81. The foundations for all structures shall be executed by the contractor for masonry in such manner and to such depth as to secure a safe and secure foundation, of which the engineer will judge. If a natural foundation cannot be procured at a reasonable depth, then the contractor shall prepare such artificial foundation as the engineer may direct. The stuff moved from the foundations, if of the proper quality, shall be deposited in the adjoining embankment, provided the site for said embankment has been cleared of all perishable material. So much of the stuff as shall not be fit for the embankment, and all roots, stumps, etc., shall be deposited beyond the limits of the clearing, so as not to obstruct roads, watercourses, or ditches.

For the earth moved from such foundations, and for all earth used according to direction, in the construction of coffer-dams, there shall be paid —— cents per cubic yard.

Whenever it may be necessary to pump or bale water in the foundations, the contractor shall furnish the pumps or buckets, and all scaffolding and apparatus necessary to work them. He shall be allowed the net cost of all labor employed in the operations of pumping or baling water, and shall make a monthly return to the engineer of the value of such labor, provided that these operations are conducted in an economical manner, with efficient men, pumps, and tools, under the direction and to the satisfaction of the engineer. He shall also be allowed such compensation for the use of the pumps and apparatus, and for superintendence, as the engineer shall judge to be fair and reasonable.

TRESTLE WORK.

82. Includes all wooden structures commonly used as substitutes for abutments and piers, and for farm passes, etc., etc. These shall be built according to the plans furnished, and directions given by the engineer, of sound, durable material, to be approved by him. The price bid shall be by the thousand feet board measure, and will be considered as in full for all material except iron, and for the labor of building and erecting complete. The iron used will be of the best American, and the workmanship of approved quality. The bids will be by the pound, and will cover all cost of material and the labor incident to its use. Spikes and nails when used will be furnished by the contractor at cost.

BRIDGING.

83. Contractors may submit plans for bridging in connection with, or separate from their bids; but the engineer of the company may reject such plans if he choose, and substitute others, which if the contractor decline building at the approved prices, may be let to other parties. In every case, the exact manner of building, erecting, adjusting, and finishing bridges, and the determination of the nature and amount of material, will be specified by the engineer. The price bid must be by the running foot of the whole length of bridge, as erected and finished complete.

84. Specifications for Superstructure.

SUBSILLS.

To maintain the track in good adjustment until embankments are settled, subsills will be laid on certain banks, and likewise in cuts where the imperfect nature of the bottoming may, in the opinion of the engineer, render them expedient. These subsills to be fairly bedded in the earth or ballasting, and carefully adjusted and rammed so as to correspond with the grade lines given by the engineer. An additional piece of sill, four feet long, shall be laid at each joint of the subsill, either under the sill, or alongside, as may be directed. The sills will be of 3 × 9 plank, in length of twelve, fifteen, eighteen, and twenty-one feet; of which one fourth may be below fifteen, one fourth below eighteen, and one fourth below twenty-one feet. The plank must be square at the ends, and of sound, durable material, and not have more than two inches wane on one end only. There will be about 25,000 feet, board measure, laid per mile where it may be required, and 660 joint sills, 3 × 9 inches, and four feet long. When the depth of stuff to be moved to admit the subsills exceeds six inches, an allowance shall be made for extra labor, the amount of which shall be noted by the assistants on their receiving notice of such extra labor from the contractor or his agent.