ENGINE ROOM LABOR COST:
| 1 chief engineer per day | $ 10.00 |
| 3 engineers per day | $ 8.00 |
| Total per day | $ 34.00 |
| 365 days at $34.00 equals | $ 12,410.00 |
or 12410 / 80000 = 15.62 cents per ton
[2]
ICE PLANT LABOR COST:
| 3 men pulling ice and setting it up in store-room. | per day $ 6.00 |
| 3 men in store-room | per day $ 6.00 |
| 1 shipping clerk | per day $ 8.00 |
| Total labor | per day $ 44.00 |
365 days at $44.00 equals 16,060.00
| For filling the winter storage house and taking the ice out of it will require 3 additional men for five months, equals 150 days x $18.00, equals | $ 2,700.00 |
Total Ice Plant Labor Cost Equals $18,760.00
or 18670 / 80000 = 23.46 cents per ton