CHAPTER IV
PREPARATIONS FOR ANOTHER ATTEMPT

“Taking Stock”—Further Capital—Alterations in Paying-Out Machinery—Improved Testing and Signaling Apparatus.

THIS untoward interruption to the expedition was naturally a cause of great disappointment to all connected with the undertaking; for there was not enough cable left to complete the work, nor was there time to get more made and stowed on board to renew the attempt before the season would be too far advanced.

The squadron proceeded to Plymouth to unload the cable into tanks at Keyham (now Devonport) Dockyard, chiefly because some of the ships could not be spared by their respective governments till the following year. In the middle of October (1857), the engineer-in-chief proceeded to Valentia in a small paddle-steamer with the object of picking up some of the lost line from this end. After experiencing a series of gales, over fifty miles of the main cable were recovered, and the shore end buoyed ready for splicing on to in the coming year.

The first expedition had opened the eyes of the investing public to the vastness of the undertaking, and led many to doubt who did not doubt before. Some began to look upon it as a romantic adventure of the sea, rather than as a serious commercial{75} undertaking. This decline of popular faith was felt as soon as there was a call for more money. The loss of 335 miles of cable, with the postponement of the expedition to another year, was equivalent to a loss of £100,000.