The name of "Basket Frame" would convey a better impression, but the name "Balloon" has long ago outlived the derision which suggested it.

Fig. 109.—Elevation Section—manner of nailing—A. corner stud, 4 by 4—B. joist, 3 by 8—C. stud, 2 by 4.

Fig. 110.—D. Upper Edge of Joist—E. Stud.

The moment the foundation is prepared, and the bill of lumber on the ground, the balloon frame is ready to raise, and a man and boy can do all of it. The sills are generally 3 inches by 8 inches, halved at the ends or corners, and nailed together with large nails. Having laid the sills upon the foundation, the next thing in order is to put up the studding. Use 4 by 4 studs for corners and door posts, or spike two 2 by 4 studs together, stand them up, set them plumb, and with stay laths secure them in position. Set up the intermediate studs, which are 2 by 4 inches, and 16 inches between centres, toe or nail them diagonally to the sill. Then put in the floor joists for first floor, each joist to be placed alongside each stud, and nailed to it and to the sill. Next measure the height to ceiling, and with a chalk line mark it around the entire range of studding; below the ceiling line notch each stud one inch deep and four inches wide, and into this, flush with the inside face of the studding, nail an inch strip four inches wide. This notch may be cut before putting up the studs. If the frame be lined on the inside, it will not be necessary to notch the strip into the studs, but simply to nail it to the studding; the object of notching the studding is to present a flush surface for lathing, as well as to form a shoulder or bearing necessary to sustain the second floor; both of these are accomplished by lining inside the studding—(for small barns and outbuildings that do not require plastering, nail the strip 1 by 4 to the studding)—on this rests the joists of the second floor, the ends of which come flush to the outside face of the studding, and both ends of each joist are securely nailed to each stud; the bearing of the joist on the inch strip below is close by the stud, and the inch strip rests on a shoulder or lower side of the notch cut to receive it. This bearing is so strong that the joists will break before it would yield. Having reached the top of the building, each stud is sawed off to an equal height; if any are too short they are spliced by placing one on top of the other, and nailing a strip of inch board on both sides. The wall plate, 2 by 4 inches, is laid flat on top of the studding, and nailed to each stud; the rafters are then put on; they are notched, allowing the ends to project outside for cornice, &c. The bearing of each rafter comes directly over the top of each stud, and is nailed to it.