DETAILED EXPENDITURE STATEMENT—PAVING—MULTNOMAH
COUNTY LINE TO SCAPPOOSE

Engineering $ 1,364.28
Right-of-way attorney fees 35.00
Contract Construction Work as follows:
Common excavation, 800 cu. yds. at 45c$ 360.00
Standard Bith. pavement, 24,248.2 sq. yds. at $1.1728,370.39
Broken stone, loose measure, 3,115.5 cu. yds. at
$1.90
5,919.45
Broken stone shoulders, 26,974 lin. ft. at 5c1,348.70
Force account:
34 feet of 12-inch corrugated iron pipe and
120 feet of 6-inch porous drain tile
254.77
Total paid to contractor $ 36,253.31
Total cost $ 37,652.59

Westport-Clatskanie Macadam

On the Clatskanie-Westport Section, which extended from Clatskanie to the Clatsop County Line, the work was handled originally by the Warren Construction Company, on a cost plus ten per cent. basis. The State Highway Department took this work over December 26, 1917, and from that time on the work was handled by this Department. This work consisted of 8.62 miles of sixteen-foot waterbound macadam.

On this section the costs show that the Warren Construction Company laid crushed rock slightly cheaper than the State. However, the State did all the finishing on this section, which is more expensive than laying the base rock and it was necessary to raise the wages twenty-five per cent. after the work was taken over by the Department. C. L. Grutze was resident engineer on this work.

COST STATEMENT—WESTPORT-CLATSKANIE MACADAM

ItemUnitQuantityTotal costUnit cost
By Warren Construction Co. on cost
plus contract—
Clearing and grubbingAcres1⁄2$ 49.87$ 99.74
ExcavationCu. yd.6,2006,820.701.10
6-ft. by 12-in. drain pipeFoot1,0852,752.382.80
Water-bound macadam[9]Cu. yd.7,74227,698.873.59
Engineering 497.03
By State Forces—
ExcavationCu. yd.8,2995,594.75.67
6-ft. by 12-in. drain pipe (laying)Foot29821.05.07
Water-bound macadamCu. yd.17,97768,168.503.79
Engineering 25.09
Total cost......$ 111,628.24...

[9] 4,972 cu. yds. purchased at cost of $5,966.40, all other rock crushed on this job.