Summary
| From the preceding estimate of quantities, the | |
| number of pressed brick laid is 5,041, which, | |
| at $53.71 per M, will cost | $270.75 |
| Pressed brick, not laid, 252, at $30 per M | 7.56 |
| Total cost of pressed brickwork | $278.31 |
Common Brick
Cost
The cost of the common brickwork is based on the analysis given in Estimating and Calculating Quantities, Part 1, and is $16.68 per thousand for lime-cement mortar.
Summary
| According to the estimate of quantities, | |
| the number of common brick laid is 46,303, | |
| which, at $16.68, will cost | $ 772.33 |
| Common bricks, not laid, 2,315, at $8 | 18.52 |
| Molded brick and terra-cotta cap for rear chimney | 10.00 |
| Total cost of common brickwork | $ 800.85 |
| Recapitulation of Cost of Brickwork | |
| Pressed brickwork | $ 278.31 |
| Common brickwork | 800.85 |
| Total cost of brickwork | $1,079.16 |
CARPENTRY
5. In estimating carpentry work, it is advisable to make a tabulated list of the various sizes of joists, rafters, etc., giving the number and dimensions of each size. In this way, any error in calculation or change in price can be corrected with little difficulty.