TEXAS CREEK PIPE AND AQUEDUCT.

A description of this work will be of interest in showing the general practice followed in California for carrying water across deep mountain gorges. In order to augment its water supply, the North Bloomfield Gravel Mining Company desired to conduct water from a stream known as Texas Creek, in Nevada County, California, across the Big Cañon branch of the South Yuba River into the main Bloomfield flume or aqueduct, which was located on the side of Big Cañon Creek, at a vertical elevation of 620 feet above the bed of the latter stream. The quantity of water to be carried was about 32 cubic feet a second (1,250 miner's inches), which could be diverted from Texas Creek at a point 480 feet vertical above the Bloomfield flume. An aqueduct about 4,000 feet long, partly of ditch and partly of flume, was needed to bring the water from the catchment dam on the creek to the brow of the gorge. The vertical head for the pipe could therefore be from a maximum of 460 feet down to any lesser head; with a head of 460 feet, the pipe would be 4,790 feet long; and with a head of 220 feet, the length would be 4,290 feet. Assuming a maximum tensile strain upon the iron of 16,500 pounds per square inch, with the formula for the greatest head of about

and a lower value of the coefficient in the last equation for the lesser heads, it was found, by calculation, that the least cost could be obtained with a head from 300 to 350 feet. The head fixed upon was 303.6 feet, with a length of 4,438.7 feet. A profile of the pipe, with nearly the same horizontal and vertical scales (horizontal scale, showing slope lengths), is given in Fig. 14; details are given in Figs. 15 and 16. The pipe was of double riveted sheet iron, made in lengths of about 20 feet, and of the following thicknesses:

1,349linear feet,0.083inch thick.
220"0.095"
240"0.109"
250"0.120"
320"0.134"
610"0.148"
1,450"0.165"

Some of the iron was of the very poorest quality; the pipe was made by contract in San Francisco, without the supervision of an inspector, as the contractors were a firm of good reputation; the bad quality of the iron was not detected until too late to have it corrected. Since then, the writer has always had such pipes—the mines of which he has been the manager using large quantities—made directly on the ground where they are to be used; the pipe makers, in the latter case, always reject such sheets as are too much below in thickness the standard gauge, and those which show in passing through the rolls the bad quality of iron; tests of each joint by hydrostatic pressure would add too much to the cost.

FIG. 16.

The maximum tensile strain upon each of the seven thicknesses of iron used was intended to be 16,500 pounds per square inch. Some of the sheets were below the standard gauge, so that, in reality, the tensile strain is sometimes as high as 18,000 pounds. The mean diameter of the pipe was 1.416 feet. The entrance into the pen-stock was tapered, so that the coefficient of contraction was about 0.92. For pressures not exceeding say 380 feet, the joints were put together stove-pipe fashion. For greater pressures, the joints were made by an inner sleeve riveted on one end of the joint, with an outer lap-welded band, as shown by Fig. 15; lead was run into the space between the outer band and the pipe, and then tightly driven up by calking-irons. The pipe was laid under the bed of the Big Cañon Creek, a large stream when in freshet, where the head below the hydraulic grade line was 760 feet. Some of the lead joints leaked slightly at first, but this was soon remedied by more careful calking. No man-holes or escape-gates were used. The pipe for the larger part of the year is not filled at its upper end; when such is the case, the water at the inlet carries down the pipe a great quantity of air, for which escapes must be provided to prevent a jarring or throbbing, which would soon destroy the pipe. The escape air-valves used are shown by Fig. 16. They consist simply of a heavy flap valve of cast-iron, with recess for lead filling to give greater weight set on top the pipe, seating on a vulcanized rubber cushion, and swinging on a loose hinge. When the pipe is only partly filled with water, the valves drop down by their own weight, allowing the air to freely escape; when the water rises above the level of a valve, it is tightly closed by the resulting pressure. There are fourteen of these valves, those on the lower end being designed to allow air to freely enter the pipe in case it should burst in the deeper portion, and thus prevent any collapse from atmospheric pressure. The valves have answered the desired purposes most effectually. The pipe was hauled over a road built to the inlet end, and shot down the mountain side by means of a V-shaped trough of wood. For the lower end, the joints were hauled up the cliff side into place by a crab worked by horse-power. On steep inclinations, the pipe was held firmly in place by wire ropes fastened to iron pins in the solid rock, as shown by the sketch. The covering of earth and stone was 1 foot to 2 feet in depth; with steep slopes, the earth was kept from sliding by rough dry walls, or by cedar plank placed crosswise. The pipe was laid in 1878; the first year it broke twice, owing to the wretched quality of the iron; since then, it has given no trouble, and has required practically no attention. The cost of this work—ditch and flume 4,000 feet, and pipe 4,440 feet—was $23,779.53.

A comparison of the relative values of n, in the formula v = n (r s)½, for the foregoing ditch, flume, and pipe will be instructive. The ditch has a width on the bottom of 3 feet, on the top of 6 feet, with a depth of 3 feet, and an inclination of 20 feet per mile; its sides are rough, being cut in part through the rock and with sharp curves, although fairly regular; with a flow of about 1,300 miner's inches (32.8 cubic feet per second) the ditch runs about full.

Therefore:

Q = 32.8, hence

and

The flume is of unplaned boards, rectangular, 2.67 wide X 2.83 deep, with an inclination of 32 feet per mile. There are sharp curves, although these were made as regular as practicable; the boiling action of the water passing around these curves brought the flow line (Q = 32.8) nearly up to the top of the sides; with a straight flume of the same size, the water would have doubtless stood several inches lower.

Therefore:

a = 2.67 × 2.83 = 7.56 ;

Q = 32.8, hence

and n = 59.

With the pipe,[[6]] 1.416 diameter,

Allowing for loss of head due to imparting velocity to water, and for contraction,

We hence have the following values of n, in v = n (r s)½, Q being constant:

Rough ditch, with sharp curves.33
Rectangular flume, with sharp curves.59
Wrought-iron pipe, with easy curves, coated with asphalt, but with rivet-heads forming noteworthy obstructions (m = 65.5, and 2m = n)131

[6]

Vide pages 120-122, Transactions American Society of Civil Engineers for 1883.