During the 1884-85 expedition the railway was continued for some 40 miles, but in consequence of the evacuation of the Sudan it was dropped, and the portion beyond Sarras was destroyed by the Dervishes.

In 1896, when operations became imminent, the Sirdar began laying a line from Korosko southwards, but this was soon abandoned, and the original railway was continued in April, 1896, in the direction of Dongola. This line was completed after considerable difficulties, as far as its present terminus, Kerma, on 4th April, 1897.

The main line, striking from Halfa across the desert to Abu Hamed, was commenced on 1st January, 1897, and, after a stoppage of 22 days for want of material, reached Abu Hamed, 230 miles, on 31st October, 1897. It was laid at the great rate of about a mile a day, the maximum speed for one day being 5,200 yards. The record for 1 month was 48 miles; this was during October, 1897.

It eventually reached Khartoum North (Halfaya) on the last day of 1899.

The Suakin-Berber railway was boldly taken in hand during the Suakin expedition in the spring of 1885, but only a few miles were laid, and it was then abandoned.

The route for the future Nile-Red Sea railway has now been decided on and surveyed (1902-03), and the laying has been commenced from both ends.

The present lines from Halfa to Khartoum North and Dongola (Kerma) were laid primarily to supply an army in the field; the route, method of laying, and materials, were all chosen with this object in view.

Partly as a consequence of this, nearly 50 per cent. of the line is in the desert.

The main line is 575 miles, and the Kerma line is 203 miles long.

The gauge of the lines is 3 feet 6 inches, the same as the Cape railways. Single line throughout (except at the crossing-places).