EXCAVATION

2. In calculating the cubic yards of earth excavated for the cellar, all measurements are taken from the foundation plan and the sections. The plan is blocked out as shown in the accompanying Cellar Plan, and the area of each block found; then, by multiplying the sum of these partial areas by the depth of the cellar, the cubic contents is determined. The trenches for the foundation walls of porches and for the footings of cellar walls are calculated separately, as also are the excavations for piers, drains, cesspools, area, etc.

Cellar Excavation

Square
Feet
Cubic
Feet
Quantities
Block A, 23' 4" × 16' 4" 381.0
Block B, 14' 6" × 20' 10"302.0
Deduct 4" × 3' 0"1.0
Add for projection of wall, (13' 6" + 7') ÷ 2 × 3' = 30.8331.8
Block C, 27' 6" × 17' 5"479.0
Deduct for breaks in wall, 1' 7" × 6' 8" and 2' 6" × 3'18.0461.0
Block D, 26' 6" × 10' 5½" 277.2
Block E, 16' 8" × 11' 6½"192.4
Deduct for breaks in wall, 6' 6" × 1' 11" and 3' × 5" 13.7178.7
[2] Block F, 9' 10" × 9' 7½" ÷ 2 47.3
[3] Block G, 14' × 14' × .7854 ÷ 277.0
Deduct for portion of semicircular part,
included in F, 12" × 14' approximately14.0 63.0
Total area of excavation 1,740.0
Contents, 1,740 sq. ft. × 6.5 ft. (depth) 11,311.0

Excavation for Wall Footings [4]

Square
Feet
Cubic
Feet
Quantities
a b, 26' × 2' 6"65.0
b c, 5' 6" × 3'16.5
c d, 9' 9" × 2' 6"24.4
d e, 17' 6" × 2' 6"43.7
e f, 27' 4" × 2' 6"68.3
f g, 9' 2" × 3' 8"33.6
g h, 21' × 2' 6"52.5
i j, 27' 7" × 2' 6"69.0
j a, 31' × 2' 6"77.5
k l, 20' 2" × 2' 6"50.4
Chimney, 12' 6" × 4' (approximately)50 
Deductions10.439.6
q r, 16' 4" × 1' 10" 29.9
r s, 9' 2" × 1' 10"16.8
m n (less openings), 7' 9" × 2' 6"19.4
o p, 20' × 1' 10"36.7
Total area of excavation for footings643.3
Contents, 643.3 sq. ft. × 10 in. (.833 ft.) depth 535.9

Miscellaneous Excavations [5]

Cubic
Feet
Quantities
Front porch, 69' 9" × 2' 3" × 3'470.8
Back porch, 24' × 2' 4" × 3'168.0
Piers for steps, 1' 8" × 2' × 3' × 220.0
Piers for side steps and back porch, 2' × 2' × 3' × 448.0
Cellar area, 5' 9" × 6' 4" × 6' 6"236.7
Deduct 2' × 3' × 6' 6"39.0197.7
Dry cesspool, 6 ft. diameter × 6 ft. depth 169.6
Cesspool, 6 ft. diameter × 8 ft. depth226.2
Trench for pipe to cesspool, 25' × 7' 6" × 2'375.0
Trench for drain pipes (roof drainage), 228' × 3' × 1'684.0
Trench for drain pipes from junction to dry cesspool,
 20' × 3' × 18"90.0
Total2,449.3
Grand total of excavation14,296.2

Filling

Cubic
Feet
Quantities
Around foundation walls, 181' 2" × 6" × 6' 6"588.8
Around foundation of porches, etc., 142' 3" × 6" × 3'  213.4
Total filling802.2

Cost

The cost of excavation in sandy soil, taken from Estimating and Calculating Quantities, Part 1, is 53 cents per cubic yard. The cost of filling, including tamping, may be taken as about one-third that of excavation, or, say, 18 cents per cubic yard.

Summary

Excavation, 14,296.2 cu. ft. = 529.5 cu. yd.,
at 53 cents per cubic yard$280.64
Filling, 802.2 cu. ft. = 29.7 cu. yd.,
at 18 cents per cubic yard5.35
Total cost of excavation and filling$285.99