“The desirability of removing the obelisk resolves itself into two questions—the cost, and the value and interest of the monument as compared with the necessary expenditure. There can be no doubt as to the feasibility of removal. An opinion has certainly prevailed in England that the obelisk is so much defaced and broken as to have lost all interest. But I will venture to say that this opinion has not been formed by any one who has seen the whole of three sides which have been exposed by the excavations recently made by Sir James Alexander. The opinion was formed when but very little more than the upper side of the base was visible—a valueless part which appears never to have been sculptured, and to have been intended for burial in the foundation when the obelisk was in position. The column, as at present exposed, is at once seen to be a monument of great value and interest; one which, not only for its antiquity, but also from its quality as a monolith, would be specially notable in London, which, unlike most of the capital cities of Europe, possesses no adornment of this character. The English people cannot see in their own country a carved stone even approaching the dimensions of this colossal obelisk of red granite. As to the condition of the monument, I have examined three of the four sides, and there is no part of any one of the hieroglyphics the carving of which is not distinctly traceable. The edges of the carving are somewhat worn, and the angles of the obelisk rounded; but the interest of the monument is in no place substantially impaired, nor is there discernable any important fracture of the stone. The dimensions of the obelisk are:—Total length from extremity of base to apex, sixty-six feet; seven feet square at base, and four and a-half feet square at base of apex. The weight is probably about 250 tons.

“In considering the method and cost of removal to England, I have had the great advantage of the assistance, on the ground, of Captain Methven, the senior captain and commodore of the fleet of steam-ships belonging to the Peninsular and Oriental Company. The base of the obelisk is less than twenty yards from the waters of the Mediterranean; and within about 100 yards there is a depth of two and a-half fathoms of water. It has been suggested to float the obelisk by attaching to it a sufficient quantity of timber. But this is a very crude proposal, apart from the fact that no sufficient quantity of timber is obtainable in this almost treeless country. Undoubtedly it would be possible to remove and to ship the obelisk by constructing a railway on piles for such a distance as would admit of the approach of a vessel capable of carrying it securely to England. In this case the obelisk would be suspended in slings from running-gear, and moved out to sea until it hung over its destined position in the vessel. But the shore is not the most suitable for this plan, which, moreover, would involve a very large expenditure.

“The position of the obelisk is favourable for the adoption of a third method, which appears both to Captain Methven and to myself to be the most easy, safe, and practicable; and, at the same time, the least costly of any that have been suggested. The ground in which the obelisk now lies seems sufficiently firm (with proper supports at the sides of the necessary excavation) to sustain girders from which the column could be slung without any change in its position. To ensure a proper distribution of the weight, it would be desirable that these girders should rest on iron plates, and that they should be of greater substance in the centre, where the weight of the obelisk would be borne. Captain Methven is confidently of opinion that the obelisk could be safely conveyed to England in an iron vessel not exceeding 400 tons of builder’s measurement, 120 feet in length, and drawing, when loaded, not more than six feet of water. This decked iron vessel, or barge, would be constructed in England, and sent in pieces to Alexandria, where it would be put together in the space to be excavated beneath the suspended obelisk, the channel necessary to get to the deep water being at the same time formed by a steam dredge, or, if the shore is rocky, by blasting—a method which has been very successfully adopted, on a much larger scale than would be requisite here, by the Peninsular and Oriental Company at Bombay. When the vessel was ready to receive the obelisk, the intervening wall of earth between the base of the stone and the sea would be thrown down, and the incoming water would raise the vessel to its burden. The iron barge could then be towed into the harbour, when it would be decked, and have so much freeboard added as appeared desirable. Captain Methven feels quite sure, that by any competent steam-ship of Her Majesty’s navy the vessel could be towed to England without danger of damage to the towing-ship, or risk of losing the obelisk, regard being had to the season and to the state of the barometer on quitting this port and that of Gibraltar.

“Finally, I would say that Captain Methven seems to be of opinion that all this could be accomplished at a cost of about £5,000.

“Yours faithfully,
“Arthur Arnold.”

Our memoranda next lead us to the consideration of suggestions which have been made, from time to time, for the transport of the obelisk from Alexandria to England. Thus, in The Builder for 1851, vol. v., we find the following communication with respect to two plans proposed by Captain (afterwards Admiral) Smyth.

“One, by building a pier from the immediate vicinity of the obelisk into the little harbour, to the end of which a north-country-built vessel could be brought, with her stern-frame cut out; the obelisk to be conveyed along the pier on rollers in such a manner that half of it should be in the vessel before the weight was felt.

“His other plan was to excavate the ground on which it was lying, so as to form a dry dock beneath; then build under it a lighter, into which the monolith could be lowered, and then letting the water into a canal made to the port to float it away; such vessel subsequently to be towed by a steamer: in either case, the vessel to be properly dunaged with bales of cotton and fascines, so that the Needle, being in midships, would lie easy, and press equally on the vessel’s frame. This method is very similar to that mentioned by Pliny.”

These several details relating to the British obelisk, naturally awaken our interest to everything bearing upon the subject; and, amongst others, to the method of conveyance of the Luxor obelisk to Paris. Thus, in the “Pictorial Gallery of Arts,” we find a description of the transport of the Theban obelisk to Paris, from the pen of our old friend, Charles Knight:—

“The transport of one of these two obelisks to Paris was a very remarkable enterprise. When Napoleon accompanied the French army to Thebes, he was so struck with these magnificent towering masses, that he conceived the idea of sending one of them to France; but his subsequent reverses prevented the idea from being carried out. Thirty years afterwards, Charles X. obtained from Mehemet Ali permission to make the transfer, and he and his successor, Louis Philippe, proceeded with the necessary arrangements. A vessel was built of fir and other light wood, strong enough to bear the sea, but shallow enough to descend the Nile and ascend the Seine. The expedition, comprising about 140 persons, sailed from Toulon in April, 1831, and arrived at Thebes in August of the same year. The difficulties of navigating the vessel up the Nile were very great, and the men suffered much from heat, sand-storms, ophthalmia, cholera, and other visitations of that climate. The officers, on landing at Luxor, superintended the erection of barracks, sheds, and tents; the building of baking-ovens and provision-stores; and the establishment of such arrangements as should ensure the comfort of the men during the operations for the removal of the obelisk.