The principal obstructions between Old Moldova and Turnu Severin were the Stenka Rapids, the Kozla Dojke Rapids, the Greben section and the Iron Gates. At the first named there was a bank of rocks, some of them dry at low water, extending almost across the river (985 yds. wide). The fall of the river bed is small, but the length of the rapid is 1100 yds. The Kozla Dojke, 9 m. below the Stenka Rapids, extend also for 1100 yds., with a fall of 1 in 1000, where two banks of rocks cause a sudden alternation in the direction of the current. The river is here only 170 to 330 yds. in width. Six miles farther on is the Greben section, the most difficult part of the works of improvement. A spur of the Greben mountains runs out below two shoals where the river suddenly narrows to 300 yds. at low water, but presently widens to 1½ m. Seven miles lower down are the Jucz Rapids, where the river-bed has a fall of 1 in 433. At the Iron Gates, 34 m. below the Greben, the Prigrada rocky bank nearly blocked the river at the point where it widens out after leaving the Kazan defile. The general object of the works was to obtain a navigable depth of water at all seasons of 2 metres (6.56 ft.) on that portion of the river above Orsova, and a depth of 3 metres (9.84 ft.) below that town. To effect this at Stenka, Kozla Dojke, Islaz and Tachtalia, channels 66 yds. wide had to be cut in the solid rock to a depth of 6 ft. 6 in. below low water. The point of the Greben spur had to be entirely removed for a distance of 167 yds. back from its original face. Below the Greben point a training wall 7 to 9 ft. high, 10 ft. at top and nearly 4 m. in length, has been built along the Servian shore in order to confine the river in a narrow channel. At Jucz another similar channel had to be cut and a training wall built. At the Iron Gates a channel 80 yds. wide, nearly 2000 yds. in length and 10 ft. deep (in the immediate vicinity of traces of an old Roman canal) had to be cut on the Servian side of the river through solid rock. Training walls have been built on either side of the channel to confine the water so as to raise its level; that on the right bank having a width of 19 ft. 6 in. at top, and serving as a tow-path; that on the left being 13 ft. in width. These training walls are built of stone with flat revetments to protect them against ice. These formidable and expensive works have not altogether realized the expectations that had been formed of them. One most important result, however, has been attained, i.e. vessels can now navigate the Iron Gates at all seasons of the year when the river is not closed by ice, whereas formerly at extreme low water, lasting generally for about three months in the late summer and autumn, through navigation was always at a standstill, and goods had to be landed and transported considerable distances by land. The canal was opened for traffic on the 1st of October 1898. It was designed of sufficient width, as was supposed, for the simultaneous passage of boats in opposite directions; but on account of the great velocity of the current this has been found to be impracticable.

From the Iron Gates down to Braila, which is the highest point to which large sea-going ships ascend the river, there have been no important works of improvement. From Braila to Sulina, a distance of about 100 m., the river falls under European commission of the Danube. the jurisdiction of the European commission of the Danube, an institution of such importance as to merit lengthened notice. It was called into existence under Art. XVI. of the treaty of Paris (1856), and in November of that year a commission was constituted in which Austria, France, Great Britain, Prussia, Russia, Sardinia and Turkey were each represented by one delegate “to designate and cause to be executed the works necessary below Isaktcha[1] to clear the mouths of the Danube as well as the neighbouring parts of the sea, from the sands and other impediments which obstructed them, in order to put that part of the river and the said parts of the sea in the best possible state for navigation.”

In Art. XVIII. of the same treaty it was anticipated that the European commission would have finished the works described within the period of two years, when it was to be dissolved and its powers taken over by a Riverain commission to be established under the same treaty; but this commission has never come into existence. Extended by short periods up to 1871, the powers of the European commission were then prolonged under the treaty of London for twelve years. At the congress of Berlin in 1878 its jurisdiction was extended from Isakcea to Galatz (26 m.), and it was decided that the commission, in which Rumania was henceforward to be represented by a delegate, should exercise its powers in complete independence of the territorial authority. By the treaty of London of 1883 the jurisdiction of the commission was extended from Galatz to Braila and its powers were prolonged for twenty-one years (i.e. till the 24th of April 1904), after which its existence was to continue by tacit prolongation for successive terms of three years unless one of the high contracting powers should propose any modification in its constitution or attributes. It was also decided that the European commission should no longer exercise any effective control over that portion of the Kilia branch of which the two banks belonged to one of the riverain powers (Russia and Rumania), while as regards that portion of it which separated the two countries, control was to be exercised by the Russian and Rumanian delegates on the European commission. Russia was also authorized to levy tolls intended to cover the expenses of any works of improvement that might be undertaken by her. Art. VII. of the same treaty declared that the regulations for navigation, river police, and superintendence drawn up on the 2nd of June 1882 by the European commission, assisted by the delegates of Servia and Bulgaria, should be made applicable to that part of the Danube situated between the Iron Gates and Braila. In consequence of Rumania’s opposition, the proposed Commission Mixte was never formed, and these regulations have never been put in force. As regards the extension of the powers of the European commission to Braila, 11 m. above Galatz, and at the head of the maritime navigation, a tacit understanding has been arrived at, under which questions concerning navigation proper come under the jurisdiction of the commission, while the police of the ports remains in the hands of the Rumanian authorities.

Sir Charles Hartley, who was chief engineer of the commission from 1856 to 1907,[2] in a paper contributed to the Institution of Civil Engineers in 1873 (vol. xxxvi.), gave the following graphic description of the state of the Sulina mouth when the commission entered on its labours in 1856:—

“The entrance to the Sulina branch was a wild open seaboard strewn with wrecks, the hulls and masts of which, sticking out of the submerged sandbanks, gave to mariners the only guide where the deepest channel was to be found. The depth of the channel varied from 7 to 11 ft., and was rarely more than 9 ft.

“The site now occupied by wide quays extending several miles in length was then entirely covered with water when the sea rose a few inches above ordinary level, and that even in a perfect calm; the banks of the river near the mouth were only indicated by clusters of wretched hovels built on piles and by narrow patches of sand skirted by tall weeds, the only vegetable product of the vast swamps beyond.

“For some years before the improvements, an average of 2000 vessels of an aggregate capacity of 400,000 tons visited the Danube, and of this number more than three-fourths loaded either the whole or part of their cargoes from lighters in the Sulina roadstead, where, lying off a lee shore, they were frequently exposed to the greatest danger. Shipwrecks were of common occurrence, and occasionally the number of disasters was appalling. One dark winter night in 1855, during a terrific gale, 24 sailing ships and 60 lighters went ashore off the mouth and upwards of 300 persons perished.”

The state of affairs in the river was not much better than at the Sulina mouth. Of the three arms of the Danube, the Kilia, the Sulina and the St George, the central or Sulina branch, owing to its greater depth of water over the bar, had from time immemorial been the principal waterway for sea-going vessels; its average depth throughout its course, which could not always be counted on, was 8 ft., but it contained numerous shoals where vessels had to lighten, so that cargo had often to be shifted several times in the voyage down the river. It also contained numerous bends and sharp curves, sources of the greatest difficulty to navigation.

The commission fixed its seat at Galatz. Provisional works of improvement were begun almost immediately at the mouth of the Sulina branch of the Danube, but two years were spent in discussing the relative claims to adoption of the Kilia, the Sulina and the St George’s mouths. Unable to agree, the delegates referred the question to their respective governments, and a technical commission appointed by France, England, Prussia and Sardinia met at Paris and decided unanimously in favour of St George’s; but recommended, instead of the embankment of the natural channel, the formation of an artificial canal 17 ft. in depth closed by sluices at its junction with the river, and reaching the sea at some distance from the natural embouchure. The choice of St George’s made by this commission was adopted at Galatz in December 1858, and six of the seven representatives voted for its canalization; but owing to various political and financial considerations, it was ultimately decided to do nothing more in the meantime than render permanent and effective the provisional works already in progress at the Sulina mouth. These consisted of two piers forming a seaward prolongation of the fluvial channel, begun in 1858 and completed in 1861. The northern pier had a length of 4631 ft., the southern of 3000, and the depth of the water in which they were built varied from 6 to 20 ft. At the commencement of the works the depth of the channel was only 9 ft. but by their completion it had increased to 19 ft. The works designed and constructed by Sir Charles Hartley had in fact proved so successful that nothing more was ever heard of the St George’s project. In 1865 a new lighthouse was erected at the end of the north pier. The value of these early works of the commission is shown by the fact that of 2928 vessels navigating the lower Danube in 1855, 36 were wrecked, while of 2676 in 1865 only 7 were wrecked. In 1871 it was found expedient to lengthen the piers seaward, and in 1876 the south jetty was prolonged, so as to bring its end exactly opposite the lighthouse on the north pier. This resulted in an increase of the depth to 20½ ft., and for fifteen years, from 1879 to 1895, this depth remained constant without the aid of dredging. In 1894, owing to the constantly increasing size of vessels frequenting the Danube, it was found necessary to deepen the entrance still further, and to construct two parallel piers between the main jetties, reducing the breadth of the river to 500 ft., and thereby increasing the scour. There is now a continuous channel 24 ft. in depth, 5200 ft. in length, and 300 ft. in width between the piers, and 600 ft. outside the extremities of the piers, until deep water is reached in the open sea. This depth is only maintained by constant dredging. The engineers of the commission have been equally successful in dealing with the Sulina branch of the river. Its original length of 45 m. from St George’s Chatal to the sea was impeded at the commencement of the improvement works by eleven bends, each with a radius of less than 1000 ft., besides numerous others of somewhat larger radius, and its bed was encumbered by ten shifting shoals, varying from 8 to 13 ft. in depth at low water. By means of a series of training walls, by groynes thrown out from the banks, by revetments of the banks, and by dredging, all done with the view of narrowing the river, a minimum depth of 11 ft. was attained in 1865, and 13 ft. in 1871. In 1880 the needs of commerce and the increased size of steamers frequenting the river necessitated the construction of a new entrance from the St George’s branch. This work, designed in 1857, but unexecuted during a quarter of a century, owing to insufficiency of funds, was completed in 1882; and in 1886, after other comparatively short cuttings had been made to get rid of difficult bends and further to deepen the channel without having to resort to dredgers, the desired minimum depth of 15 ft. was attained. Since that date a series of new cuttings has been made. These have shortened the length of the Sulina canal by 11 nautical m., eliminated all the difficult bends and shoals, and provided an almost straight waterway 34 m. in length from Sulina to St George’s Chatal, with a minimum depth of 20 ft. when the river is at its lowest.

In the early days of the commission, i.e. from 1857 to 1860, the money spent on the works of improvement, amounting to about £150,000, was advanced as a loan by the then territorial power, Turkey; but in 1860 the commission began to levy taxes on vessels frequenting the river, and since then has repaid its debt to the Turkish government, as well as various loans for short periods, and a larger one of £120,000 guaranteed by the powers, and raised in 1868, mainly through the energy of the British commissioner, Sir John Stokes. This last loan was paid off in 1882 and the commission became free from debt in 1887. It has now an average annual income of about £80,000 derived from taxes paid by ships when[3] leaving the river. The normal annual expenditure amounts to about £56,000, while £24,000 is generally allotted to extraordinary works, such as new cuttings, &c. Between 1857 and 1905 a sum of about one and three quarter millions sterling was spent on engineering works, including the construction of quays, lighthouses, workshops and buildings, &c. Sulina from being a collection of mud hovels has developed into a town with 5000 inhabitants; a well-found hospital has been established where all merchant sailors receive gratuitous treatment; lighthouses, quays, floating elevators and an efficient pilot service all combine to make it a first-class port.