That iron-work lying under ground has been completely covered with cement grout, as this is found by the above-named engineer to be an effectual guard against oxidation.

Engineers wishing to study the details of the Niagara bridge, will find the final report of Mr. Roebling full of valuable matter, both as regards the making of cables, anchoring, stiffening, and the effect of passing trains.

Note.—This engineer is at present engaged upon a still greater work, namely, a railroad suspension bridge across Kentucky River, of 1,224 feet span, 300 feet above the water. There is no lower road-way in this bridge, the cross section being a triangle base upwards.

235. Note.—The Britannia tubular bridge, across the Menai Straits, is doubtless a great work, and also an enormously extravagant one. If no other structure were possible it would be admissible; but it is equalled in strength and by far surpassed in economy by Mr. Roebling’s system of trussed suspension bridges. The cost of material alone in one span of the Britannia bridge, of 460 feet, exceeds the entire cost of the Niagara bridge of 800 feet span; add to this that we are sure of the strength of wire cables, but not of tubes, and that the 800 feet span of the Niagara bridge weighs only 1,000 tons in itself against 1,400 in a 460 feet span of tube, and it will not be difficult to prove the superiority of the suspension over the tubular system; thus,

A suspension bridge of 800 feet span costs $400,000.

A tubular bridge of 460 feet span costs $500,000.

When we double the linear dimensions we increase the weight by the cube; and the cost of a tube is very nearly as the weight; whence a tubular bridge of 800 feet span will cost 2 × 2 × 2, or eight times 500,000, or $4,000,000 against $400,000. Thus,

Suspension400,0001
Tubular4,000,00010

Fig. 105.