Construction.

Conditions as to detailed engineering supervision.

6. Where the cost of the projected work is estimated to amount to Rs. 10,000 or more an adequate provision for detailed engineering supervision shall be a condition precedent to the grant of sanction by the Government.

In the absence of special sanction to the contrary, the local authority shall agree to such one of the following conditions as may be considered suitable in each case:—

(a) that the work shall be carried out by the Public Works Department if that Department can undertake it: in such cases an extra charge of 15 per cent. on the sanctioned estimates shall be made for supervision, unless the case is one of extraordinary difficulty, under which circumstances a higher charge may be imposed under the orders of Government; or

(b) that arrangements shall be made with the District Board for the carrying out of the work under the supervision of the District Engineer and his staff; or

(c) that the work shall be carried out under the supervision of an Engineer qualified for appointment as a District Engineer according to the rules under the Local Self-Government Act of 1885 (Ben. Act III of 1885) specially employed for the purpose; or

(d) that the work shall be carried out by private engineering firm of established reputation:

Provided that the local authority shall not advertise for tenders or enter into any contract or agreement for the execution of any works in connection with schemes or parts of schemes which have been sanctioned by Government under conditions (b), (c) or (d), until the specification and form of tender for such contract have been examined and approved by the Sanitary Engineer. No tender or contract for any such work shall be accepted until it has been submitted to the Sanitary Board and they have approved the acceptance thereof;

And further provided that when the work is carried out under condition (d), it shall be supervised by an officer appointed for the purpose by the local authority with the approval of the Sanitary Board, and shall, while in progress, be periodically inspected by the Sanitary Engineer.

Report by local authority to the Commissioner in case of small works.

7. Where the estimated cost of works amounts to less than Rs. 10,000, the local authority shall report, for the information of the Commissioner of the Division, the agency by which it is proposed to have the works carried out, and shall follow the instructions issued by him in the matter.