[C] ]Figures taken from typical cross-sections.
[D] This gives the actual amount of drilling done and powder used per cubic yard for the whole period of 5 months of observation, but as this length included 280 ft. of heading and only 220 ft. of bench, the average figures (for powder especially) are too low.
[Table 6] gives the rate and cost of drilling, and the cost of powder. It will be seen that the average rate of drilling was 2.71 ft. per hour per drill or 27.1 ft. per drill per shift.
[Table 7] shows the result of observation as to the time taken in various subdivisions of the drilling operations. These observations were not carried on for a long enough period to give correct results, but the percentages of time spent on each division of the operation are believed to be about right. The headings of this table are self-explanatory. The necessary delays include all time spent in changing bits, making air-line connections, etc. The unnecessary delays are stoppages caused by lack of supplies or insufficient air pressure.
By [Table 6] it will be noticed that the cost of labor for drilling and sharpening steels was about $0.29 per lin. ft. of hole drilled. The total cost, including repairs, supply of air, etc., came to about $0.38, as will be seen from [Table 8].
Timbering.—On the New York side nearly the whole length of the excavation needed timbering, to a greater or less extent, and for the most part required timbering of quite a heavy type.
TABLE 6.—Rock Tunnel Excavation under 32d Street, East of Cut-and-Cover Section. Drilling and Blasting.—Detailed Cost of Labor in Drilling, also Quantity and Cost of Powder Used.
| Drilling and Blasting. | Powder Used. | ||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Type. | Date. | Total feet drilled. | No. of drill shifts (10-hour.) | Feet drilled per man per hour. | Quantity of excavation, in cubic yards. | Cost of labor only. Drilling and sharpening. | Total Quantity. | Cost per cubic Yard at 11 cents per pound. | |||||||||||
| Total. | Per linear feet. | Per cubic yard | |||||||||||||||||
| Actual. | Paid for. | Actual. | Paid for | ||||||||||||||||
| 1907 | Heading | Bench | Total | Heading | Bench | Total | Heading | Bench | Total | Actual.[E] | Paid for[F] | Pounds. | |||||||
| $ | $ | $ | $ | $ | $ | ||||||||||||||
| Ke. | May | 2,971 | 5,578 | 8,549 | 98 | 204 | 302 | 3.031 | 2.734 | 2.831 | 1,736 | 1,664 | 2,331 | 0.27 | 1.34 | 1.40 | 1,595 | 0.10 | 0.10 |
| June | 2,093 | 6,194 | 8,287 | 85 | 223 | 308 | 2.462 | 2.777 | 2.691 | 809 | 698 | 2,440 | 0.29 | 3.01 | 3.49 | 1,960 | 0.27 | 0.31 | |
| July | 7,627 | 7,627 | 268 | 268 | 2.845 | 2.845 | 1,022 | 960 | 2,031 | 0.26 | 1.98 | 2.11 | 966 | 0.10 | 0.11 | ||||
| Aug. | 2,552 | 2,552 | 95 | 95 | 2.688 | 2.688 | 743 | 716 | 640 | 0.25 | 0.86 | 0.89 | 430 | 0.06 | 0.07 | ||||
| Sept. | 2,133 | 2,133 | 79 | 79 | 2.700 | 2.700 | 238 | 238 | 533 | 0.25 | 2.24 | 2.24 | 280 | 0.13 | 0.13 | ||||
| Total | 5,064 | 24,084 | 29,148 | 183 | 869 | 1,052 | 2.767 | 2.770 | 2.770 | 4,548 | 4,276 | 7,975 | 0.27 | 1.75 | 1.87 | 5,231 | 0.13 | 0.13 | |
| Ki. | May | 6,976 | 6,976 | 216 | 216 | 3.229 | 3.229 | 614 | 527 | 1,604 | 0.23 | 2.61 | 3.04 | 1,230 | 0.22 | 0.26 | |||
| June | 4,089 | 4,089 | 135 | 135 | 3.029 | 3.029 | 357 | 259 | 1,234 | 0.30 | 3.45 | 4.76 | 1,036 | 0.32 | 0.44 | ||||
| July | 3,733 | 3,733 | 140 | 140 | 2.666 | 2.666 | 530 | 404 | 1,084 | 0.29 | 2.04 | 2.68 | 550 | 0.11 | 0.15 | ||||
| Aug. | 6,715 | 6,715 | 249 | 249 | 2.769 | 2.769 | 925 | 890 | 1,901 | 0.28 | 2.05 | 2.13 | 905 | 0.10 | 0.11 | ||||
| Estim | 14,742 | 14,742 | 46 | 546 | 2.700 | 2.700 | 3,254 | 2,908 | 4,570 | 0.31 | 1.40 | 1.57 | 2,470 | 0.08 | 0.09 | ||||
| Total | 11,065 | 25,190 | 36,255 | 351 | 935 | 1,286 | 3.152 | 2.694 | 2.819 | 5,680 | 4,988 | 10,393 | 0.29 | 1.83 | 2.08 | 6,191 | 0.12 | 0.14 | |
| Ko. | May | 1,617 | 1,617 | 55 | 55 | 2.921 | 2.921 | 250 | 188 | 471 | 0.29 | 1.88 | 2.50 | 376 | 0.17 | 0.22 | |||
| June | 2,948 | 2,948 | 107 | 107 | 2.755 | 2.755 | 496 | 347 | 883 | 0.29 | 1.78 | 2.54 | 357 | 0.08 | 0.11 | ||||
| July | 3,734 | 3,734 | 131 | 131 | 2.850 | 2.850 | 626 | 606 | 1,003 | 0.27 | 1.60 | 1.65 | 609 | 0.11 | 0.11 | ||||
| Aug. | 8,260 | 8,260 | 290 | 290 | 2.848 | 2.848 | 709 | 2,161 | 0.26 | 3.00 | 3.04 | 918 | 0.14 | 0.14 | |||||
| Estim | 4,787 | 4,787 | 285 | 285 | 1.180 | 1.680 | 605 | 535 | 2,397 | 0.50 | 3.96 | 4.48 | 762 | 0.14 | 0.16 | ||||
| Total | 21,346 | 21,346 | 868 | 868 | 2.460 | 2.460 | 2,695 | 2,385 | 6,915 | 0.32 | 2.57 | 2.90 | 3,022 | 0.12 | 0.14 | ||||
| Grand Total | 16,129 | 70,620 | 86,749 | 534 | 2,672 | 3,206 | 3.020 | 2.710 | 2.710 | 12,923 | 11,649 | 25,283 | 0.29 | 1.96 | 2.17 | 14,444 | 0.12 | 0.14 | |
The work done during the 5 months when these analyzed cost figures were kept includes 280 ft. of bench and 220 ft. of heading. This excess of bench over heading causes the general average amounts per cubic yard to be too low.
[E]Actual amount of excavation.