The said reservoir was completed about the beginning of December, 1860, when the defendants caused the same to be partially filled with water, and on the morning of the 11th December in the same year, whilst the reservoir was so partially filled, one of the shafts which had been so met with as aforesaid gave way and burst downwards; in consequence of which the water of the reservoir flowed into the old workings underneath, and by means of the underground communications so then existing between those old coal workings and the plaintiff’s coal workings in the plaintiff’s colliery, as above described, large quantities of the water so flowing from the said reservoir as aforesaid found their way into the said coal workings in the plaintiff’s colliery, and by reason thereof the said colliery became and was flooded, and the working thereof was obliged to be and was for a time necessarily suspended.

The question for the opinion of the Court was whether the plaintiff was entitled to recover damages from the defendants by reason of the matters thus stated by the arbitrator.

The Court of Exchequer (Pollock, C. B., and Martin, B., concurring; Bramwell, B., dissenting) gave judgment for defendants.


Plaintiff brought error in the Exchequer Chamber.


May 14, 1866. The judgment of the Court (Willes, Blackburn, Keating, Mellor, Montague Smith, and Lush, JJ.) was delivered by

Blackburn, J. This was a special case stated by an arbitrator, under an order of nisi prius, in which the question for the Court is stated to be, whether the plaintiff is entitled to recover any and, if any, what damages from the defendants by reason of the matters thereinbefore stated.

In the Court of Exchequer, the Chief Baron and Martin, B., were of opinion that the plaintiff was not entitled to recover at all, Bramwell, B., being of a different opinion. The judgment in the Exchequer was consequently given for the defendants, in conformity with the opinion of the majority of the Court. The only question argued before us was whether this judgment was right, nothing being said about the measure of damages in case the plaintiff should be held entitled to recover. We have come to the conclusion that the opinion of Bramwell, B., was right, and that the answer to the question should be that the plaintiff was entitled to recover damages from the defendants by reason of the matters stated in the case, and consequently that the judgment below should be reversed, but we cannot at present say to what damages the plaintiff is entitled.

It appears from the statement in the case that the plaintiff was damaged by his property being flooded by water which, without any fault on his part, broke out of a reservoir constructed on the defendants’ land by the defendants’ orders, and maintained by the defendants.