PAINTING
14. In taking off quantities for painting, it is customary to estimate the cost by assuming a price per square yard for each class of work, instead of estimating the material and labor separately.
Exterior Work
Interior Work
Quantities
Chestnut finish, parlor, library, dining room, hall, stair hall, lavatory, and stairway. One coat of wood paste filler, one coat of white shellac, and three coats of varnish, rubbed down with pumice stone and water:
| Square | |
| Yards | |
| Architrave | 32 |
| Base | 16 |
| Wainscoting | 30 |
| Sash | 17 |
| Doors | 54 |
| Jamb casings | 7 |
| Stairway | 50 |
| Balustrade of stairway | 20 |
| Total | 226 |
White pine, natural finish, all of house not finished in chestnut. One coat of spirit shellac and two coats of varnish:
| Square | |
| Yards | |
| Architrave | 73 |
| Base | 60 |
| Wainscoting | 29 |
| Sash | 40 |
| Dresser | 9 |
| Doors | 131 |
| Jamb casings | 31 |
| Back stairs | 34 |
| Total | 407 |