Training or canalising should not be effected in any reach of a stream without regard to other reaches. A mere local lowering of the water-level by dredging may accentuate the effect of a shoal at the upper end of the reach.

When the water-level is raised by a weir or by narrowing the channel—though in the latter case the raising may not be permanent—it is generally best to commence the work from the upstream end. The raising of the water-level will then not interfere with the execution of the rest of the work. But in a case of widening, where the water-level upstream of the work is lowered, the work can conveniently be begun at the downstream end, and the remark applies also to a case of straightening, provided that the new channel is not so small that it at first causes no lowering. In any case in which there is a doubt whether the whole of the scheme will be carried out, the reach to be dealt with first can be decided on according to circumstances. There is no general reason for selecting an upstream or downstream reach, except that any raising or lowering of the water-level will extend upstream of the reach and not downstream of it ([Chap. I., Art. 4]).

Training walls and groynes, if made with stakes or fascines or any materials except stone, require careful watching and maintenance.

CHAPTER IX
CANALS AND CONDUITS

1. Banks.—All banks which have to hold up water should be carefully made. The earth should be deposited in layers and all clods broken up. In high banks the layers should be moistened and rammed. The dotted lines in [fig. 29] show two possible courses of percolation water. The vertical height—from the water-level to the ground outside the bank,—divided by the length of the line of percolation is the hydraulic gradient, as in the case of a pipe, and this gradient is more or less a measure of the tendency to leakage. A bank which has water constantly against it nearly always becomes almost water-tight in time. The time is less or greater according as the soil is better, and according to the amount of care with which the bank is made.

Fig. 29.

The side slopes of banks vary with the soil. Generally they are 1½ to 1, but they are sometimes 2 to 1 or even 3 to 1 if the soil is bad or sandy, or if great precautions against breaches are to be taken.

Leakage can sometimes be stopped by throwing chaff or other finely divided substances into the water at the site of the leak. In other cases it is necessary to dig up part of the bank, find the channel by which the water is escaping, and fill it up by adding earth and ramming. On some navigable canals in France it was at one time the custom to lay the reach dry, when a bad leak occurred, and to dig away the bank and lay slabs of concrete or puddle over the place. This plan was abandoned, and instead of it sheet piles are driven in. They are then withdrawn one at a time and, if any leakage occurs, the space is filled with concrete.

The dimensions of a bank should depend to some extent on the head of water against it and on the volume of the stream whose water it holds up. A breach is obviously more serious the greater the volume of the escaping water. This volume depends on the size of the stream and on its velocity. In navigation canals in England the bank on the side opposite the towing-path is usually 4 to 6 feet wide and 1½ feet above the water. In irrigation canals in India the bank of a very large canal is 2 feet above the water and 20 feet wide, while that of a small canal with 6 feet of water is 8 or 10 feet wide and 1½ feet above the water, and that of a small distributary channel with 3 feet of water is 4 feet wide and 1 foot above the water. The soil is often poor.