STREET PAVING WORK

14. Sub-foundation.—The usual procedure in preparing the sub-foundation for a pavement is:

The removal of the old pavement if one exists on the street.

The setting of new or the resetting of the old curbing. (If concrete combined curb and gutter is used it is not constructed until after the rough grading is done.)

The rough grading of the street.

The fine grading of the street.

In this work the main things for the inspector to look after are the following:

If an old pavement is to be taken up and any part of it is to be reserved for use by the city, see that the material is not injured in handling and is disposed of as the specifications or the instructions of the engineer require.

15. Curbing.—New curb stone should be inspected as soon as practicable after it is delivered on the street so that the contractor may have time to replace any that may be rejected. Rejected stones should be plainly marked on their tops with red paint, and the contractor required to remove them from the street. Stones that are defective in dressing should be given some distinctive mark and the attention of the contractor called to them so that the necessary redressing may be done well in advance of the setting, and reinspected.

If the old curb stone is to be redressed and reset, it should be inspected as soon as possible after it is taken out and all stones that are not suitable for re-use rejected and removed from the work. The redressing of the stones should be looked after carefully. The tendency in this work is toward the use of old stones that do not, or cannot be made to comply with the specifications, and toward laxity in the dressing.

Setting Curbing.—In the setting of curbing the points to be looked after are:

To see that the trenches are excavated to the full dimensions so as to provide space for the use of the full quantity required of concrete, gravel or broken stone in which the curb is to be embedded.

To see that the stones are set to true grade and alignment.

That the concrete, gravel or crushed stone used is of the proper quality, the proper quantity used, and that it is placed and compacted so as to fill the spaces designated under and around the stone. The tendency of the workmen is to treat these details as unimportant and to slight the work.

After the curbing is set any spaces between it and the edge of the sidewalk are to be cleaned out, filled and trimmed with Portland cement mortar.

16. Rough Grading.—If plows and scrapers are used in the rough grading, see that they are not allowed to penetrate or to disturb the natural soil below the true grade, and to prevent this it is better to require that the plowing and scraping shall not approach nearer than one or two inches to the true grade.

If embankment or filling is necessary, the filling material must be deposited in regular layers not more than six inches deep and each layer must be well compacted by rolling or ramming before the next layer is applied.

17. Fine Grading.—The fine grading (with pick or mattock and shovel), to bring the sub-grade to the true grade and contour required, should be done with reasonable accuracy and care. Allowance must be made for compression under the roller, so that when completed the surface shall not vary more than half an inch below nor more than a quarter of an inch above the true grade, in order that room for the full thickness of concrete foundation may be provided, and no more. Humps, depressions and irregularities of the surface are to be avoided. The fine grading will be completed by thoroughly rolling or tamping the surface to make the soil firm and dense. On some soft or wet, clayey soils, excessive rolling may produce a plastic or “liver-like” condition and the rolling should be discontinued where such a tendency appears.

18. Work Incidental to Grading.—Where it is a part of the contractor’s work to reconstruct or readjust catch basins, manholes, covers, and other structures, he should be required to keep this work done well in advance of the laying of the concrete foundation. If this work is delayed until after the main body of the concrete is in place, leaving openings to be filled later, hurriedly and perhaps carelessly, it may result in weak patches in the concrete around these structures, where, in fact, the concrete should be strongest.

CONCRETE FOUNDATIONS

19. The concrete foundation of a pavement is a most important part of the work, and must not be slighted in any way.

20. Quality of Materials.—The quality of the materials used for making the concrete are fully described in the specifications, and they must be substantially and uniformly adhered to.

The Portland cement delivered on the street will presumably have been previously inspected and accepted by the engineer, but any change in the kind, or brand, or apparent quality of the cement delivered after the beginning of the work should not be permitted without the approval of the engineer. Barrels or bags of cement not plainly marked with the brand, or name of the manufacturer must be rejected. You will frequently make balls of stiff mortar from the cement and sand used (1 part cement, 2 parts sand) and set them aside for observation. If in eight hours these balls do not set up hard the fact should be promptly reported to the engineer.

The sand and stone will naturally vary slightly from time to time, but should not differ materially from the requirements of the specifications or the standards adopted by the engineer. Stone or gravel that contains any considerable quantity, say more than 5%, of foreign matter, such as soil or refuse, should be rejected. Stone containing an excessive quantity of fine fragments or screenings bunched together in the pile, should be mixed with the mass of larger stone before it is used, so as to produce a mass of fairly even composition. Stone that is coated with mud, or that is not sound and hard should be thrown out.

Sand that is moderately coarse and does not contain more than 7½% of clay or soil, and is free from vegetable refuse, may be used.

21. Storing Materials.—Cement stored on the street must be stacked up on dry lumber floors at least four inches from the ground and effectually covered to protect it from rain or snow. Packages of cement which, when turned out for use contain hard lumps should be rejected.

Sand and stone must be stored on tight lumber floors to prevent their admixture, when being shoveled up, with street soil or other impurities. This requirement must be enforced.

22. Proportioning Concrete.—The proportions of cement, sand and stone or gravel named in the specifications must be strictly adhered to.

A barrel of Portland cement will be considered as four cubic feet and a standard bag of cement as one cubic foot.

It is usual for the contractor to measure the sand and stone by wheelbarrow loads. In that case you will measure and determine the capacity, in cubic feet, of the convenient or average wheelbarrow load, and determine the size and number of loads each of sand and stone required for one batch of concrete (if made by hand) and thereafter see that the quantities thus determined are used, and the wheelbarrow loading uniform. To measure the contents of a wheelbarrow load, use a square box holding one cubic foot. It cannot be accurately measured on the barrow.

As a check upon the proportioning of materials, you should occasionally keep a record of the quantities of cement, sand and stone used for, say, one or two hours, and mark and measure up the quantity of concrete made with them, and from this data compute the ratios of the materials used. (In ordinary street concrete, proportioned 1:3:6, the volume of rammed concrete made will just about equal the volume of the stone used.)

Where the concrete is mixed by a machine with automatic feeding devices, reliance must not be placed upon the machine for proper proportioning. Frequent tests of the materials used and the volume of concrete turned out should be made as described above, and any necessary corrections made in the feeding devices of the machine. This test should be made daily if practicable. The eye will usually detect any material change in the composition of the concrete, and whenever such changes are observed the composition ought to be at once checked up by measurement.

23. Mixing Concrete.—See that the specifications are followed. Use sufficient water to make what is commonly called a wet concrete but not so wet that free water will drain from the mixed batch before ramming. The test for proper mixing will be that all the fragments of stone are completely covered with mortar.

24. Placing Concrete on Street.—All concrete must be placed and rammed before it begins to stiffen or set. Concrete should be so handled that the mortar will segregate or separate from the stone as little as possible. When in place on the street it should make a mass of uniform consistency and appearance. The concrete should, as soon as placed on the street, be graded to a proper thickness and surface, and then well compacted by ramming. Insist on good ramming; this part of the work is not often properly done. The surface of the concrete should be brought to the true grade by proper grading and tamping. Where necessary to raise the surface, additional concrete, made of small stone, may be applied during the tamping. Neat mortar should not be used for this purpose. Sweeping mortar over the surface with street brooms should not be permitted—it is useful only to cover up defects and to produce an extra smooth surface (which is not usually desirable). To measure the thickness of the bed of concrete, lay a straight-edge upon the surface with the end of the straight-edge projecting a foot or two beyond the edge of the concrete, and measure the space from the lower edge of the straight-edge down to the sub-foundation.

Care must be taken to finish the surface of the completed concrete at the proper distance below and truly parallel to the grade and contour of the finished pavement. This is more important in the case of sheet asphalt pavements, since irregularities in the concrete will cause variation in the thickness of the finished asphalt surface, which will affect the durability of the pavement. The grade stakes for the concrete should therefore be carefully set and worked to, and humps or depressions between the stakes should be avoided.

25. In hot, dry, weather the concrete must be kept damp by watering it until it is at least five days old, and horse-travel over it must be prohibited until it has set up hard enough not to be injured thereby.

26. Old Paving Stone Foundations.—If a foundation is to be made of old paving stone blocks reset, the important points to be looked after are,

The preparation of the sub-foundation.

The sand bed.

The setting of the blocks.

The grouting of the blocks.

The sub-foundation should be prepared, where necessary, as stipulated in Sects. 16 and 17 of these instructions. This part of the work is likely to be carelessly done unless proper work is insisted upon.

The sand used as a cushion course must be of good quality and reasonably clean. The use of mixed sand and soil taken from the street excavation should not be permitted.

The blocks, after being cleaned from adhering dirt, should be set with reasonable care, well bedded in the sand cushion, and laid at such an elevation below the completed pavement surface, that after being well rammed, the surface will be at the proper elevation below the pavement datum.

The grouting of the joints is the most important part of the work. See that the mortar is made and used in accordance with the specifications, and that the joints are completely filled.

27. Broken Stone Foundations.—The specifications for broken stone foundations are sufficiently explicit, and compliance should be insisted upon. Thorough rolling is especially important.

SHEET ASPHALT PAVEMENTS

28. The manufacture of the mixture for sheet asphalt pavement, and the laying of it on the street, involve a number of separate elements or operations. The quality and durability of the pavement will depend largely upon the skill, intelligence and accuracy with which each and all parts of the work are carried out. The inspector, both at the mixing plant and on the street, must give constant and intelligent attention to the work.

29. Inspecting at Paving Plant.—Inspectors at the plant where the asphalt paving mixture is made will be provided with the following apparatus:

1 nest of standard sieves, Nos. 10, 30, 50, 80, 100 and 200 2 thermometers for sand 1 tank thermometer 2 standard flow-plates and one dozen cartridges for same 1 balance for weighing sand 6 dishes, glass or porcelain, 4 inches in diameter.

30. The more important things for the Plant Inspector to watch during the manufacture of asphalt paving mixture are:

a. Quality and grading of the sand. b. Temperature of heated sand. c. Uniform quality of the refined asphalt and flux. d. Temperature of melted bitumens. e. Uniform consistency of asphaltic cement. f. Correct ratios of sand and asphaltic cement. g. Thorough mixing of materials.

31. Sand.—The general quality and grain-size of the sand, required by the specifications, must be closely watched and adhered to.

It is hardly ever possible to secure a natural sand that will conform strictly to the theoretical composition, but substantial compliance should be required unless the Chief Engineer directs otherwise. After any sand has been approved for a given contract or street, all the sand thereafter used for that street should conform closely to the standard so approved; for any material change in the quality of the sand will change the quality of the pavement produced, unless the proportions of the other materials are changed accordingly. Any material change in the sand should therefore be promptly reported to the Chief Engineer.

32. Sand for the sieve tests should be taken from the hot-sand box and allowed to become cold. From the sample thus taken, weigh out 50 grams. Arrange the nest of sieves with the No. 200 at the bottom followed by Nos. 100, No. 80, No. 50, No. 30 and No. 10 at the top.

Place the weighed sample upon the No. 10 sieve and thoroughly shake the nest until all the sand that will, has passed through the various sieves; then weigh the various portions, beginning with that which has passed the No. 200 (deducting in each case the weight of the dish). The portion remaining on the No. 200, is the quantity passing the No. 100, etc. The sum of all these portions should be 50 grams, though it will usually be slightly less because of unavoidable waste. In use, keep the sieves clean and as free as possible from adhering grains by using a bristle brush.

33. Temperature of the Sand.—The temperature of the heated sand should be frequently noted by plunging the thermometer into the mass. It should not fall below 315° F. nor exceed 375° F. It is very important to avoid over-hot sand, because, in the mixer, the very thin films of bitumen covering the hot-sand grains are readily and quickly scorched by the excessive heat in the sand.

34. Refined Asphalt and Fluxing Oil.—Unless otherwise notified by the Chief Engineer you will assume that the stock of refined asphalt on hand at the beginning of the work has been inspected and is satisfactory. You will, however, note the appearance of the material and the character and marking of the barrels or packages, and will not permit the use of any new shipments of materials of different appearance or brand without authority from the Chief Engineer. The above instructions apply also to the oil used for fluxing.

35. Ratio of Asphalt and Flux.—You will frequently note and record the weight of asphalt and of flux used in charging the melting tanks.

36. Temperature in Melting Tanks.—The melting kettles are usually equipped with fixed thermometers, but their reading should be frequently checked with your detached tank thermometer. You will see that the temperatures in the kettles are kept within the limits named in the specifications. See that the melted asphaltic cement is kept constantly agitated as required by the specifications.

37. Uniformity of Asphaltic Cement.—It is very important that the asphaltic cement shall be of uniform composition and consistency, or hardness.

When the composition and consistency of the asphaltic cement to be used for the surface-course of any street has been determined upon and approved by the engineer, you will take out and preserve a sufficiently large quantity to be used thereafter as a standard, and each subsequent tank of cement, before it is used, should be tested by comparing it with this standard in the following manner, using the flow-plate apparatus:

Melt and fill two cartridges with the standard cement, and two with the cement to be tested, marking them for identification. When cold, carefully remove with a wetted dull knife any surplus cement from the ends of the cartridges so as to leave them exactly full and the metal ends clean. Immerse them in cold water until they are all of the same temperature. Then place and fasten these filled cartridges on the grooved plate with their lower ends exactly to the zero line on the plate, the standard samples alternating with the new. Then place the plate, at an inclination of about 45°, in front of a source of uniformly distributed heat, as, for instance, near a steam boiler or large steam pipe, or (when the weather is favorable) in the sunshine, facing the sun. Leave the plate in this position until the bitumen in the cartridges shall have melted and flowed down the grooves an average of from four to five inches. Then measure the lengths of flow of each from the zero line on the plate. If the average flow of the new samples differs more than 5 per cent. from that of the standards, the new cement should be regarded as unsatisfactory and should be corrected by adding more asphalt or flux, as may be required.

(If a penetration apparatus is supplied or is available, the penetration method may be used instead of this flow-method for determining the consistency of the cements. Proper instructions for its use will accompany the apparatus.)

38. Ratio of Sand and Cement.—When the proper ratio of sand and asphaltic cement has been determined for any street you will see that this ratio is carefully adhered to. The correctness of the weighing scales used should be frequently tested.

39. Mixing.—When the sand and asphaltic cement are properly mixed the appearance of the mass will be perfectly uniform throughout, with every grain of sand entirely and evenly coated with cement. The mixing should, however, be continued somewhat beyond the attainment of this condition, so as to insure thoroughness. After the proper result has been arrived at, either the time in the mixer, or the number of revolutions of the mixer shaft should be noted and the standard thus determined substantially adhered to thereafter. With the standard mixers commonly used, the hot sand and the filler (dust) should first be put into the mixer and mixed for about fifteen seconds; then the asphaltic cement added and the mixing continued as long as necessary (in the usual mixer not less than sixty seconds).

40. Records.—You will keep complete records of the results of your observations and tests in a book which will be provided for the purpose, and will make such reports to the Engineer as he may direct.

41. Inspection on the Street.—The leading things to be kept in mind by the street inspector, in the laying of asphalt pavement on the street, are the following:

a. Temperature of mixtures when applied to the street. b. Proper preparation of the street surface before material is laid. c. Laying and rolling of the binder-course. d. Laying of the surface-course. e. Rolling the surface-course.

42. Inspector’s Equipment.—The inspector will be supplied with the following apparatus:

1 armored thermometer reading from 200° F. to 500° F. 1 graduated spatula. 1 twelve-foot straight-edge. 1 fifty-foot tape line.

43. Temperature of Mixture.—If proper care has been taken at the mixing plant the mixture will not arrive on the street at too high a temperature, and your principal care will be to see that it is not laid at too low a temperature. The minimum temperature named in the specifications should be adhered to. While the main or interior mass of a wagon load may be well above that temperature, the top and outer part of the load may be, particularly in cold weather, too cold to be safely used. Some of this colder portion may usually be sufficiently reheated by mixing it with the hotter material, if properly handled in unloading; but any material that is so cold as to be lumpy when unloaded, or, more particularly, when being raked out, should be discarded. This applies to both surface and binder mixtures.

It must not, however, be overlooked that the different kinds of asphalts have different appropriate working temperatures, and for some asphalts the minimum temperature named in the specifications may be too low. The best practical guide is the manner in which the mixture behaves in raking. It must always be so hot that it will, under the rake, break up into a uniform, crumbling or powdery mass. If it does not do this it is (unless the mixture is excessively rich in bitumen or improperly compounded) too cold.

44. Preparation of Street Surface.—Before the binder-course is laid, all loose material, rubbish, street dirt and other matter foreign to the concrete surface must be removed and the concrete surface swept, if necessary, to properly clean it, with street brooms. Neither binder nor surface mixture shall be laid upon wet surfaces. Before the spreading of the surface mixture on the binder the latter must be cleaned of all foreign matter and, if necessary, swept. If the binder is covered with mud from wagons or other travel, the surface must be scrubbed clean. Any part of the binder-course that may have become broken or loosened before the surface-course is applied must be taken up and new material laid in its place with the same care as the original.

45. Laying Binder-course.—The binder mixture must be carefully spread and raked to such thickness that after being rolled it will present an even, true surface not varying more than one-fourth inch from the intended finished surface of the binder. The tendency is to lay the binder-course carelessly and to roll it insufficiently. Nearly the same care in raking and rolling as for the surface-course, should be insisted upon. If the binder is not thoroughly compressed before it becomes cold it is likely, in future hot weather, to soften and yield under heavy travel and thus to start depressions in the pavement which will increase with time.

46. Laying the Surface-course.—The requirements of the specifications should be rigidly enforced in the laying of the surface-course. Joints against a cold edge of previously laid surface must be cut back until solid, fully compressed material of full thickness is reached, and the raw edge completely but thinly painted with liquid paving cement or pitch. No masses or fragments of cold mixture, whether of binder or surface, must be allowed to remain on the surface of the binder in advance of the placing of the surface-course, to be covered up by the latter. Such cold masses will not be compressed by the roller, but will later, under a hot sun and heavy travel, yield and start depressions in the pavement. The raking out requires to be properly and skilfully done. The tines of the rakes must penetrate to the binder, so that the raked material will be a uniform mass from top to bottom.

47. Rolling.—You will insist upon the rollers being placed upon the freshly raked surface just as soon as the material will bear them without being squeezed out or displaced laterally. The tendency is to keep the rollers off too long, thus permitting the chilling of the surface and preventing its proper compression. Do not take the contractor’s word as to how soon the rolling may be begun, but have trials made until you are able yourself to judge. The rolling by the heavy roller should be very thorough: keep the roller at work constantly until the surface is too cold to be impressed. In operating the roller lengthwise of the street begin at the gutters and work toward the center of the street. Cross rolling and diagonal rolling must be insisted upon wherever the width of the street will permit it.

48. Proper Thickness and Surface.—While the completed surface is still warm enough to permit it, measure the thickness of the surface-course by forcing the graduated spatula through it to the binder and noting the depth of penetration. Also test the trueness of the finished surface with the straight-edge, and if found defective in either thickness of pavement or trueness of surface, insist on more careful grading and raking on the further work. Try the completed gutters with water to see that they are so truly laid that puddles of water will not stand in them.

49. Asphalt surface must not be laid when rain or snow is falling, or so long as the street surfaces are wet. Surface mixture raked out and caught in a shower before it is well enough rolled to exclude water must be taken up and discarded.

Unless unavoidable, neither binder nor surface should be laid when the street surface or the air is below 40° F. As a rule, the lower the temperature the of air the greater is the care necessary to properly lay asphalt pavement.

50. Measure each day the area of pavement laid and record that, and the quantity (number of batches) of surface mixture used, and note any lack of uniformity in the area laid per batch.