The blistered condition of the front of the girls' hall and academy from the intense heat of the fire were then relieved by a thorough scraping, sandpapering and repainting.
Owing to the limited accommodations for the boys in this building, and for the large number of pupils in the primary department in the academy, an extension of twelve feet, with an upper room for special students, was added that fall to the academy. While this improvement was under construction, other boys built a new wood shed, obtained in the timber and prepared the supplies of fuel, and built 170 rods of new fence. A considerable quantity of sand was also hauled for the foundation of the new hall for the boys.
ELLIOTT HALL
In 1910, the erection of Elliott Hall became a necessity after the disastrous fire which occurred on March 13th. This building is 80x32 feet, with an extension 6x32 feet, in front, and a two story addition 18x16 feet, for kitchen store and bath rooms, at the northwest corner over a large brick-walled cistern.
This building absorbed the attention of all for more than a year, although it was opened for occupancy on November 14th. It was a great undertaking with the few workmen obtainable. The clearing away of the rubbish, the excavation for the cellar 28x75 feet and the construction of the foundation wall, and the same for the large cistern took a good deal more time than was expected, and all of it was heavy and hard work for every one that participated in it. It was the 15th of June when the cement wall around the main part of the foundation was completed by the superintendent, who placed the rock, cement and reinforcing materials in the walls with his own hands as a precaution against defects.
The construction of the frame work was entrusted to Samuel A. Folsom, who, acting as foreman of the carpenters, succeeded in getting the building ready for occupancy at the end of five months, or November 14th. So great, however, was the amount of unfinished work in the halls and rooms upstairs and of cement lining needed for the excavation walls in the cellar that a considerable number of students were employed principally at this work during that and the following term.
Every part of the work on this building was very faithfully performed. It is a creditable monument to the memory of every one that wrought upon it. It is symmetrical and, though plain, is handsome in appearance and very convenient in its uses; as an administration building, girls dormitory and boarding house. The lumber was furnished and delivered by J. R. Bowles of Swink; David Folsom made the window and door frames; Solomon Buchanan served as foreman of the painters, and he and George Stewart built the walls of the cistern and the first story of the chimneys. Edward Hollingsworth, in addition to important work on other parts of the building, served as foreman of the construction of the stairways, belfry and porches. It represents an expenditure of $6,500 in cash and student labor. This does not include the services of the superintendent, who had previously prepared the plans for the building and personally superintended its construction.
LATER IMPROVEMENTS
During 1911 and 1912 while some were putting the finishing touches on Elliott Hall, the last being the insertion of the fixtures in the two bath rooms and the construction of a closed room in the cellar for canned fruit and vegetables, the other boys removed the old oak stumps from the north field, drained a slough covering four acres of land, cleaned twenty acres of land for cultivation and built 160 rods of good fence around it. They also built a pretty and very convenient semi-monitor hen house, with open front and two out-yards.