TABLE XVIII.—ITEMIZED COST OF CONCRETING NORTH CAISSON FOR BROOKLYN TOWER OF THE WILLIAMSBURG BRIDGE:

COST OF CONCRETING CAISSON ABOVE ROOF (5,692 cu. yds.)
Materials.Quantity.Rate.Amount.
Cement6,707½ bbls.$1.57$10,531.00
Sand2,133cu. yds..40845.00
Broken stone4,938cu. yds.1.105,432.00
Water51.00
—————————————
Total5,692cu. yds.$2.96$16,859.00
Labor.
Mixing and placing5,692cu. yds.$0.73$4,159.00
Plant charges2,952.00
Plant labor517.00
—————————————
Total5,692cu. yds.$0.61$3,469.00
Total cost5,692cu. yds.$4.30$24,487.00
General expenses, 10%5,692cu. yds..432,448.00
Grand total5,692cu. yds.$4.73$26,935.00
COST OF CONCRETING SHAFTS.
Materials.Quantity.Rate.Amount.
Cement614½bbls.$1.57$965.00
Sand204cu. yds..4082.00
Stone521cu. yds.1.10574.00
—————————————
Total576cu. yds.$2.82$1,621.00
Labor.
Mixing and placing576cu. yds.1.70982.00
Plant charges, etc.576cu. yds.1.36795.00
—————————————
Total576cu. yds.$5.88$3,398.00
General expenses, 10%576cu. yds..59339.00
—————————————
Grand total576cu. yds.$6.47$3,737.00
COST OF CONCRETING WORKING CHAMBERS (1,566 cu. yds.).
Materials.Quantity.Rate.Amount.
Cement for concrete1,559bbls.$1.51$2,446.00
Cement for mortar442bbls.1.51$694.00
Sand for both630cu. yds..40252.00
Broken stone1,380cu. yds.1.101,518.00
—————————————
Total1.566cu. yds.$3.14$4,910.00
Labor.
Top labor, mixing and placing1,566cu. yds.$0.78$1,198.00
Pneumatic labor1,566cu. yds.4.917,694.00
Compressor house labor1,566cu. yds..11180.00
—————————————
Total labor1,566cu. yds.$5.80$9,072.00
Plant.
Coal at $2.40 per ton1,566cu. yds..0687.00
Concrete plant1,566cu. yds..861,352.00
Pneumatic plant1,566cu. yds..811,272.00
—————————————
Total plant1,566cu. yds.$1.73$2,711.00
—————————————
Totals1,566cu. yds.$10.67$16,693.00
—————————————
General expenses, 10%1,566cu. yds.1.061,669.00
—————————————
Grand total1,566cu. yds.$11.73$18,362.00

COST OF FILLING PIER CYLINDERS.—The following costs were obtained in mixing and placing concrete in steel cylinder piers. The sand and gravel were wheeled 100 ft. to the mixing board at the foot of the cylinder, mixed and shoveled into wooden skips, hoisted 20 ft. by horsepower and dumped into the cylinder. The foreman worked on the mixing board and the men worked with great energy. The costs were as follows:

Item—Per day.Per cu. yd.
6 men wheeling materials and mixing at 15 cts. per hour9.00$0.45
2 men dumping skips and ramming at 15 cts. per hour3.000.15
1 team and driver at 40 cts. per hour4.000.20
1 foreman at 30 cts. per hour3.000.15
————
Totals$19.00$0.95

PIERS, CALF KILLER RIVER BRIDGE.—The following methods and costs of building two new piers and extending three old piers with concrete are given by Mr. J. Guy Huff. The work was done by the railway company's masonry gangs. Figure 94 shows the arrangement of the several piers and the character of the work on each and Fig. 95 gives the detail dimensions of the three main piers.

The sand and aggregate, consisting of blast furnace slag, were unloaded from cars to platforms on a level with the top of rail, placed about 100 ft. south from the south end of the bridge. A cubical 1/6 cu. yd. mixer was used. This was operated by a gasoline engine, and was located on a platform about 50 ft. south of the south end pier. A tank near the mixer to supply water was elevated enough to get the desired head, and was kept filled by a pump run by another gasoline engine located down by the river bank. The cement house was located between the mixer platform and slag pile.

Fig. 94.—Diagram Arrangement of Piers, Calf Killer River Bridge.