The courts have gradually evolved certain rules or principles for the proper assessment of damages, although extreme difficulty is found in their application to concrete cases. A distinction is drawn between general and special Measure of damages. damages. (1) General damage is that implied by law as necessarily flowing from the breach of right, and requiring no proof. (2) Special damage is that in fact caused by the wrong. Under existing practice this form of damage cannot be recovered unless it has been specifically claimed and proved, or unless the best available particulars or details have been before trial communicated to the party against whom it is claimed.
Contracts.—“The law imposes or implies a term that upon breach of contract damages must be paid.” The general tendency of legal decisions in cases of contract is (i.) to make the amount of damages which may be awarded a matter of legal certainty, (ii.) to leave to a jury or like tribunal little more to do than find the facts, (iii.) and to revise the assessment if it is clear that it has been made in disregard of the terms of the contract or of the natural and direct consequences of the breach. The measure of damage, general speaking, is the sum necessary to place the aggrieved party in the same position so far as money will do it as if the contract had been performed. If the breach is proved, but the person complaining has suffered no real damage, he is entitled to have his legal right recognized by an award of what are called nominal damages, i.e. a sum just sufficient to carry a judgment in his favour on the infraction of his rights. Nominal damages, it will therefore be seen, are not the same as “small damages.” He is, however, also entitled to prove and recover the special or particular damage lawfully attributable to the breach. Where the contract is to pay a fixed sum of money or liquidated amount, the measure of damages for non-payment is the sum agreed to be paid and interest thereon at the rate stipulated in the contract or recognized by law.
The law is the same in Scotland and in France (Civil Code, art. 1153). In some contracts the parties themselves fix the sum to be paid as damages if the contract is not fulfilled. These damages are described as liquidated, in Scots law stipulated or estimated. It would be supposed that the sum thus fixed would be the proper damages to be awarded. And under the French Civil Code (arts. 1152, 1153, 1780) the stipulation of the parties as to the damages to be paid for breach of a stipulation other than for paying a sum of money is binding on the courts. But in England, Scotland and the United States, courts disregard the words used, and inquire into the real nature of the transaction in order to see whether the sum fixed is to be treated as ascertained damage or as a penalty to be held in terrorem over the defaulter, and in the latter case, notwithstanding the stipulation, will require proof of the actual loss. In Kemble v. Farren (1829, 6 Bingham, 141), a contract between a manager and an actor provided that for a breach of any of the stipulations therein, the sum of £1000 should be payable by the defaulter, not as a penalty, but as liquidated and ascertained damages. Yet, the court, observing that under the stipulations of the contract the sum of £1000, if it were taken to be liquidated damages, might become payable for mere non-payment of a trifling sum, held that it was not fixed as damages, but as a penalty only. The case in which an agreed sum is most usually treated as a penalty is a bond to pay a fixed sum containing a condition that it shall be void if certain acts are done or a certain smaller sum paid. Another case is where a single lump sum is fixed as the liquidated amount of damage to be paid for doing or failing to do a number of different things of very varying degrees of importance (Elphinstone v. Monkland Iron Co., 1887, 11 A.C. 333). But the courts have accepted as creating a contractual measure of damage a stipulation to finish sewerage works by a given day (Law v. Redditch Local Board, 1892, 1 Q.B. 127); or to complete torpedo boats within a limited time for a foreign government (Clydebank Engineering Co. v. Yzquierda, 1905, A.C. 6). In this last case the law lords indicated that the provision of an agreed sum was peculiarly appropriate in view of the difficulty of showing the exact damage which a state sustains by non-delivery of a warship. Where the damage is not liquidated or agreed it is assessed to upon evidence as to the actual loss naturally and directly flowing from the breach of contract.
In contracts for the sale of goods the measure of damages is fixed by statute. Where the buyer wrongfully refuses or neglects to accept and pay for, or the seller wrongfully neglects or refuses to deliver the goods, the measure is the estimated loss directly and naturally resulting in the ordinary course of events from the buyer’s or seller’s breach of contract. Where there is an available market for the goods in question, the measure of damages is prima facie to be ascertained by the difference between the contract price and the market or current price at the time or times when the goods ought to have been accepted or delivered, or if no such time was fixed for acceptance or delivery, then at the time of refusal to accept or deliver (Sale of Goods Act 1893, §§ 50, 51).
Where there is no market, the value is fixed by the price of the nearest available substitute. Where the sufferer, at the request of the person in default, postpones purchase or sale, any increased loss thereby caused falls on the defaulter. If the buyer, before the time fixed for delivery, has resold the goods to a sub-vendor, he cannot claim against his own vendor any damages which the sub-vendor may recover against him for breach of contract, because he ought to have gone into the market and purchased other goods. But this is subject to modification in cases falling within the rule in Hadley v. Baxendale (1854, 9 Exchequer, 341). But trouble and expense incurred by the seller of finding a new purchaser or other goods may be taken account of in assessing the damages.
Where the goods delivered are not as contracted the buyer may as a rule sue the seller for a breach of warranty, or set it up as reduction of price. Where the warranty is of quality the loss is prima facie the difference between the value of the goods delivered when delivered and the value which they would have then had if they had answered to the warranty (Sale of Goods Act 1893, § 53). In an American case, where a person had agreed with a boarding-house keeper for a year, and quitted the house within the time, it was held that the measure of damages was not the price stipulated to be paid, but only the loss caused by the breach of contract. In contracts to marry, a special class of considerations is recognized, and the jury in assessing damages will take notice of the conduct of the parties. The social position and means of the defendant may be given in evidence to show what the plaintiff has lost by the breach of contract.
On a breach of contract to replace stock lent, the measure of damages is the price of the stock on the day when it ought to have been delivered, or on the day of trial, at the plaintiff’s option.
In contracts for the sale of realty, the measure of damage for breach by the vendor is the amount of any deposit paid by the would-be purchaser and of the expenses thrown away. But the purchaser may, in a proper case, obtain specific performance, and if he has been cheated may obtain damages in an action for deceit.
Breaches of trust are in a sense distinct from breaches of contract, as they fell under the jurisdiction of courts of equity and not of the common law courts. The rule applied was to require a defaulting trustee to make good to the beneficiaries any loss flowing from a breach of trust and not to allow him to set off against this liability any gain to the trust fund resulting from a different breach of trust or from good management (Lewin on Trusts, ed. 1904, 1146).
In estimating the proper amount to be assessed as damages for a breach of contract, it is not permissible to include every loss caused by the act or default upon which the claim for damages is based. The damage to be awarded must be that fairly and naturally arising from the breach under ordinary circumstances or the special circumstances of the particular contract, or in other words, which may reasonably be supposed to have been in the contemplation of the parties at the time of making the contract. The chief authority for this rule is the case of Hadley v. Baxendale (1854, 9 Exch. 341), which has been accepted in Scotland and the United States and throughout the British empire, and often differs little, if at all, from the rule adopted in the French civil code (art. 1150). In that case damages were sought for the loss of profits caused by a steam mill being kept idle, on account of the delay of the defendants in sending a new shaft which they had contracted to make. The court held the damage to be too remote, and stated the proper rule as follows:—