With these prices and wages the average cost of concrete work for the whole line was:

Item.Per cu. yd.
Form building and removing$1.98
Mixing and placing concrete0.74
Placing reinforcement0.10
Wire, nails, water, etc.0.20
1.1 bbls. cement at $1.751.93
½ cu. yd. sand at $0.720.36
0.9 cu. yd. stone at $1.491.34
Lumber for forms0.49
———
Total$7.14

The following are the costs of specific structures built at different times:

Example I.—Indian Creek Culvert. 14×15 ft., 250 long, completed November, 1905:

Per cu. yd.
Cement$1.37
Sand.34
Stone1.10
Labor2.48
Lumber.76
Miscellaneous.18
Total$6.23

Example II.—Third Street Abutments and Retaining Wall. Completed November, 1906:

Per cu. yd.
Cement$1.78
Sand.35
Stone1.35
Lumber.74
Labor2.75
Miscellaneous.16
——
Total$7.13

Example III.—Abutments, Overhead Crossing with Union Pacific and Rock Island. Completed May, 1907:

Per cu. yd.
Cement$1.92
Sand.32
Stone1.74
Lumber.98
Labor2.96
Miscellaneous.16
——
Total$8.08