| Material. | Method. | Station: | Date: | Number of days. | Linear Feet. | Rate of progress in feet per day. | Remarks. | ||
| From | To | From | To | ||||||
| All rock | Bottom heading | 69+39.9 | 69+79 | Aug. 2, '06 | Sept 25, '06 | 54 | 39.1 | 0.724 | |
| All rock | Center heading | 69+79 | 70+64 | Sept 25, '06 | Nov. 21, '06 | 57 | 85 | 1.49 | |
| Earth and rock | Center heading | 70+64 | 71+34 | Nov. 21, '06 | Dec. 30, '06 | 39 | 70 | 1.79 | |
| Earth and rock | Bottom heading | 71+34 | 71+89 | Dec. 30, '06 | Feb. 13, '07 | 45 | 55 | 1.22 | |
| All rock | Bottom heading | 71+89 | 72+11 | Feb. 13, '07 | Feb. 21, '07 | 8 | 22 | 2.75 | |
| Earth and rock | Center heading | 72+11 | 72+67 | Feb. 21, '07 | Mar. 19, '07 | 26 | 56 | 2.15 | |
| All rock | Center heading | 72+67 | 76+54 | Mar. 19, '07 | Sept 6, '07 | 171 | 387 | 2.26 | |
| Earth and rock | Going out of rock | 76+54 | 77+24 | Sept 6, '07 | Oct. 4, '07 | 28 | 70 | 2.50 | |
| All earth | Soft ground | 77+24 | 90+57.3 | Oct. 4, '07 | Mar. 26, '08 | 174 | 1,333.3 | 7.66 | |
Line B, Long Island.
| Material. | Method. | Station: | Date: | Number of days. | Linear Feet. | Rate of progress in feet per day. | Remarks. | ||
| From | To | From | To | ||||||
| All rock | Bottom heading | 69+29.6 | 70+46 | Oct. 16, '06 | Nov. 20, '06 | 35 | 116.4 | 3.33 | |
| Earth and rock | Bottom heading | 70+46 | 71+95 | Nov. 20, '06 | Feb. 23, '07 | 95 | 149 | 1.57 | |
| All rock | Bottom heading | 71+95 | 72+25 | Feb. 23, '07 | Mar. 6, '07 | 11 | 30 | 2.73 | |
| Earth and rock | Center heading | 72+25 | 72+60 | Mar. 6, '07 | Mar. 24, '07 | 18 | 35 | 1.94 | |
| All rock | Going out of rock | 72+60 | 76+57 | Mar. 24, '07 | Aug. 7, '07 | 136 | 397 | 2.92 | |
| Earth and rock | Soft ground | 76+57 | 77+30 | Aug. 7, '07 | Sept 5, '07 | 29 | 73 | 2.52 | |
| All earth | Soft ground | 77+30 | 90+49.6 | Sept 5, '07 | Mar. 19, '08 | 196 | 1,319.6 | 6.73 | |
Line C, Long Island.
| Material. | Method. | Station: | Date: | Number of days. | Linear Feet. | Rate of progress in feet per day. | Remarks. | ||
| From | To | From | To | ||||||
| All rock | Bottom heading | 68+61.9 | 69+93 | June 11, '06 | Oct. 16, '06 | 127 | 131.1 | 1.03 | |
| Earth and rock | Bottom heading | 69+93 | 71+65 | Oct. 16, '06 | Feb. 7, '07 | 114 | 172 | 1.51 | |
| All rock | Bottom heading | 71+65 | 71+91 | Feb. 7, '07 | Feb. 13, '07 | 6 | 26 | 4.33 | |
| All rock | Center heading | 71+91 | 75+81 | Feb. 13, '07 | July 20, '07 | 157 | 390 | 2.48 | |
| Earth and rock | Going out of rock | 75+81 | 76+56 | July 20, '07 | Aug. 25, '07 | 36 | 75 | 2.08 | |
| All earth | Soft ground | 76+56 | 90+44.4 | Aug. 25, '07 | Mar. 17, '08 | 205 | 1,388.4 | 6.77 | |
Line D, Long Island.
| Material. | Method. | Station: | Date: | Number of days. | Linear Feet. | Rate of progress in feet per day. | Remarks. | ||
| From | To | From | To | ||||||
| Rock | Bottom heading | 68+50.6 | 69+77 | June 2, '06 | Oct. 24, '06 | 144 | 126.4 | 0.87 | |
| Earth and rock | Bottom heading | 69+77 | 71+22 | Oct. 24, '06 | Jan. 13, '06 | 81 | 145 | 1.79 | |
| All rock | Bottom heading | 71+23 | 72+00 | Jan. 13, '07 | Mar. 3, '07 | 49 | 78 | 1.59 | |
| All rock | Center heading | 72+00 | 75+73 | Mar. 3, '07 | July 10, '07 | 129 | 373 | 2.89 | |
| Earth and rock | Going out of rock | 75+73 | 77+63 | July 10, '07 | Sept 25, '07 | 77 | 190 | 2.47 | |
| All earth | Soft ground | 77+63 | 90+38.6 | Sept 25, '07 | Mar. 7. '08 | 164 | 1,275.6 | 7.78 | |