[TABLE NO. 4.

APPROXIMATE HOURLY VARIATION IN THE FLOW OF SEWAGE.
Percentage of Total Flow Passing Off in each Hour.

—————-+————————————————————————
| Population.
Hour. +——-+——-+——-+——-+——-+——-+——-+———
|1,000|2,000|3,000|4,000|5,000|6,000|8,000|10,000
—————-+——-+——-+——-+——-+——-+——-+——-+———
Midnight | 1.0 | 1.0 | 1.2 | 1.3 | 1.5 | 1.5 | 1.8 | 2.0
1.0 a.m. | 0.7 | 0.7 | 0.7 | 0.8 | 0.8 | 1.0 | 1.0 | 1.0
2.0 " | nil | nil | nil | nil | 0.2 | 0.2 | 0.3 | 0.5
3.0 " | nil | nil | nil | nil | nil | nil | nil | 0.2
4.0 " | nil | nil | nil | nil | nil | nil | nil | nil
5.0 " | nil | nil | nil | nil | nil | nil | nil | 0.2
6.0 " | 0.2 | 0.2 | 0.3 | 0.5 | 0.6 | 0.5 | 0.7 | 0.8
7.0 " | 0.5 | 0.5 | 1.0 | 1.5 | 1.6 | 1.7 | 2.0 | 2.5
8.0 " | 1.0 | 1.5 | 2.0 | 2.5 | 3.0 | 3.5 | 4.0 | 5.0
9.0 " | 3.5 | 4.5 | 4.5 | 4.8 | 5.5 | 5.8 | 6.0 | 6.5
10.0 " | 6.5 | 6.5 | 6.8 | 7.0 | 7.5 | 7.7 | 8.0 | 8.0
11.0 " |10.5 |11.0 |10.5 |10.0 | 9.6 | 9.3 | 9.0 | 8.8
Noon |11.0 |11.3 |10.8 |10.3 | 9.3 | 9.5 | 9.2 | 9.0
1.0 p.m. | 6.0 | 5.5 | 6.0 | 6.7 | 7.0 | 7.2 | 7.3 | 7.5
2.0 " | 7.0 | 7.3 | 7.0 | 7.0 | 6.5 | 6.5 | 6.2 | 6.0
3.0 " | 6.8 | 6.5 | 6.5 | 6.5 | 6.5 | 6.3 | 6.3 | 6.0
4.0 " | 7.5 | 7.5 | 7.3 | 7.0 | 6.7 | 6.5 | 6.2 | 6.7
5.0 " | 6.5 | 6.5 | 6.5 | 6.3 | 6.0 | 6.0 | 6.0 | 5.8
6.0 " | 4.5 | 4.5 | 4.7 | 4.8 | 5.0 | 5.0 | 5.0 | 5.2
7.0 " | 6.5 | 6.2 | 6.0 | 5.8 | 5.5 | 5.5 | 5.5 | 4.7
8.0 " | 6.2 | 6.0 | 5.8 | 5.5 | 5.5 | 5.3 | 5.0 | 4.8
9.0 " | 5.0 | 4.8 | 4.7 | 4.5 | 4.5 | 4.5 | 4.5 | 4.0
10.0 " | 4.8 | 4.6 | 4.2 | 4.0 | 3.8 | 3.5 | 3.0 | 3.0
11.0 " | 4.3 | 3.5 | 3.5 | 3.2 | 3.2 | 3.0 | 3.0 | 2.8
—————-+——-+——-+——-+——-+——-+——-+——-+———
Total |100.0|100.0|100.0|100.0|100.0|100.0|100.0|100.0
—————-+——-+——-+——-+——-+——-+——-+——-+———

ANALYSIS OF FLOW]

Percentage of total flow passing off during period named.

——————————-+————————————————————————————————+
| Population. |
+———-+———-+———-+———-+———-+———-+———-+————+
| 1,000 | 2,000 | 3,000 | 4,000 | 5,000 | 6,000 | 8,000 | 10,000 |
——————————-+———-+———-+———-+———-+———-+———-+———-+————+
7.0 a.m. to 7.0 p.m | 77.3 | 78.8 | 78.6 | 78.7 | 78.5 | 78.8 | 78.7 | 75.2 |
7.0 p.m. to 7.0 a.m | 22.7 | 21.2 | 21.4 | 21.3 | 21.5 | 21.2 | 21.3 | 21.8 |
Maximum 12 hrs. | 84.0 | 83.6 | 82.6 | 81.7 | 81.0 | 80.6 | 79.7 | 78.2 |
" 10 " | 72.8 | 72.8 | 72.1 | 71.4 | 70.0 | 69.8 | 69.2 | 68.5 |
" 9 " | 66.3 | 66.6 | 66.1 | 65.6 | 64.5 | 64.8 | 64.2 | 63.3 |
" 8 " | 61.8 | 62.1 | 61.4 | 60.8 | 59.5 | 59.0 | 58.2 | 57.5 |
" 6 " | 48.8 | 49.1 | 43.1 | 47.5 | 46.8 | 46.5 | 46.0 | 45.8 |
" 3 " | 23.0 | 28.8 | 27.11| 27.3 | 26.8 | 26.5 | 26.2 | 25.8 |
" 2 " | 21.5 | 22.3 | 21.3 | 20.3 | 19.3 | 18.5 | 18.2 | 17.3 |
" 1 " | 11.0 | 11.3 | 10.8 | 10.3 | 9.8 | 9.5 | 9.2 | 9.0 |
Minimum 9 " | 3.4 | 3.9 | 5.2 | 6.6 | 7.5 | 6.9 | 8.8 | 10.0 |
" 10 " | 6.9 | 7.4 | 8.7 | 9.8 | 10.7 | 10.4 | 11.8 | 13.0 |
——————————-+———-+———-+———-+———-+———-+———-+———-+————+

The data in the foregoing table, so far as they relate to populations of one, five, and ten thousand respectively, are reproduced graphically in Fig. 12.

This table and diagram relate only to the flow of sewage—that is, water which is intentionally fouled; but unfortunately it is almost invariably found that the flow in the sewers is greater than is thus indicated, and due allowance must be made accordingly. The greater the amount of extra liquid flowing in the sewers as a permanent constant stream, the less marked will be the hourly variations; and in one set of gaugings which came under the writer's notice the quantity of extraneous liquid in the sewers was so greatly in excess of the ordinary sewage flow that, taken as a percentage of the total daily flow, the hourly variation was almost imperceptible.

[Illustration: Fig 12 Hourly Variation in Flow of Sewage.]

Provision must be made in the scheme for the leakage from the water fittings, and for the subsoil water, which will inevitably find its way into the sewers. The quantity will vary very considerably, and is difficult of estimation. If the water is cheap, and the supply plentiful, the water authority may not seriously attempt to curtail the leakage; but in other cases it will be reduced to a minimum by frequent house to house inspection; some authorities going so far as to gratuitously fix new washers to taps when they are required. Theoretically, there should be no infiltration of subsoil water, as in nearly all modern sewerage schemes the pipes are tested and proved to be watertight before the trenches are filled in; but in practice this happy state is not obtainable. The pipes may not all be bedded as solidly as they should be, and when the pressure of the earth comes upon them settlement takes place and the joints are broken. Joints may also be broken by careless filling of trenches, or by men walking upon the pipes before they are sufficiently covered. Some engineers specify that all sewers shall be tested and proved to be absolutely water-tight before they are "passed" and covered in, but make a proviso that if, after the completion of the works, the leakage into any section exceeds 1/2 cubic foot per minute per mile of sewer, that length shall be taken up and relaid. Even if the greatest vigilance is exercised to obtain water-tight sewers, the numerous house connections are each potential sources of leakage, and when the scheme is complete there may be a large quantity of infiltration water to be dealt with. Where there are existing systems of old sewers the quantity of infiltration water can be ascertained by gauging the night flow; and if it is proved to be excessive, a careful examination of the course of the sewers should be made with a view to locating the places where the greater part of the leakage occurs, and then to take such steps as may be practicable to reduce the quantity.