Excavation of Weehawken Rock Tunnels.—This subject may be dismissed in a few words, as very few features of interest were called into play. The rock was of good quality, being the sandstone typical of this part of the country. Little or no timbering was needed, there were no buildings above the tunnel to be taken care of, and large charges of powder could be used.
TABLE 9.— Supplementary Analysis of Timbering, Rock Tunnel Excavation Under 32d Street, East of Cut-and-Cover Section. Analyzed Cost of Timbering, per Foot Run and per Bent.
| Ke | |||
|---|---|---|---|
| Per foot run of tunnel | Per bent, 3 ft, 6 in., center to center | Per cubic yard excavation | |
| PERMANENT TIMBERING. | |||
| Lumber in feet, B. M. | |||
| Upper Bent. | 274 | 685 | 7.8 |
| Blocking. | 294 | 735 | 8.3 |
| Total. | 568 | 1,420 | 16.1 |
| Cost, in dollars. | |||
| Lumber. | 23.75 | 59.38 | 0.67 |
| Labor. | 37.50 | 93.75 | 1.06 |
| Total. | 61.25 | 153.13 | 1.73 |
| TEMPORARY TIMBERING. | |||
| Lumber in feet, B. M. | |||
| Lower Bent. | 479 | 11.97 | 13.6 |
| Blocking. | 193 | 483 | 5.5 |
| Total. | 672 | 16.80 | 19.1 |
| Cost, in dollars. | |||
| Lumber. | 29.13 | 72.81 | 0.82 |
| Erection labor. | 28.85 | 72.13 | 0.82 |
| Removal labor. | 8.29 | 20.73 | 0.23 |
| Total labor. | 37.14 | 92.86 | 1.05 |
| Total. | 66.27 | 165.67 | 1.87 |
| GRAND TOTAL. | |||
| Lumber in feet, B. M. | 1,240 | 3,100 | 35.2 |
| Cost, in dollars. | |||
| Lumber. | 52.88 | 132.19 | 1.49 |
| Labor. | 74.64 | 186.61 | 3.60 |
| Total. | 127.52 | 318.80 | |
| Ki | |||
| Per foot run of tunnel | Per bent, 3 ft, 6 in., center to center | Per cubic yard excavation | |
| PERMANENT TIMBERING. | |||
| Lumber in feet, B. M. | |||
| Upper Bent. | 227 | 830 | 5.3 |
| Blocking. | 164 | 601 | 3.8 |
| Total. | 391 | 1,431 | 9.1 |
| Cost, in dollars. | |||
| Lumber. | 16.84 | 61.56 | 0.39 |
| Labor. | 12.82 | 46.88 | 0.30 |
| Total. | 29.66 | 108.44 | 0.69 |
| TEMPORARY TIMBERING. | |||
| Lumber in feet, B. M. | |||
| Lower Bent. | 186.33 | 681.25 | 4.33 |
| Blocking. | 42.80 | 156.50 | 0.99 |
| Total. | 229.13 | 837.75 | 5.32 |
| Cost, in dollars. | |||
| Lumber. | 9.65 | 35.31 | 0.22 |
| Erection labor. | 10.38 | 37.97 | 0.24 |
| Removal labor. | 9.74 | 34.09 | 0.23 |
| Total labor. | 20.12 | 72.06 | 0.47 |
| Total. | 29.77 | 107.37 | 0.69 |
| GRAND TOTAL. | |||
| Lumber in feet, B. M. | 6.20 | 22.69 | 14.4 |
| Cost, in dollars. | |||
| Lumber. | 26.49 | 96.87 | 0.61 |
| Labor. | 32.94 | 118.94 | 0.77 |
| Total. | 59.43 | 215.81 | 1.38 |
| Ko | |||
| Per foot run of tunnel | Per bent, 3 ft, 6 in., center to center | Per cubic yard excavation | |
| PERMANENT TIMBERING. | |||
| Lumber in feet, B. M. | |||
| Upper Bent. | 261 | 962 | 4.1 |
| Blocking. | 408 | 1,508 | 6.5 |
| Total. | 669 | 24.70 | 10.5 |
| Cost, in dollars. | |||
| Lumber. | 28.00 | 103.38 | 0.44 |
| Labor. | 29.79 | 110.00 | 0.47 |
| Total. | 57.79 | 213.38 | 0.91 |
| TEMPORARY TIMBERING. | |||
| Lumber in feet, B. M. | |||
| Lower Bent. | 350 | 1,291 | 5.5 |
| Blocking. | 61 | 227 | 1.0 |
| Total. | 411 | 1,518 | 6.5 |
| Cost, in dollars. | |||
| Lumber. | 18.45 | 68.16 | 0.29 |
| Erection labor. | 20.83 | 76.92 | 0.33 |
| Removal labor. | 12.16 | 44.59 | 0.19 |
| Total labor. | 32.99 | 121.51 | 0.52 |
| Total. | 51.44 | 189.67 | 0.81 |
| GRAND TOTAL. | |||
| Lumber in feet, B. M. | 1,080 | 3,988 | 17.1 |
| Cost, in dollars. | |||
| Lumber. | 46.45 | 171.54 | 0.73 |
| Labor. | 62.78 | 231.50 | 0.99 |
| Total. | 109.23 | 403.04 | 1.72 |
TABLE 10.—Timbering:—Detailed Cost of Timber, Labor, and Superintendence. Rock Tunnel Excavation under 32d Street, East of Cut-and-Cover Section.
| Date. | Timber Used, in Feet, B. M. | Excavation in Cubic Yards. | Cost of Timber. | Cost of Labor. | Total Cost. | Cost per Cubic Yard (Actual). | Cost per Cubic Yard (Paid for). | Cost, per 1,000 Ft., B. M., of Total Timber. | ||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Main timber. | Blocking timber. | Total timber. | Actual. | Paid for. | Main. | Block. | Total. | Timber. | Labor. | Total. | Timber. | Labor. | Total. | Total timber. | Labor. | Total. | ||||
| 1907 | a | b | c | d | e | f | g | h | i | j | h / d | i / d | j / d | h / e | i / e | j / e | h / c | i / c | j / c | |
| Ke | May | 18,016 | 15,234 | 33,250 | 1,736 | 1,664 | $810 | $565 | $1,375 | $1,792 | $3,167 | $0.79 | $1.03 | $1.82 | $0.82 | $1.07 | $1.90 | $41.35 | $53.89 | $95.24 |
| June | 14,048 | 11,528 | 25,576 | 809 | 698 | 680 | 457 | 1,087 | 1,576 | 2,663 | 1.34 | 1.95 | 3.29 | 1.55 | 2.25 | 3.81 | 42.50 | 61.62 | 104.12 | |
| July | 20,092 | 7,339 | 27,431 | 1,022 | 960 | 900 | 300 | 1,200 | 1,580 | 2,780 | 1.16 | 1.55 | 2.72 | 1.25 | 1.64 | 2.89 | 43.74 | 57.60 | 101.34 | |
| August | 6,485 | 2,632 | 9,117 | 743 | 716 | 290 | 110 | 400 | 300 | 700 | 0.53 | 0.40 | 0.94 | 0.57 | 0.41 | 0.98 | 43.87 | 32.90 | 76.77 | |
| Sept. | 1,632 | 2,224 | 3,856 | 238 | 238 | 73 | 94 | 167 | 60 | 227 | 0.70 | 0.25 | 0.95 | 0.70 | 0.25 | 0.95 | 43.31 | 15.56 | 58.87 | |
| Removal | 663 | 663 | ||||||||||||||||||
| Total | 60,273 | 38,957 | 99,230 | 4,548 | 4,276 | $2,703 | $1,526 | $4,229 | $5,971 | $10,200 | $0.91 | $1.51 | $2.22 | $1.00 | $1.40 | $2.40 | $42.62 | $60.19 | $102.81 | |
| Ki | May | 3,537 | 3,537 | 614 | 527 | $150 | $150 | $100 | $250 | $0.24 | $0.16 | $0.40 | $0.28 | $0.19 | $0.47 | $42.41 | $28.27 | $70.68 | ||
| June | 300 | 300 | 357 | 259 | $14 | 14 | 44 | 58 | 0.04 | 0.12 | 0.16 | 0.05 | 0.17 | 0.22 | 46.66 | 146.33 | 193.33 | |||
| July | 7,776 | 5,811 | 13,587 | 530 | 404 | 350 | 233 | 583 | 525 | 7,108 | 1.10 | 0.99 | 2.09 | 1.44 | 1.30 | 2.74 | 42.91 | 38.64 | 81.54 | |
| August | 19,712 | 5,702 | 25,414 | 925 | 890 | 887 | 220 | 1,107 | 1,018 | 2,125 | 1.20 | 1.10 | 2.30 | 1.24 | 1.14 | 2.38 | 43.56 | 40.06 | 83.61 | |
| Sept. | 20,556 | 9,218 | 29,774 | 1,585 | 1,501 | 925 | 325 | 1,250 | 1,028 | 2,278 | 0.79 | 0.65 | 1.44 | 0.83 | 0.68 | 1.51 | 41.98 | 34.53 | 76.51 | |
| Removal | 1,669 | 1,407 | 1,139 | 1,139 | 0.68 | 0.68 | 0.81 | 0.81 | ||||||||||||
| Total | 48,344 | 24,268 | 72,612 | 5,680 | 4,988 | $2,176 | $928 | $3,104 | $3,854 | $6,958 | $0.55 | $0.68 | $1.23 | $0.63 | $0.77 | $1.40 | $42.75 | $53.09 | $95.84 | |
| Ko | May | 4,332 | 8,788 | 13,120 | 250 | 188 | $175 | $366 | $561 | $303 | $864 | $2.24 | $1.21 | $3.45 | $3.00 | $1.61 | $4.61 | $42.76 | $23.10 | $65.86 |
| June | 7,132 | 10,017 | 17,149 | 496 | 347 | 324 | 396 | 720 | 562 | 1,282 | 1.45 | 1.18 | 2.58 | 2.07 | 1.61 | 3.68 | 41.98 | 32.77 | 74.75 | |
| July | 3,070 | 200 | 3,270 | 626 | 606 | 134 | 10 | 144 | 156 | 300 | 0.23 | 0.25 | 0.48 | 0.23 | 0.26 | 0.49 | 44.04 | 47.70 | 91.74 | |
| August | 10,704 | 2,102 | 12,806 | 718 | 709 | 481 | 80 | 561 | 727 | 1,288 | 0.78 | 1.01 | 1.79 | 0.80 | 1.02 | 1.82 | 43.80 | 56.77 | 100.57 | |
| Sept. | 2,400 | 245 | 2,645 | 396 | 324 | 108 | 8 | 116 | 400 | 516 | 0.29 | 1.01 | 1.30 | 0.36 | 1.23 | 1.59 | 43.85 | 151.23 | 195.08 | |
| Removal | 209 | 211 | 535 | 535 | 2.56 | 2.56 | 2.54 | 2.54 | ||||||||||||
| Total | 27,638 | 21,352 | 48,990 | 2,695 | 2,385 | $1,242 | $860 | $2,102 | $2,683 | $4,785 | $0.78 | $1.00 | $1.78 | $0.88 | $1.12 | $2.00 | $42.91 | $54.75 | $97.65 | |
| Grand total | 136,255 | 84,577 | 220,832 | 12,923 | 11,649 | $6,121 | $3,314 | $9,435 | $12,508 | $21,943 | $0.73 | $0.97 | $1.70 | $0.81 | $1.07 | $1.88 | $42.73 | $56.65 | $99.38 | |
Work was begun on September 1st, 1904, immediately on the completion of the work on the shaft. The North and South Tunnels in this case are completely independent, as will be seen from [Plate XXXIV]. The procedure adopted was to drive a top heading on the center line of each tunnel and to break down the bench from this. The drilling was at first supplied with steam power from a temporary plant, as the contractor was at that time installing his permanent plant, which was finished at the end of November, 1904. At this time the rate of advance averaged 3½ lin. ft. of full section per day of 24 hours. By the end of January the Weehawken rock tunnels were completely excavated, and by the middle of April, 1905, the excavation for the shield chambers was finished; the erection of the shields was started at the end of that month.
| Grade. | Total No. | Rate per day. | Drilling and blasting: No. | Mucking: No. | Timbering: No. |
|---|---|---|---|---|---|
| Superintendent | 1 | $7.70 | ½ | ⅛ | ⅜ |
| Assistant engineer | 1 | 5.80 | ½ | ⅛ | ⅜ |
| Electrician | 1 | 3.50 | ½ | ⅛ | ⅜ |
| Engineer | 1 | 3.50 | 1 | ||
| Signalman | 1 | 2.00 | 1 | ||
| Foreman | 3 | 4.00 | 1 | 1 | 1 |
| Driller | 5 | 3.00 | 5 | ||
| Driller's helper | 5 | 2.00 | 5 | ||
| Laborers | 14 | 2.00 | 14 | ||
| Timbermen | 3 | 3.00 | 3 | ||
| Timbermen's helpers | 4 | 2.00 | 4 | ||
| Machinist | 1 | 4.00 | 1 | ||
| Blacksmith | 2 | 3.50 | 2 | ||
| Blacksmith's helper | 2 | 2.00 | 2 | ||
| Nipper | 2 | 2.00 | 2 | ||
| Waterboy | 1 | 2.00 | 1 | ||
| Total | 47 | 20½ | 17⅜ | 9⅛ |