All the 3,000 miles of cable was coiled into the two large ships by the end of May. Fig. 22 gives a general idea of the paying-out apparatus mounted on the deck of the Agamemnon, and Fig. 23 a view in section of the fore-tanks of the Niagara when loaded with her cargo of cable. The engineer had this time fitted cast-iron cones in the middle of each cable-coil to meet the requirements of safe paying out, besides providing a large margin of space to the hatchway above. Fig. 24 shows the loading of the Agamemnon.{86} The rest of the telegraph squadron was on this occasion made up by H.M. Gorgon, H.M. paddle-steamer Valorous, and H.M. surveying-steamer Porcupine.
The fleet set forth on their second cruise on May 29, 1858—this time without any show of public enthusiasm. Mr. Bright was again assisted by the same engineering staff, but Professor Thomson had agreed to take a more active part in the electrical work. The Bay of Biscay was to be the scene of the experiments—the actual site being about 120 miles northwest of Corunna, where the Gorgon obtained soundings of 2,530 fathoms or nearly three statute miles.
The Agamemnon and Niagara were then backed close together, stern on, and a strong hawser was passed between them. Each ship had on board some defective cable for the experiments about to be conducted. The proceedings may perhaps best be described by extracts from the engineer’s diary:
Monday, May 31st, 10 A.M., hove to, lat. 47° 11´, long. 9° 37´. Up to midday engaged in making splice between experimental cable in fore coil and that in main hold, besides other minor operations. In afternoon getting hawser from Niagara and her portion of cable to make joint and splice. 4 P.M., commenced splice; 5.15 splice completed; 5.25, let go splice-frame (weight 3 cwt.) over gangway, amidships, starboard side.[27] 5.30, after getting splice-frame (containing the splice) clear of the ship and lowering it to the bottom, each vessel (then{87} about a quarter of a mile apart) commenced paying out in opposite directions.
9 P.M., got on board Niagara’s warp and her end of cable to make another splice for second experiment.
June 1st.—1 A.M. (night), electrical continuity gone, the cable having parted after two miles in all had been paid out.[28]
Since 1 A.M., engaged in hauling in our cable. Recovered all our portion, and even managed to heave up the splice-frame (in perfect condition), besides 100 fathoms of Niagara’s cable, which she had parted. Fastened splice to stern of vessel and ceased operations.
9.23 A.M., second experiment. Started paying-out again. Weather very misty.
9.40, one mile paid out at strain 16 cwt.; angle of cable 16° with the horizon: running out straight; rate of ship 2, cable 3.