ENGINE ROOM AND ICE PLANT LABOR COST:

1 chief engineer per day $ 8.00
3 engineers per day $ 6.00
1 shipping clerk per day $ 6.00
3 men in Storage House per day $ 4.00
Total per day $ 44.00
365 days at $44.00 per day equals
$ 16,060.00
Additional labor cost for putting
12,000 tons into winter storage
and taking out at $4.00 per day

$ 1,200.00
Total Labor Cost
$ 17,260.00

or 17260 / 53280 = 32.4 cent per ton

Engineers will do their own firing of boilers and will pull all the ice. One pull required every 43 minutes.

OFFICE EXPENSE:

1 Office Man (Manager and Bookkeeper) $ 3,000.00
Stationery, Telephone, etc. (per year) $ 300.00
Total Office Expense
$ 3,300.00

or 3300 / 53280 = 6.2 cent per ton of ice

Cost of Ammonia at 2 cent per ton $ 1,065.60
Cost of Oil and Waste at 2 cent per ton $ 1,065.60
Cost of Water at 3 cent per ton $ 1,598.40
Cost of Salt at 1/2 cent per ton $ 266.40
Plant Maintenance and Repairs $ 2,200.00

or 2200 / 53280 = 4.1 cent per ton