Materials and Supplies:
No. 1 hemlock matched per M. ft.$20
No. 1 hemlock plank per M. ft.17
No. 2 Norway pine flooring per M. ft.19
No. 2 yellow pine flooring per M. ft.20
12×12-in.×16-ft. yellow pine per M. ft.29
12×12-in.×24-ft. yellow pine, piling per M. ft.27
Maple wedges per pair50 cts.
½-in. corrugated bars per lb.2.615 cts.
¾-in. corrugated bars per lb.2.515 cts.
⅞-in. corrugated bars per lb.2.515 cts.
Coal per ton$4
Electric power per kilowatt6 cts.
Medusa cement per bbl.$1.75
Aetna cement per bbl.1.05
Bank gravel per cu. yd.0.85
Sand per cu. yd.0.66
Carpenters per day$3 to 3.50
Common labor per day1.75

The summarized cost of the whole work, with such detailed costs as the figures given permit of computation, was as follows:

General Service:Total.Per cu. yd.
Engineering$451$0.512
Miscellaneous750.084
Pumping:Total 110 days.
Coal at $4 per ton$210
Machinery, tools and cartage283
Labor497
——
Total$990

This gives a cost of $9 per day for pumping.

Excavation:Total cost.P. C. Total.
Timber cartage, etc.$ 37517.6
Tools693.3
Labor at $1.751,68779.1
—————
Total$2,131100.0
Filling 5,711 cu. yds.:Total.Per cu. yd.
Earth$1,142$0.20
Labor including riprapping3960.07
—————
Total$1,538$0.27
Removing Old Wing Walls:Total.
Labor and dynamite$ 346
Tools and sharpening64
——
Total$ 410
Hand Rail, 150 ft.:Total.Per lin. ft.
Material$ 278$1.85
Labor290.19
————
Total$ 307$2.04
Wood Block Pavement, 296 sq. yds.:Total.Per sq. yd.
Labor570.19
————
Total$ 752$2.54
Steel, 62,000 lbs.:Total.Per lb.
Corrugated bars, freight, etc.$1,4982.41 cts.
Plain steel, wire, etc.750.12 cts.
Blacksmithing, tools and placing4380.71 cts.
—————
Total$2,0113.24 cts.
Centering:Total.Concrete.
Per cu. yd.
Lumber and piles$ 332$1.14
Labor2720.95
————
Total$ 604$2.09
Total.Per cu. yd.
Forms$ 3,312$ 3.75
Concrete5,5326.25
——————
Grand total$18,113$20.50

In more detail the cost of the various items of concrete work was as follows for the whole structure, including abutments, wing walls and arch containing 884 cu. yds.:

Form Construction:Total.Per cu. yd.
Lumber and cartage$1,547$1.75
Nails and bolts1290.15
Tools1100.12
Labor, erecting and removing1,5261.72
—————
Total$3,312$3.74
Concrete Construction.
Materials:
Aetna cement at $1.05$1,218$1.37
Medusa cement at $1.754990.56
Sand at 66 cts. per cu. yd.370.04
Gravel at 85 cts. per cu. yd.9151.04
—————
Total materials$2,669$3.01
Mixing:
Machinery and supplies$ 549$0.62
Power at 6 cts. per kw.520.06
Tools220.02
Labor7370.83
————
Total mixing$1,360$1.53
Placing concrete$ 609$0.69
Tamping concrete$ 481$0.54
Heating Concrete:
Apparatus and cartage$ 47$0.05
Fuel960.11
Labor2700.31
————
Total heating$ 413$0.47
Grand total$8,844$9.98