AT THE TOP OF CANEMAH HILL ON THE PACIFIC HIGHWAY IN CLACKAMAS COUNTY.
GRADED AND PAVED IN 1918

Grading—Canemah Hill Section

To complete the grading of the Pacific Highway between Oregon City and Canby preparatory to the paving of this section, Clackamas County agreed to appropriate $25,000.00 toward the grading between Fly Creek and Oregon City, known as the Canemah Hill Section. On December 10, 1917, the Highway Commission received bids for this grading and the lowest bid having been submitted by Clackamas County, the contract was awarded to the County. This piece of work was about one and one-half miles in length and involved some very heavy rock excavation.

There has been expended on this work to date the sum of $24,037.20, of which amount Clackamas County has paid $22,092.53. The work complete will cost approximately $27,500.00. Mr. M. E. DeWitt was the resident engineer in charge.

DETAILED STATEMENT OF EXPENDITURES TO NOVEMBER 30, 1918
GRADING—CANEMAH HILL (Work in progress)

Engineering $ 1,944.67
Construction—
Clearing and grubbing$ 500.00
Common excavation, 10,231 cu. yds. at 60c6,138.60
Intermediate excavation, 8,689.4 cu. yds. at 80c6,951.52
Solid rock excavation, 7,722.2 cu. yds. at $1.259,652.75
12-inch reinforced concrete pipe, 391 lin. ft. at $1.25488.75
36-inch reinforced concrete pipe, 56 lin. ft. at $4.00224.00
6-inch porous drain tile, 585 lin. ft. at 10c58.50
Class A concrete, 48 cu. yds. at $15.00720.00
Class C concrete, 2 cu. yds. at $12.0024.00
Rubble masonry, 2 cu. yds. at $1.252.50
Overhaul per 100 lin. ft., 54,862 cu. yds. at 2c1,097.24
Crushed rock for drain tile, 30 cu. yds.46.20
18-inch concrete pipe in place, 45 lin. ft.87.15
$ 25,991.21
Less 15 per cent retained pending completion3,898.68
22,092.53
Total expended to November 30, 1918 $ 24,037.20
Paid by State—engineering 1,944.67
Paid by County—construction 22,092.53
Total $ 24,037.20
This work is estimated to cost complete $ 27,500.00