The above rate is based on figures of 30c per hour. For other rates the following will apply in addition: At 35c per hour add 17%; at 40c add 34%; at 45c add 51%; and at 50c per hour add

Example:
(A) Take 1,000 feet of hardwood floor to be cleaned at 50c per hour =
$54.00 + $36.72 = $90.72
Looking again we find it would take 180 hours at 50c per hour = $90.00

(B) Take 1,000 feet of joists to be placed at 50c per hour = $6.00 +
14.08 = $10.08.
Looking for the hours we find it would take 20 at 50c, or $10.00.

83. Total Building Costs by Percentages.—Having carefully estimated the costs of one or two of the large items in a building, such as lumber or millwork or labor, the total cost of a building may be approximated with a fair degree of accuracy by a general contractor by means of the following table of percentages. Foundations or any other parts of a building which may be unusual should be excluded and figured separately in detail. In any event, before a building is finally completed the contractor will have to settle with each sub-contractor upon the basis of detailed cost estimates. Where time is available, the contractor as a rule secures bids from the various sub-contractors, such as the plumber, the lather, the mason, etc., combining these and adding his commission of 10% for oversight, and an additional 10% for incidentals or contingencies.

COSTS BY PERCENTAGES

ItemsFrame
Building
Brick
Dwelling
Excavation, brick and cut stone16%36%
Plastering and materials, including lathing86
Millwork including glass and glazing2120
Lumber1912
Carpentry labor1810
Hardware3
Tinwork and galvanized iron
Plumbing and gas fitting and materials73
Painting and materials5
Heating (not included)
Total100%100%

Example:
A lumber bill for a given frame house is found to "figure" $500,
determine the approximate cost of the various sub-contracts, and
for the house as a whole.
Solution:

$500 = 19% of the total cost.
Total cost = $2632 (exclusive of heating).
Excavation, brick and cement work = 16% of $2632= $421.12
Plastering = 8% of $2632= 210.56
Millwork and glazing = 21% of $2632= 552.72
Carpentry labor = 18% of $2632= 473.76
Hardware = 3½% of $2632= 92.12
Tinwork = 2½% of $2632= 65.80
Plumbing = 7% of $2632= 184.24
Painting = 5% of $2632= 131.60
Lumber= 500.00
$2631.92

To this must be added heating, electric wiring, electric and gas fixtures, window shades, cement walks, sewerage, grading, decoration of walls, architect's fee and contractor's commission.

For furnace heat, add 6 to 7% ; for steam, add 8 to 10% ; for hot water, add 10 to 12% additional.