1 crusher, No. 7 Gates$12,000
Use of locomotive2,200
Car and track5,300
3 mixers3,000
Lumber1,200
Pipe720
Small tools1,000
———
Total$25,420

This $25,420 distributed over the 44,811 cu. yds. of concrete amounts to 57 cts. per cu. yd.

It will be noted that 2 mixers were kept busy. Their average output was 100 cu. yds. each per day, which is the same as for the mixers on Section 14.

The total cost of concrete on Section 15 was as follows:

Per cu. yd.
Labor quarrying, crushing and mixing$0.991
Explosives0.083
Utica cement, at $0.60 per bbl.0.930
Portland cement, at $2.25 per bbl.0.180
Sand, at $1.35 per cu. yd.0.476
———
Total$2,660
First cost of plant$0.567

It is not strictly correct to charge the full first cost of the plant to the work as it possessed considerable salvage value at the end.

Comparison.—For the purpose of comparing Sections 14 and 15 the following summary is given of the cost per cubic yard of concrete:

Sec. 14.Sec. 15.
General force$0.078$0.082
Wall force0.1080.116
Mixing force0.1210.250
Timbering force0.1500.140
Hauling force0.1420.081
Crushing force0.0730.128
Quarry force0.3030.275
Cement, natural0.8630.930
Cement, Portland0.3050.180
Sand0.4650.476
Plant (full cost)0.4070.567
——————
Total$3.015$3.225

It should be remembered that on Section 14 there was no drilling and blasting of the rock, but that the "quarry force" not only loaded but hauled the stone to the crusher. The cost of mixing on Section 15 is higher than on Section 14 because the materials were dumped on platforms and shoveled into the mixer, instead of being discharged from bins into the mixer as on Section 14.