

When it was realised that the check at Plevna rendered certain a prolongation of the campaign, Russia set about the construction of a series of new lines of railway during the course of the war. The principal lines thus taken in hand were:—

1. A line in Russia, from Bender, on the Dniester, to Galatz, establishing direct communication between the Odessa railways and the Rumanian frontier, and affording improved facilities for the sending of reinforcements to the seat of war.

2. A line from Fratesti, on the Bucharest-Giurgevo Railway, to Simnitza, the point on the north bank of the Danube where, on the night of June 26-7, the Russians built the bridge which enabled them to cross the river.

3. A line from Sistova, on the south side of the Danube, to Tirnova (Bulgaria), situate about thirty miles south-east of Plevna, and about twenty-five north of the Shipka Pass.

Of these three lines the construction of the first, 189 miles in length, was begun at the end of July, 1877. The original intention was to build a railway to serve the purposes of the war only; but the conclusion that ulterior strategical and commercial purposes would alike be served by linking up Odessa with the Rumanian frontier led to the building of a railway likely to be of permanent usefulness. The line was a single-track one, with a sufficient number of stations and passing places to allow of the running of seven trains in each direction in the twenty-four hours. The construction, carried out by contract, involved the building of a number of timber bridges and the provision of several embankments, one of which was over three miles in length. Great difficulties were experienced in regard to labour, and especially by reason of the refusal of the men to work either on Sundays or on their numerous saints' days. Trains were, nevertheless, running on the line within 100 days of the construction being started, and this notwithstanding the fact that the number of actual working days had been only fifty-eight. Whereas, therefore, the Germans had, in 1870, with the help of a Construction Corps over 4,000 strong, taken forty-eight days to build twenty-two miles of railway between Pont à Mousson and Remilly, the Russians in 1877 built, by contract, 189 miles of railway in just over double the same period.

A railway from Fratesti to Simnitza had become indispensable inasmuch as the main line of communication for the Russian Army could not be continued for an indefinite period along the forty miles of defective roads—speedily worn out by the heavy traffic—which separated the Bucharest-Giurgevo line from the bridge built across the Danube. The only important earthwork necessary was an embankment a mile and a half long and fourteen feet high. The bridges to be provided included one of 420 feet and two of 210 feet each. In this instance the troubles experienced were due to the difficulty in getting the necessary materials for the work of construction owing partly to the existing Rumanian lines being blocked with military traffic, and partly to the state of the roads and to the use of all available draught horses for Army transport purposes. There could thus be no great celerity shown in construction, and the forty miles of railway, begun in the middle of September, were, in fact, not ready for working until the beginning of December.

Like difficulties were experienced, though to a still more acute degree, in regard to the Sistova-Tirnova line, the length of which was to be seventy-five miles; and here only the earthworks could be finished before the end of the campaign.

What, however, had been accomplished during the time the war was in progress was (1) the completion of 229 miles of new railway, and the making of the road-bed for another seventy-five miles, together with the carrying out of a number of minor railway works; (2) the acquisition, by purchase in different countries, of 120 locomotives and 2,150 wagons and trucks, all new, and (3) the provision of a steam railway ferry across the Danube.[38]

So the development of the rail-power principle in warfare was carried still further by this construction, during the course of the Russo-Turkish conflict, of a greater length of railways, designed for military use, than had ever been built under like conditions before. The world gained a fresh lesson as to the importance of the rôle played by railways in war, and it was offered, also, a striking example of what could be done in the way of rapidly providing them in a time of emergency.

On the other hand it had to be remembered that, of the three railways in question, the one which included 189 miles out of the total 229 miles built was constructed on Russian territory where there was no danger of interruption by the enemy, while the delays which occurred with the two other lines, owing to the congestion of traffic, under war conditions, on existing railways depended upon for the supply of materials, seemed to point (1) to the risk that might, from this cause, be run if the building of lines necessary or desirable in the interests of some prospective campaign were left until the outbreak of hostilities, and (2) to the wisdom of constructing all such lines, as far as necessary and practicable, in time of peace.