The great majority of river cities which have undertaken modern improvements on their water fronts have had to deal with more or less serious flood problems, and the complex and varying conditions of each river have had an important influence on the design of the embankment. The technical problems involved in the control of rivers are among the most complex and baffling with which the engineering profession has to deal, and any attempt to forestall the investigations of the Flood Commission, by definite plans for permanent improvements on the water front, would be folly. Nevertheless, the experience of hundreds of cities and the work of thousands of engineers have developed certain types of treatment, one or more of which, with suitable local modifications, will pretty surely appear in the final solution of the Pittsburgh problem. Subject, therefore, to the conclusions of the Flood Commission, a satisfactory development of the Pittsburgh wharf may be expected to include the following features.

First, there should be an amply wide water-front street, presumably formed by extending Water Street and Duquesne Way over the upper part of the present sloping bank. Second, the outer sidewalk of this street should become at most points a tree-shaded promenade, of such width and with such equipment of benches and other features for public recreation as the circumstances permit, so arranged that the people using it will neither be in the way of the transportation activities nor be annoyed or endangered by them, and so designed that the people can enjoy to the full the natural beauty of the river valley and the always interesting activities of which it is the stage. Third, there should be next the water a commercial quay, substantially level, of adequate but not unnecessary width, and accessible from the streets by inclined roads of reasonable gradient, parallel with the river, in place of the present excessive slopes.

In the first typical section here given is shown one such arrangement. Here, the level of the promenade is such that its solid parapet rises above the maximum flood level. This is of a type adopted for rivers that are subject to occasional excessive floods, as at Pittsburgh. It assumes the embankment to be made water-tight; the sewers and drains to be provided with proper back-pressure gates, and the openings from the streets, through the promenade and its parapet to the commercial quay, to be arranged for prompt damming on the rise of the water above the danger level. Thus would the entire business district be protected from floods, not only on the surface but also in the basements. The quay shown on this section is supposed to be at a level just above ordinary navigable stages, and to be equipped with power cranes for direct loading and unloading between steamers or barges, tied up at the quay, and wagons upon it. Provision could also be made for a freight track running in alongside the cranes for transfer between cars and vessels (if thought desirable), in addition to the facilities provided on railroad property. Alongside the quay, floating landing-stages for packets and so forth, reached by gang-planks or bridges, would be provided as at present, but in a more decent and commodious style.

Typical section for the water front. The parapet along the promenade would be above extreme flood height; the commercial quay would be at a lower level, flooded at very high water, but above all ordinary river stages.

Alternative section for the water front, suggesting a floating commercial quay that would rise and fall with the river. Large cranes could transfer freight directly from the boats to trucks at the street level. At certain places roadways would cut through the promenade to provide access to ramps leading down to the quays and to provide places for freight trucks to stand while being loaded and unloaded.

This section is of a type tested by practical experience and is clearly a great improvement upon the present primitive conditions. But it is open to two objections: first, that the quay is flooded at intervals, although so designed as to suffer no injury and to be put out of commission only when the river is practically closed to navigation by the height of the flood; and, second, that at low water, that is to say "pool full," it is not at the most convenient height.