CHAPTER V
THE MURGHAB VALLEY RAILWAY
STREET SCENE, ANDIJAN
The Russian Government has shown remarkable energy during the past few years in improving its railway communications in Central Asian regions. After the Trans-Caspian line had been finished from the Caspian Sea to Samarkand there was a lull in construction, but presently an extension was carried on to Tashkent and thence to Andijan. By creating railway communication with Merv, Russia met half-way the difficulties of her station in Trans-Caspia. In the event of any military crisis arising with Afghanistan 300 versts of difficult country yet remained to be crossed before concentration upon that frontier could be effected. At a later date, a branch was run from Merv to Pendjeh, by which this hiatus was at once repaired and Russia secured to herself a position of commanding importance across the road to Herat.
Surveys, carried out in the year 1894 in two directions, from the station of Tejend and from Merv, demonstrated that the Merv-Murghab route did not present any technical difficulties. Shorter than the Tejend line by 65 versts and more level, it traversed the well-populated Merv, Yulatan and Pendjeh oases. Water was also plentiful. On the other hand the line from Tejend crossed very difficult country; while it doubled the distance, necessitating 700,000 cubic sagenes’ additional excavation. Perhaps a more emphatic objection arose from the inadequacy of water between Tejend and Sarakhs, supplies in the Tejend district drying up between September and January. As a consequence the line was constructed from Merv to Kushkinski Post, on the Afghan frontier, through the valleys of the Murghab and Kushk rivers, just over 293 versts or 192 miles in length, with a terminal depôt only 80 miles distant from Herat. From motives of economy one station was allowed to every 50 versts, with sidings half-way between them; only two engine sheds and workshops were provided, while all other buildings were limited and none but the cheapest materials employed. Bridges were made of wood instead of stone, the rolling-stock sufficing for four trains in the twenty-four hours. Railway and military telegraph wires were fixed to the same posts and it was not intended to ballast the permanent way. Construction was reduced by these precautions to 8,408,000 roubles. After revision by a commission of the General Staff this sum was increased by the cost of ballasting the permanent way, 329,000 roubles; the total expenditure upon the work finally amounting to 9,669,000 roubles or 33,000 roubles per verst.
Imperial ukase authorised construction on August 26, 1896, actual work beginning on April 27, 1897.