Dimensions of the Carr Rock.

The length of the Carr Rock, from south to north, measures 75 feet; but its greatest breadth, as seen at low-water of spring-tides, being only 23 feet, it was found to be impracticable to obtain a base for a building of greater diameter than 18 feet. Such also was the fractured and rugged state of the surface of this rock, that it became necessary to excavate part of the foundation-pit of the building to the depth of seven feet. The difficulties of this part of the work were also greatly increased, owing to the foundation, on the eastern side, being under the level of the lowest tides: so that it became necessary to construct a coffer-dam. Part of this coffer-dam it was necessary to remove, and carry ashore, after each tide’s work; and on the return of the workmen at ebb-tide, a considerable time was unavoidably occupied in fixing the moveable part of the coffer-dam, and in pumping the water out of the foundation-pit.

Difficulties of this work compared with those of the Bell Rock.

But, to enable the reader to form a comparative estimate of the difficulties attending the early stages of the Carr Rock Beacon, with those of the Bell Rock Light-house, it may be noticed, that the period which the artificers were actually at work upon the Carr Rock, as ascertained by the foreman during the first season, or the summer of 1813, was 41 hours; and in 1814, after the experience of one year’s work, these were only extended to 53 hours. Now, if we compare 1807 and 1808, the two first years’ work at the Bell Rock, we find the artificers were respectively about 180 and 265 hours upon that rock. The first two years at the Carr Rock were entirely occupied in excavating and preparing the foundation, and in laying 10 stones, or the half-course of masonry, which brings the foundation to a uniform level, for the first entire course of the building, as shewn in [Plate II.]; while, at the Bell Rock, in the two first seasons three courses were erected, as represented in [Plate IX.], of a building situate 12 miles from the shore, and measuring 42 feet in diameter at the base, besides the erection of a Beacon-house or Barrack for the workmen. The establishment for the works at the Bell Rock was of course on a much larger scale than that of the Carr Rock; but still the latter was equally effective, and the same apparatus, artificers and seamen, were employed at both.

Third year’s work at the Carr Rock.

During the third year’s work, or 1815, the second course of the masonry was completed upon the Carr, and nine stones of the third course had been got laid by the 3d of October, when a heavy ground-swell obliged the artificers precipitately to leave the rock and take to their boats. This swell was immediately accompanied by a gale of easterly wind, and before the cement had taken bond or firmness, the surge of the sea washed it out; when the oaken trenails, used as a temporary fixture during the progress of the work, were wrenched off, and the stone-joggles broken asunder. The whole of the nine blocks of stone were thus swept off the rock and lost in deep water, though they had been completely dove-tailed, and fitted on the same principles as the masonry of the Bell Rock Light-house, where not a single stone was lost during the whole progress of the work.

Fourth year’s work.

In the year 1816, or fourth season, the work was continued till the month of November, when the building had attained the height of about 20 feet, or the 16th course, and still wanting 18 courses to complete the masonry. In this state, it was left till the following season, having been previously loaded with about four tons of lead, cast in suitable pieces, and suspended within the void or central hollow of the building. The operations of the fourth season had been also much retarded by several untoward accidents. In particular, a heavy gale overtook the workmen while they were laying the 7th course, which obliged them to leave the rock before the precautionary measures could be taken, for closing and completing the work immediately in hand; in consequence of which, the stones on the eastern, or weather-side of this course, were lifted off their bases, the oaken trenails broken, and five of the blocks of stone swept away. At another period, the Pozzolano mortar of the beds of two of the stones was washed out, and so much injured, that the stones required to be lifted and relaid. The works were this season intended to have been closed early in the month of October, when another unlucky gale sprung up, just as the sixteenth course had been laid, which lifted seven of the stones off their beds; but they were fortunately held by the oaken trenails, and in this state they remained for about three weeks, before a landing could possibly be effected, to replace them.

Fifth year’s work.

In the month of June 1817, the fifth year’s work was begun, and the remaining courses of the masonry were built; but in the month of November, the coast was visited with a gale of wind at south-east, accompanied with a heavy swell of sea, which, unfortunately, washed down the upper part of the building, and reduced it to the height of the fifth course, which formed part of the fourth year’s work.