A full-scale temperature control model of the spacecraft went into the large space simulator on February 26. In mid-March, system tests began on both spacecraft and it was decided that the flight hardware would be tested only in the small simulator, with the temperature control model continuing in the large chamber.

Technician wears hood and protective goggles while working on Mariner spacecraft in Space simulator chamber at Jet Propulsion Laboratory, Pasadena.

On March 26, MR-1 was subjected to full-scale mating tests with the shroud (cover) and the adapter for mounting the spacecraft on top of the Agena. MR-2 was undergoing vibration tests during the week of April 16. By April 30, MR-1 had completed vibration tests and had been mapped for magnetic fields so that, once compensated for, they would not interfere with the magnetometer experiment in space.

A dummy run of MR-1 was conducted on May 7 and the spacecraft, space flight center, and computing equipment were put through a simulated operations test run during the same week.

By May 14, clean-up and final inspection by microscope had begun on MR-1, MR-2, and MR-3 (the latter spacecraft had been assembled from the spares). Soon after, the first two van loads of equipment were shipped to Cape Canaveral. The final system test of MR-1 was completed on May 21 and the test of MR-2 followed during the same week.

During the week of May 28, all three spacecraft and their associated ground support equipment were packed, loaded, and shipped to the Atlantic Missile Range (AMR). At the same time, the Atlas designated to launch MR-1 went aboard a C-133 freight aircraft at San Diego. On the same day, an Air Force order grounded all C-133’s for inspection and the plane did not depart until June 9.

By June 11, 1962, the firing dates had been established and both spacecraft were ready for launching. The Atlas booster had already been erected on the launch pad. The dummy run and a joint flight acceptance test were completed on MR-1 during the week of July 2. Final flight preparations and system test of MR-1 and the system test of MR-2 were concluded a week later.

Thus, in 324 days, a new spacecraft project had been activated; the design, assembly, and testing had been completed; and the infinite number of decisions pertaining to launch, AMR Range Operations, deep-space tracking, and data processing activities had been made and implemented.

Venus was approaching the Earth at the end of its 19-month excursion around the Sun. The launch vehicles and Mariners I and II stood ready to go from Canaveral’s Launch Complex 12. The events leading to the first close-up look at Venus and intervening space were about to reach their first crisis: a fiery explosion over the Atlantic Ocean.