When you build your wooden form, of course you put up the door and window frames. They can’t be cut out of the walls afterward as with a log cabin. Drive numerous long spikes into the outer surfaces of these frames. This gives you something to “tie” to when you reach that height with your masonry.
Building a stone house is slow work, and since you’ll have to leave your work at times, remember that all mortar that has been laid the day before must be thoroughly wet before fresh mortal is applied on top of it. And the entire walls ought to be wet down at least twice daily for a week or more after completion.
When you have reached the top course of stones, set in a row of threaded iron bolts two feet apart and long enough to allow three inches of the threaded end to stick up. On these you must bolt 2×4’s, so that you have something to nail the rafters to.
Window and door frames are set into the masonry as it proceeds, with long spikes protruding to “tie” them firmly.
2″×6″ WINDOW FRAME SPIKES TIE FRAME TO MASONRY
When the walls have set, remove the interior wooden forms and go over the inside walls to fill up any air holes. These are not important unless they are too large. The rest of the job is done just as in finishing any other house. You’ll probably want to cover the interior with some material, because concrete is pretty cold and might remind someone of the time he was arrested for speeding.
The cost of a stone house depends on the amount of material you can find lying around the neighborhood and the cost of labor. Some stone cabins, with most of the labor hired, have been built for approximately $2.50 per square foot of floor space. This includes labor, materials, built-ins, electrical wiring and fixtures, and plastered walls. If you find it necessary to hire skilled stone masons or to transport your material considerable distance, the cost will be higher. You can, of course, lower it by doing a larger amount of the work yourself.
Remember that stone work is slow work, so allow yourself plenty of time. The first course or so of stone will drop into place pretty fast, but don’t forget that Rome was not built in a day—and Rome was built of stone.
For making colored concrete, for floors, hearths, etc., a topping containing the color is put on over the previously-poured base. This topping consists of five gallons of water per sack of cement, one cubic foot of sand and 1½ cubic feet of coarse aggregate. You may use factory-colored cement, or mix it on the job by passing the dry cement and coloring matter through a screen with a ⅛-inch mesh until well mixed.