Progress of Excavation.

Owing to the numerous sections of poor rock, interspersed throughout the work with stretches of sound rock, the progress of the excavation was very irregular, especially in 32d Street. The rate of excavation in good ground is shown in Table 1. In the sections of bad ground, the operations of excavation, timbering, and lining were often carried on alternately, and it is impracticable to include them in the table.

TABLE 1.—Progress and Methods of Excavation in Good Ground.

Thirty-Third Street.

Type of excavation.Tunnels.Worked from:Dates.Time
elapsed,
in
days.
Length of
tunnel
excavated,
in
linear feet.
Average
advance
per day,
in
linear feet.
Methods and conditions.
FromTo
Full-sized single tunnelB1st Ave. shaft.Feb. 28, 1906.May 12, 1906.743464.7Top heading and bench. Muck loaded by hand.
Full-sized single tunnelA1st Ave. shaft.Feb. 28, 1906.Apr. 30, 1906. 622554.1 " " " " " " " "
Full-sized twin tunnelA and B1st Ave. shaft.Aug. 23, 1906.Jan. 5, 1907.1367895.8Top full-width heading and bench. Muck loaded
by steam shovel. Working exclusively on this
heading.
Full-sized twin tunnelA and BIntermediate shaft.
(West of shaft.)
Apr. 4, 1906.Oct. 31, 1906.2107303.5Top center heading and bench. Muck loaded by
steam shovel. Working alternately in headings
east and west of the shaft.
Full-sized twin tunnelA and BIntermediate shaft.
(East of shaft.)
Apr. 4, 1906.Oct. 31, 1906.2107833.7Top center heading and bench. Muck loaded by
steam shovel. Working alternately in headings
east and west of the shaft.
Full-sized twin tunnelA and BIntermediate shaft.
(East of shaft.)
Nov. 1, 1906.Dec. 26, 1906.563115.5Top full-width heading and bench. Muck loaded
by steam shovel working exclusively on this
heading.
Exploration driftA and BIntermediate shaft.
(West of shaft.)
Mar. 1, 1907.July 23, 1907.1459476.5Exploration drift about 9 ft. by 12 ft. Mucking
by hand. Fourteen timber bents were placed in
March, and seven in April, 1907.
Twin tunnel. Enlargement
of exploration drift
A and BWest shaft.
(East of shaft.)
Sept. 6, 1907.Dec. 4, 1907.896036.8Drift excavated to full width and bench. Muck
loaded by steam shovel.