System of Distribution.
The mains from the Kensington Court Station are laid underground in a culvert 18 in. by 12 in., which is built with brickwork and cement under the pavement. A double conductor of flat copper, 0·25 square inches section, is stretched from shackle insulators attached to iron bars, which are firmly built into the culvert; the continuity of the circuit is provided by means of stranded wire, which connects each section; the flat copper rests on the top of porcelain insulators, fixed on vertical iron pieces, which are built into the floor. Connections with the sewers are left for drainage, and six surface boxes are provided for every hundred yards. Where house connections have to be made, the branch wires are united by soldering to the bare copper mains. For crossing under the streets a heavily insulated cable is employed, and is led through cast-iron pipes.
Fig. 26.
Until a larger amount of mileage is actually at work, it is difficult to express an opinion as to which is the cheapest and most efficient method of laying conductors in the streets. The relative cost of two plans tried at Kensington Court—the insulated and the bare cable in a culvert—was given by Mr. Crompton in the following Tables, [No. 1] and [No. 2], which are taken from a paper read before the Society of Telegraph Engineers and Electricians on April 12th, 1888.
[Table No. 1] refers more particularly to what is known as the Callender-Webber system of using bitumen concrete, which is compressed into blocks or cases usually about 6 ft. long, 8 in. by 5½ in. section, having two-inch holes through which the insulated copper cable is led.
The estimates given in [Table No. 2] were criticised by Mr. Kapp, who thought that “a more reliable conductor could be obtained by using a high-class lead-covered cable, which might be laid in the ground with the simple protection of a rough tarred plank to cover it.” The cost of digging the trench and running in the cable from the drum was quoted at 3s. a yard, and the total cost, inclusive of £10 for surface boxes, at £155 per 100 yards, instead of £187, as shown by the Table.
Table I.
Cost of Laying 100 Yards of Double Conductor
underneath the Footway of a London Street.
| Single. No. 16. | ⁷⁄₁₆ | ¹⁹⁄₁₅ | ¹⁹⁄₁₂ | ¹⁹⁄₁₀ | |||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Area, square inches | ·0032 | ·0225 | ·0773 | ·1613 | 0·25 | ||||||||||
| Area, square millimetres | 2·08 | 14·6 | 50 | 104 | 161·25 | ||||||||||
| Weight per 100 yards run lb. | 7½ | 53½ | 183¼ | 392 | 576 | ||||||||||
| Cost of copper at 7¾ d. | £ 0 | 4 | 10 | 1 | 14 | 6 | 5 | 18 | 0 | 12 | 13 | 0 | 18 | 15 | 0 |
| Cost of insulation | 1 | 3 | 2 | 4 | 8 | 6 | 11 | 2 | 0 | 24 | 17 | 0 | 35 | 17 | 0 |
| Total cost of Cables | 1 | 8 | 0 | 6 | 3 | 0 | 17 | 0 | 0 | 37 | 10 | 0 | 54 | 12 | 0 |
| Casing, bitumen, and cement | 5 | 3 | 0 | 5 | 5 | 0 | 8 | 0 | 0 | 12 | 10 | 0 | 12 | 10 | 0 |
| Labour, Laying | 3 | 0 | 0 | 4 | 0 | 0 | 5 | 0 | 0 | 5 | 0 | 0 | 6 | 0 | 0 |
| Trenching and repairing | 25 | 0 | 0 | 25 | 0 | 0 | 25 | 0 | 0 | 25 | 0 | 0 | 25 | 0 | 0 |
| Surface boxes and connection | 5 | 0 | 0 | 7 | 0 | 0 | 10 | 0 | 0 | 10 | 0 | 0 | 10 | 0 | 0 |
| Engineer and superintendent | 3 | 0 | 0 | 4 | 0 | 0 | 5 | 0 | 0 | 5 | 0 | 0 | 6 | 0 | 0 |
| Total | £ 42 | 11 | 0 | 51 | 8 | 0 | 70 | 0 | 0 | 95 | 0 | 0 | 114 | 2 | 0 |
| Add extra if copper, at 9½ d. | 0 | 1 | 1 | 0 | 8 | 0 | 1 | 7 | 0 | 2 | 17 | 0 | 3 | 5 | 0 |
| 42 | 12 | 1 | 51 | 16 | 0 | 71 | 7 | 0 | 97 | 17 | 0 | 117 | 7 | 0 | |
| Cost of copper per lb., laid complete | 5 | 13 | 6 | 0 | 19 | 4 | 0 | 7 | 9 | 0 | 5 | 0 | 0 | 4 | 1 |
| Current in ampères | 1·2 | 8·1 | 28 | 58 | 90 | ||||||||||
| Cost per ampère | 35 | 10 | 0 | 6 | 8 | 0 | 2 | 10 | 6 | 1 | 13 | 9 | 1 | 6 | 0 |
| ³⁷⁄₁₀ | Two Sets. ³⁷⁄₁₀ | Four Sets. ³⁷⁄₁₀ | Six Sets. ³⁷⁄₁₀ | |||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Area, square inches | 0·5 | 1·0 | 2·0 | 3·0 | ||||||||
| Area, square millimetres | 322 | 645 | 1290 | 1935 | ||||||||
| Weight per 100 yards run lb. | 1153 | 2306 | 4612 | 6918 | ||||||||
| Total cost of Cables | 108 | 0 | 0 | 216 | 0 | 0 | 432 | 0 | 0 | 648 | 0 | 0 |
| Casing, bitumen, and cement | 16 | 0 | 0 | 22 | 0 | 0 | 40 | 0 | 0 | 55 | 0 | 0 |
| Labour, Laying | 10 | 0 | 0 | 18 | 0 | 0 | 35 | 0 | 0 | 50 | 0 | 0 |
| Trenching and repairing | 25 | 0 | 0 | 25 | 0 | 0 | 30 | 0 | 0 | 35 | 0 | 0 |
| Surface boxes and connection | 10 | 0 | 0 | 10 | 0 | 0 | 10 | 0 | 0 | 10 | 0 | 0 |
| Engineer and superintendent | 10 | 0 | 0 | 10 | 0 | 0 | 20 | 0 | 0 | 25 | 0 | 0 |
| Total | 179 | 0 | 0 | 301 | 0 | 0 | 567 | 0 | 0 | 823 | 0 | 0 |
| Add extra if copper, at 9½ d. | 8 | 10 | 0 | 17 | 0 | 0 | 34 | 0 | 0 | 51 | 0 | 0 |
| 187 | 10 | 0 | 318 | 0 | 0 | 601 | 0 | 0 | 874 | 0 | 0 | |
| Cost of copper per lb., laid complete | 0 | 3 | 3½ | 0 | 2 | 8¾ | 0 | 2 | 7¼ | 0 | 2 | 6¼ |
| Current in ampères | 180 | 360 | 720 | 1,080 | ||||||||
| Cost per ampère | 1 | 1 | 0 | 0 | 17 | 6 | 0 | 16 | 8 | 0 | 16 | 1 |
Table II.
Cost of Laying 100 Yards of Double Conductor of
Bare Copper carried on Insulators in a Culvert.
| Area in square inches | 0·25 | 0·5 | 1·0 | ||||||
| Area in square millimetres | 161·25 | 322·5 | 645 | ||||||
| Weight of copper in lb. per 100 yards | 576 | 1153 | 2306 | ||||||
| Cost of copper at 7¾ d. per lb. | £ 18 | 15 | 0 | 37 | 5 | 0 | 74 | 10 | 0 |
| Laying | 9 | 0 | 0 | 9 | 12 | 0 | 9 | 12 | 0 |
| Insulators | 0 | 4 | 6 | 0 | 4 | 6 | 0 | 4 | 6 |
| 6 surface boxes and connections | 10 | 0 | 0 | 10 | 0 | 0 | 10 | 0 | 0 |
| Culvert, 18 inches × 12 inches, for two lines conductor, | 53 | 8 | 0 | 53 | 8 | 0 | 53 | 8 | 0 |
| in brickwork and cement, replacing pavement | |||||||||
| Engineers and superintendence | 6 | 0 | 0 | 10 | 0 | 0 | 10 | 0 | 0 |
| Total | £ 97 | 7 | 6 | 120 | 9 | 6 | 157 | 14 | 6 |
| Extra for copper at 9½ d. per lb. | 3 | 5 | 0 | 8 | 10 | 0 | 17 | 0 | 0 |
| Total | £ 100 | 12 | 6 | 128 | 19 | 6 | 174 | 14 | 6 |
| Cost of copper per lb. laid complete | 42 d. | 27 d. | 18·2 d. | ||||||
| Current in ampères | 90 | 180 | 360 | ||||||
| Cost per ampère | 1 | 2 | 3 | 0 | 14 | 5 | 0 | 9 | 8 |
| Area, square inches | 2·0 | 2·55 | 3·00 | ||||||
| Area, square millimetres | 1290 | 1645 | 1935 | ||||||
| Weight of copper in lb. per 100 yards | 4612 | 6125 | 6918 | ||||||
| Cost of copper at 7¾ d. per lb. | 149 | 0 | 0 | 190 | 0 | 0 | 224 | 0 | 0 |
| Laying | 9 | 15 | 0 | 9 | 15 | 0 | 10 | 0 | 0 |
| Insulators | 0 | 4 | 6 | 0 | 4 | 6 | 0 | 4 | 6 |
| 6 surface boxes and connections | 10 | 0 | 0 | 10 | 0 | 0 | 10 | 0 | 0 |
| Culvert, 18 inches × 12 inches, for two lines conductor, | 53 | 8 | 0 | 53 | 8 | 0 | 53 | 8 | 0 |
| in brickwork and cement, replacing pavement | |||||||||
| Engineers and superintendence | 10 | 0 | 0 | 10 | 0 | 0 | 15 | 0 | 0 |
| Total | 232 | 7 | 6 | 263 | 7 | 6 | 312 | 12 | 6 |
| Extra for copper at 9½ d. per lb. | 34 | 0 | 0 | 43 | 10 | 0 | 51 | 0 | 0 |
| Total | 266 | 7 | 6 | 306 | 7 | 6 | 363 | 12 | 6 |
| Cost of copper per lb. laid complete | 13·8 d. | 12 d. | 12 | 6 d. | |||||
| Current in ampères | 720 | 910 | 1080 | ||||||
| Cost per ampère | 0 | 7 | 5 | 0 | 6 | 9 | 0 | 6 | 8½ |