With these prices and wages the average cost of concrete work for the whole line was:
| Item. | Per cu. yd. |
| Form building and removing | $1.98 |
| Mixing and placing concrete | 0.74 |
| Placing reinforcement | 0.10 |
| Wire, nails, water, etc. | 0.20 |
| 1.1 bbls. cement at $1.75 | 1.93 |
| ½ cu. yd. sand at $0.72 | 0.36 |
| 0.9 cu. yd. stone at $1.49 | 1.34 |
| Lumber for forms | 0.49 |
| ——— |
| Total | $7.14 |
The following are the costs of specific structures built at different times:
Example I.—Indian Creek Culvert. 14×15 ft., 250 long, completed November, 1905:
| Per cu. yd. |
| Cement | $1.37 |
| Sand | .34 |
| Stone | 1.10 |
| Labor | 2.48 |
| Lumber | .76 |
| Miscellaneous | .18 |
| Total | $6.23 |
Example II.—Third Street Abutments and Retaining Wall. Completed November, 1906:
| Per cu. yd. |
| Cement | $1.78 |
| Sand | .35 |
| Stone | 1.35 |
| Lumber | .74 |
| Labor | 2.75 |
| Miscellaneous | .16 |
| —— |
| Total | $7.13 |
Example III.—Abutments, Overhead Crossing with Union Pacific and Rock Island. Completed May, 1907:
| Per cu. yd. |
| Cement | $1.92 |
| Sand | .32 |
| Stone | 1.74 |
| Lumber | .98 |
| Labor | 2.96 |
| Miscellaneous | .16 |
| —— |
| Total | $8.08 |