BRICKWORK
4. In estimating the brickwork, openings have been deducted, thus practically giving “kiln count,” so that the analyses of prices given heretofore will apply. If openings had not been deducted, the prices would be 15 per cent. lower.
Pressed Brick
Cost
The cost of pressed brickwork is based on the analysis given in Estimating and Calculating Quantities, Part 1, and is $53.71 per thousand.
Summary
| From the preceding estimate of quantities, the | |
| number of pressed brick laid is 5,041, which, | |
| at $53.71 per M, will cost | $270.75 |
| Pressed brick, not laid, 252, at $30 per M | 7.56 |
| Total cost of pressed brickwork | $278.31 |
Common Brick
Cost
The cost of the common brickwork is based on the analysis given in Estimating and Calculating Quantities, Part 1, and is $16.68 per thousand for lime-cement mortar.
Summary
| According to the estimate of quantities, | |
| the number of common brick laid is 46,303, | |
| which, at $16.68, will cost | $ 772.33 |
| Common bricks, not laid, 2,315, at $8 | 18.52 |
| Molded brick and terra-cotta cap for rear chimney | 10.00 |
| Total cost of common brickwork | $ 800.85 |
| Recapitulation of Cost of Brickwork | |
| Pressed brickwork | $ 278.31 |
| Common brickwork | 800.85 |
| Total cost of brickwork | $1,079.16 |