Costs.

During the work, careful records of the actual cost to the contractor of carrying out this work were kept by the Company's forces; these costs include all direct charges, such as labor and materials, and all indirect charges such as head office, plant depreciation, insurance, etc., but do not include the cost of any financing, of which the Company had no information.

TRANS. AM. SOC. CIV. ENGRS.
VOL. LXVIII, No. 1155.
HEWETT AND BROWN ON
PENNSYLVANIA R. R. TUNNELS: NORTH RIVER TUNNELS.

Click to view larger image.

TABLE 33.— Average Force per Shift for Transportation in Two Tunnels.

LocationGradeRateWork in Progress
Two inverts and two duct benchesTwo arches, two inverts, and two duct benchesFour arches and one face of bench
TunnelForeman$3.00222
Laborer 1.75242870
Switchmen 2.0022
Hoisting engineers 3.00245
SurfaceForeman 3.00112
Laborers 1.758815
Teams 6.50112

Field Engineering Staff.