In pursuance of this policy the management, faced with a hesitating market, decided upon a bold step. Late in 1883, acting in accordance with the advice of New York and London financiers, they decided to endeavour to make a market for the unissued stock by giving assurance of a dividend for a term of years. They offered to deposit with the government as trustees a sum sufficient to provide for ten years a dividend of three per cent on the $65,000,000 stock already issued, to be supplemented, if possible, by a further dividend out of current revenues, and they arranged to make similar provision for the remaining $35,000,000 as it was sold. Over half the $16,000,000 necessary to purchase this annuity was deposited with the government at once and security given for the early payment of the balance. Only success could have justified such a locking up of the funds urgently needed for construction, and success did not come, though for a time it seemed probable. The sudden smash of the Northern Pacific, just completed by Villard, brought the stock down lower than before the fillip had been given. With sixteen millions locked up or pledged the company was in a worse state than before.[[7]]

In this emergency Stephen and Smith and M'Intyre pledged their St Paul or other stock for loans in New York and Montreal, but still the gap was unfilled. They turned to the government, requesting a loan of $22,500,000, to be secured by a first charge on the main line. In return, they agreed to complete the road by May 1886, five years earlier than the contract required. The request at first was scouted by Sir John Macdonald. Parliament would not consent, and if parliament consented the country would revolt. Bankruptcy stared the company in the face when John Henry Pope came to the rescue. He soon convinced Sir John that if the Canadian Pacific smashed, the Conservative party would smash the day after, and the aid was promised. The Cabinet was won over, and Sir Charles Tupper, hastily summoned by cable from London, stormed it through caucus, and the loan was made.

The funds thus secured were soon exhausted in rapid and costly construction in the mountain and Lake Superior sections. The government's blanket mortgage on the road made it impossible to borrow elsewhere. So, after the Riel episode, to be noted later, a new arrangement was made with the government by which the $35,000,000 stock unsold was cancelled and an equal amount of first mortgage bonds issued. Twenty millions of this issue and the unsold lands were substituted for the government's security, and the remainder of the bonds sold at 95. This put the company once more in funds. The relief came none too soon. In one fateful day in July, when the final passing of the bill was being tensely awaited, the Canadian Pacific, which now borrows fifty millions any day before breakfast, was within three hours of bankruptcy for lack of a few hundred thousand dollars. But by March 1886 every cent of the company's obligations to the government was paid off, twenty millions in cash and the remainder in land at $1.50 an acre.

The men behind the Canadian Pacific proved themselves possessed of courage and determination such as will always win them honour. At more than one critical stage they staked their all to keep the work going. But the fact remains that the bulk of the resources utilized in the original building of the road were provided or advanced by the people of Canada. The Canadian Pacific is as truly a monument of public as of private faith.

Meanwhile, the work of construction had been going ahead. Under William Van Horne's masterful methods the leisurely pace of government construction quickened into the most rapid achievement on record. A time-schedule, carefully made out in advance, was adhered to with remarkably little variation.

Work was begun at the east end of the line, from the point of junction with the Canada Central, but at first energy was devoted chiefly to the portion crossing the plains. Important changes in route were made. The main line had already been deflected to pass through Winnipeg. Now a much more southerly line across the plains was adopted, making for Calgary rather than Edmonton. The new route was shorter by a hundred miles, and more likely to prevent the construction of a rival road south of it later. For many years after the Palliser-Dawson-Hinds reports of the late fifties, it had been assumed that the tillable lands of the West lay in a 'Fertile Belt' or rainbow, following roughly the Saskatchewan valley and curving round a big wedge of the American desert projecting north. Certainly the short, withered, russet-coloured grass lands of the border country looked forbidding beside the green herbage of the North Saskatchewan. But in 1879 Professor Macoun's investigations had shown that the southern lands had been belied by rumour, and that only a very small section was hopelessly arid. With this objection removed, the only drawback to the southern route was the difficulty of finding as good a route through the mountains as the northerly Yellowhead Pass route afforded, but on this the company decided to take its chances.

Work on the plains was begun in May 1881, and by the end of the year 161 miles had been completed. This progress was counted too slow, and under Van Horne's management a contract was made in 1882, with Langdon and Shepard of St Paul, to complete the line to Calgary. Later in the year a construction company was organized, the North American Railway Contracting Company, to build all the uncompleted sections of the main line for $32,000,000 cash and $45,000,000 common stock. This was really a financing rather than a construction expedient, and was abandoned within a year.

In this section the engineering difficulties were not serious, but the pace of construction which was demanded, and the fact that every stick of timber and every pound of food, as well as every rail and spike, had to be brought a great distance, required remarkable organization. Three hundred sub-contractors were employed on the portion of the line crossing the plains. Bridge-gangs and track-layers followed close on the graders' heels. In 1882 over two and a half miles of track a day were laid. In the following year, for weeks in succession, the average ran three and a half miles a day, and in one record-smashing three days twenty miles were covered. By the end of this year the track was within four miles of the summit of the Rockies.

The change of route across the plains had made it essential to pierce the Rockies by a more southerly pass than the Yellowhead. The Kicking Horse or Hector Pass, short but steep, was finally chosen, but here, as at the Yellowhead, to cross the first range did not mean victory. The towering Selkirk range faced the pass, as the Cariboo Mountains flanked the Rockies farther north. Until the rails reached the hills the engineers had found no way through them, and had contemplated a long detour to the north, following the winding Columbia. Then Major Rogers, the engineer whom James J. Hill had suggested to take charge of the location of the mountain section, following up a hint of Moberly, an earlier explorer, found a route, steep but practicable, across the Selkirks, following the Beaver river valley and Bear Creek, and then through Rogers Pass into the valley of the Illecillewaet, and so through Eagle Pass to the settled location at Kamloops. Both in the Kicking Horse and in the Rogers Pass gradients of 116 feet to the mile were found necessary, but these difficult stretches were concentrated within one operating section of a hundred and twenty miles, and could easily be overcome by the use of additional engines. Unique provision was made against the mountain avalanches by erecting diverting timbers near the summits and building mile upon mile of snow-sheds, over which the avalanches passed harmless. As a result of these expedients and of raising the road-bed across the prairies unusually high, the Canadian Pacific lost less time through snow blockades than the great railways of the eastern United States.

It was not until 1884 that the wilderness north of Lake Superior was attacked in strong force. Nine thousand men were employed here alone. Rock and muskeg, hill and hollow, made this section more difficult to face than even the Fraser Canyon. In one muskeg area to-day seven layers of Canadian Pacific rails are buried, one below the other. The stretch along the shore of the lake was particularly difficult. The Laurentian rocks were the oldest known to geologists, and, what was more to the purpose, the toughest known to engineers. A dynamite factory was built on the spot and a road blasted through. One mile cost $700,000 to build and several cost half a million. The time required and the total expenditure would have been prohibitive had not the management decided to make extensive use of trestle-work. It would have cost over two dollars a cubic yard to cut through the hills and fill up the hollows by team-haul; it cost only one-tenth of that to build timber trestles, carrying the line high, and to fill up later by train-haul.