Once established in the country, the first thing to do is to form roads so as to secure communications with the neighboring villages and forests, and afterward to cut down trees for building houses. These latter are usually constructed, for these works, of untrimmed wood and mud, with thatched roof. There were thus constructed at Portao de Ferro a few kilometers of roads, then some houses for the engineers and special workmen, barracks for 200 laborers, stores, kitchens, etc., a forge, and a shop with a lathe and a saw run by a wheel at the side. It was afterward necessary to repair the old lateral canal which had been dug out of the rock in the times of the Royal Extraction, but which had been torn open for a considerable length. This necessitated the erection of tight walls of dry stone, grass, and mud, for a length of 200 meters, and with thicknesses of from 6 to 10 meters.

In order to divert the water into this canal, it was necessary to raise its level 5 meters. The dam, then, had to support a strong pressure, and it could not be built upon sand. It therefore became necessary to build a temporary dam and to turn the river into a plank flume, so as to make it possible to dig at the location of the permanent dam in order to reach a solid bottom at a depth of nearly 4 meters. The permanent dam thus had a total height of 10 meters, with a thickness of 15 at the base and 7 at the top. It was constructed of dry stone, grass, and earth, with the addition of strong wood-work. The rocks upon which it had to be built were full of fissures, and when it was desired to close it great leakages of water occurred, which came near ruining it and necessitated the construction of a second wall behind it and a talus of earth in front. The dam as shown in Fig. 1, when finished, had a thickness of 25 meters at the base. It was closed on the second of July, and had a storage capacity of 55,000 cubic meters.

The principal excavation was begun at the point where the bed was deepest, and which consequently the older miners must have had most trouble in reaching. Here were set up two Letestu pumps that were actuated by a four-horse wheel.

These pumps lifted 50 cubic meters per hour. All except the pump chambers and pipes was made of wood on the spot. The water that was lifted was carried away from the works in a flume 160 meters in length, which likewise removed the water from the motive wheels.

For the service of the same excavation two simple acting inclined planes were installed that were moved by a four-horse wheel. Fig. 2 gives a general view of the arrangement.

The tracks of these planes were made of wood. Steel rails, however, had been brought for the cars, along with the cables and the metallic parts of the windlass; but all else was made upon the spot, including all the wooden pulleys for transmitting motion from the wheel to the windlasses.

This excavation reached bottom at a depth of 16 meters. The second touched bottom at about 10 meters, and gave access to a subterranean canal, which was followed for about 20 meters. The extraction of sand was effected here by an inclined plane moved by a Gramme machine. The generatrix had to make 1,500 revolutions, and be set in motion by an overshot wheel. As time was wanting, it became necessary to diminish to as great a degree as possible the number of parts to be employed in the transmission of motion, and since there was an abundance of water, a velocity of 15 revolutions was accepted for the wheel, which, with a total fall of 4.8 meters, had to give a power of eight horses. A three meter pulley was placed upon the shaft of the wheel. This was made of freshly cut wood that had been exposed to the sun. In order to give it sufficient stability and prevent its warping, it was placed against the wheel in such a way as to rest upon the latter's spokes. This rendered it necessary to give up the idea of using a belt, since it was not possible to prevent its getting wet. Cords could not be found in the country, and so it was necessary to make use of a too heavy chain, which was in no wise intended for such a purpose, and which at a velocity of 15 revolutions began to swing and necessarily absorbed much power. The large pulley drove one of 0.4 m. upon an intermediate shaft. Upon this latter a 2.6 m. wooden pulley directly drove, through a belt, the 0.2 m. pulley of the generatrix.

From this may be judged what the country's resources are. The motor, by means of a belt, actuated a windlass provided with suitable checking gearings. The distance of the two machines was 116 meters. Save the transmission by chain, the whole worked in a satisfactory manner. The performance could only be estimated in a lump, by comparing on the one hand the theoretical work of the fall of water, and, on the other, that of the vertical elevation of the car; and, further, one was obliged to estimate the weight of the latter. If we allow 1,000 kilogrammes for the weight of a car that received 360 liters of dry sand or 300 of wet, the performance was 19 per cent., and appeared to be satisfactory, considering the conditions under which the installation was made. This experiment was at all events of such a nature as to indicate the use of these machines in cases where the arrangement of the locality absolutely necessitates a transmission of power.

The first workmen reached Portao de Ferro December 15, 1882, and the material shipped from France did not arrive until April 25, 1883. Operations were suspended about the 25th of September, since, for a fortnight already, there had no longer been any doubt as to the manner in which the river bed had been cleaned by former operators.

As a result of this first experiment, the proof remained that it would be easy in future exploitations to introduce into the country methods of work that are quicker and more economical than those now in use. In fact, all the operations were performed with natives of the country, with the exception of a carpenter and blacksmith from Rio Janeiro.—La Nature.