The Manitoba system gridirons north Minnesota, runs to Duluth, puts two tracks down the Red River Valley (one on each side of the river) to the Canada line, sends out various spurs into Dakota, and operates a main line from Grand Forks westward through the whole of Dakota, and through Montana as far as the Great Falls of the Missouri, and thence through the canon of the Missouri and the canon of the Prickly-Pear to Helena—in all about 3000 miles of track. Its president is Mr. James J. Hill, a Canadian by birth, whose rapid career from that of a clerk on the St. Paul levee to his present position of influence, opportunity, and wealth is a romance in itself, and whose character, integrity, tastes, and accomplishments, and domestic life, were it proper to speak of them, would satisfactorily answer many of the questions that are asked about the materialistic West.

The Manitoba line west had reached Minot, 530 miles from St. Paul, in 1886. I shall speak of its extension in 1887, which was intrusted to Mr. D. C. Shepard, a veteran engineer and railway builder of St. Paul, and his firm, Messrs. Shepard, Winston & Co. Credit should be given by name to the men who conducted this Napoleonic enterprise; for it required not only the advance of millions of money, but the foresight, energy, vigilance, and capacity that insure success in a distant military campaign.

It needs to be noted that the continuation of the St. Paul, Minneapolis, and Manitoba road from Great Falls to Helena, 98 miles, is called the Montana Central. The work to be accomplished in 1887 was to grade 500 miles of railroad to reach Great Falls, to put in the bridging and mechanical structures (by hauling all material brought up by rail ahead of the track by teams, so as not to delay the progress of the track) on 530 miles of continuous railway, and to lay and put in good running condition 643 miles of rails continuously and from one end only.

In the winter of 1886-87 the road was completed to a point five miles west of Minot, and work was done beyond which if consolidated would amount to about fifty miles of completed grading, and the mechanical structures were done for twenty miles west from Minot. On the Montana Central the grading and mechanical structures were made from Helena as a base, and completed before the track reached Great Falls. St. Paul, Minneapolis, and Duluth were the primary bases of operations, and generally speaking all materials, labor, fuel, and supplies originated at these three points; Minot was the secondary base, and here in the winter of 1886-87 large depots of supplies and materials for construction were formed.

Track-laying began April 2,1887, but was greatly retarded by snow and ice in the completed cuts, and by the grading, which was heavy. The cuts were frozen more or less up to May 15th. The forwarding of grading forces to Minot began April 6th, but it was a labor of considerable magnitude to outfit them at Minot and get them forward to the work; so that it was as late as May 10th before the entire force was under employment.

The average force on the grading was 3300 teams and about 8000 men. Upon the track-laving, surfacing, piling, and timber-work there were 225 teams and about 650 men. The heaviest work was encountered on the eastern end, so that the track was close upon the grading up to the 10th of June. Some of the cuttings and embankments were heavy. After the 10th of June progress upon the grading was very rapid. From the mouth of Milk River to Great Falls (a distance of 200 miles) grading was done at an average rate of seven miles a day. Those who saw this army of men and teams stretching over the prairie and casting up this continental highway think they beheld one of the most striking achievements of civilization.

I may mention that the track is all cast up (even where the grading is easy) to such a height as to relieve it of drifting snow; and to give some idea of the character of the work, it is noted that in preparing it there were moved 9,700,000 cubic yards of earth, 15,000 cubic yards of loose rock, and 17,500 cubic yards of solid rock, and that there were hauled ahead of the track and put in the work to such distance as would not obstruct the track-laying (in some instances 30 miles), 9,000,000 feet (board measure) of timber and 390,000 lineal feet of piling.

On the 5th of August the grading of the entire line to Great Falls was either finished or properly manned for its completion the first day of September, and on the 10th of August it became necessary to remove outfits to the east as they completed their work, and about 2500 teams and their quota of men were withdrawn between the 10th and 20th of August, and placed upon work elsewhere.

The record of track laid is as follows: April 2d to 30th, 30 miles; May, 82 miles; June, 79.8 miles; July, 100.8 miles; August, 115.4 miles; September, 102.4 miles; up to October 15th to Great Falls, 34.0 miles—a total to Great Falls of 545 miles. October 10th being Sunday, no track was laid. The track started from Great Falls Monday, October 17th, and reached Helena on Friday, November 18th, a distance of 98 miles, making a grand total of 043 miles, and an average rate for every working-day of three and one-quarter miles. It will thus be seen that laying a good road was a much more expeditious method of reaching the Great Falls of the Missouri than that adopted by Lewis and Clarke.

Some of the details of this construction and tracklaying will interest railroad men. On the 16th of July 7 miles and 1040 feet of track were laid, and on the 8th of August 8 miles and 60 feet were laid, in each instance by daylight, and by the regular gang of track-layers, without any increase of their numbers whatever. The entire work was done by handling the iron on low iron cars, and depositing it on the track from the car at the front end. The method pursued was the same as when one mile of track is laid per day in the ordinary manner. The force of track-layers was maintained at the proper number for the ordinary daily work, and was never increased to obtain any special result. The result on the 11th of August was probably decreased by a quarter to a half mile by the breaking of an axle of an iron car while going to the front with its load at about 4 p.m. From six to eight iron cars were employed in doing this day’s work. The number ordinarily used was four to five.