The above rate is based on figures of 30c per hour. For other rates the following will apply in addition: At 35c per hour add 17%; at 40c add 34%; at 45c add 51%; and at 50c per hour add

Example:
(A) Take 1,000 feet of hardwood floor to be cleaned at 50c per hour =
$54.00 + $36.72 = $90.72
Looking again we find it would take 180 hours at 50c per hour = $90.00

(B) Take 1,000 feet of joists to be placed at 50c per hour = $6.00 +
14.08 = $10.08.
Looking for the hours we find it would take 20 at 50c, or $10.00.

83. Total Building Costs by Percentages.—Having carefully estimated the costs of one or two of the large items in a building, such as lumber or millwork or labor, the total cost of a building may be approximated with a fair degree of accuracy by a general contractor by means of the following table of percentages. Foundations or any other parts of a building which may be unusual should be excluded and figured separately in detail. In any event, before a building is finally completed the contractor will have to settle with each sub-contractor upon the basis of detailed cost estimates. Where time is available, the contractor as a rule secures bids from the various sub-contractors, such as the plumber, the lather, the mason, etc., combining these and adding his commission of 10% for oversight, and an additional 10% for incidentals or contingencies.

COSTS BY PERCENTAGES

ItemsFrame
Building
Brick
Dwelling
Excavation, brick and cut stone16%36%
Plastering and materials, including lathing86
Millwork including glass and glazing2120
Lumber1912
Carpentry labor1810
Hardware3½3
Tinwork and galvanized iron2½4½
Plumbing and gas fitting and materials73
Painting and materials55½
Heating (not included)
Total100%100%

Example:
A lumber bill for a given frame house is found to "figure" $500,
determine the approximate cost of the various sub-contracts, and
for the house as a whole.
Solution:

$500 = 19% of the total cost.
Total cost = $2632 (exclusive of heating).
Excavation, brick and cement work = 16% of $2632= $421.12
Plastering = 8% of $2632= 210.56
Millwork and glazing = 21% of $2632= 552.72
Carpentry labor = 18% of $2632= 473.76
Hardware = 3½% of $2632= 92.12
Tinwork = 2½% of $2632= 65.80
Plumbing = 7% of $2632= 184.24
Painting = 5% of $2632= 131.60
Lumber= 500.00
$2631.92

To this must be added heating, electric wiring, electric and gas fixtures, window shades, cement walks, sewerage, grading, decoration of walls, architect's fee and contractor's commission.

For furnace heat, add 6 to 7% ; for steam, add 8 to 10% ; for hot water, add 10 to 12% additional.