In the case of the concreting, inability to purchase a hoist and motor and the high cost of renting the same, together with the delays mentioned, added greatly to the unit cost.

When it is considered that the cost of plastering covers that of four coats over the entire inside of the tank and three more over about one-third of it, it does not appear so high, especially in view of the high rate of wages paid.

The cost per yard for concrete alone was $25.126, and this is probably about 25% in excess of the cost of the same class of work executed under more favorable conditions as to location, weather conditions, etc.

TABLE 1.—Cost of High-Level Tower, Victoria Water-Works. (412 cu. yd.)

Total Cost. Unit Cost.
Rate per hour. Amount. Complete. Labor.Material.
Preliminary Work:
Labor, Carpenter$0.50$11.00
Labor 0.344 64.94
" 0.281 249.67 $325.61 $0.790
Material 133.62 133.62 $0.324
Forms:
Buildings, shifting and stripping:
Labor, Carpenter 0.501,832.99
Labor 0.344 80.85
" 0.281 563.84 2,477.68 6.014
Material:
Lumber 583.49
Hardware 325.51
Miscellaneous 13.90 922.90 2.240
Scaffold:
Erecting and tearing down:
Labor, Carpenter 0.50 693.00
Labor 0.344 350.59
" 0.281 117.27 1,160.86 2.818
Material:
Lumber 487.77
Hardware 202.79 690.56 1.676
Concreting:
Labor 0.50 142.00
" 0.344 11.00
" 0.281 947.81 1,100.81 2.672
Material:
Rock 317.30
Sand 385.72
Cement 1,581.97
Motor and Hoist:
Rental 406.56
Power 83.53 2,735.08 6.638
Plastering (3,000 sq. ft.):
Labor, Plasterers 0.75 116.50
Labor 0.46-7/8 15.00
" 0.37-1/2 198.52
" 0.281 105.66 435.68 14.52 per sq. ft.
Material:
Sand 8.64
Cement 66.10
Alum and Potash 16.00 90.74 3.25 per sq. ft.
Cement Wash (8,560 sq. ft.):
Labor 0.48-3/4 50.00
" 0.281 47.68 97.681.14 per 100 sq ft.
Material:
Cement 15.18 15.18 0.18 " " " "
Windows, doors, and scuttle:
Labor 0.50 49.00 49.00
Material:
1 door, 7 windows, etc. 47.26 47.26
Equipment:
40% of $461.46 184.58 184.58 0.448
Superintendence 1,241.45 1.506
Steel Tank:
Labor, Carpenter$0.50 $124.24
Helper 0.344 2.75
Boiler-makers 382.57
Holders on 147.33
Labor 40.61
Foreman 0.625 186.25 $883.75$0.0441 per lb.
Material:
Tank, rivets, etc. (20,000 lb.) 1,740.69 $0.0875
Iron-work:
Spiral stairway, inlet, and overflow pipes, ventilator, reinforcing steel, etc.:
Labor, Machinists 0.50 89.50
Helper 0.344 240.16
Labor 0.281 100.79 430.45
Material 1,814.71 1,814.71
Total $16,578.29


DISCUSSION

Maurice C. Couchot, M. Am. Soc. C. E. (by letter).—It appears to the writer that in the design of this structure two features are open to criticism. The first is that such a high structure was built of plain concrete without any reinforcement. Even if the computation of stresses did not show the necessity for steel reinforcement, some should have been embedded in the work. As a matter of fact, the writer believes that, with the present knowledge of the benefit of reinforced concrete, a structure such as this should not be built without it. This applies mainly to the tower below the tank.

The second feature, which is still more important, refers to the insertion of a shell of smooth steel plate to take the stresses due to the hydrostatic pressure, and also to insure against leakage in the walls of the tank. The 6-in. shell of plain concrete outside the steel shell, and the 3-in. shell inside, do not work together, and are practically of no value as walls, but are simply outside and inside linings. Although the designer provided lugs to insure the adhesion of the concrete to the plate, such precaution, in the writer's opinion, will not prevent the separation of the concrete from the smooth steel plate, and, at some future time, the water will reach and corrode the steel. It would have been better to have reinforced the wall of the tank with rods, as is generally done. The full thickness would have been available, and less plastering would have been required. Furthermore, the adhesion of concrete to a smooth steel plate is of doubtful value, for, in reinforced concrete, it is not the adhesion which does the work, but the gripping of the steel by the concrete in the process of setting.