ENGINE ROOM LABOR COST:

1 chief engineer per day $ 10.00
3 engineers per day $ 8.00
Total per day $ 34.00
365 days at $34.00 equals $ 12,410.00

or 12410 / 60450 = 20.54 cent per ton of ice

ICE PLANT LABOR COST:

(Using present method of pulling ice)

May, June, July, August, September and October require:

6 ice pullers per day $ 6.00
3 air men per day $ 6.00
6 storage house men per day $ 6.00
Total per day $ 90.00
184 days at $90.00 equals $ 16,560.00

March, April and November require:

6 pullers per day $ 6.00
4 storage house men per day $ 6.00
Total per day $ 60.00
91 days at $60.00 equals $ 5,460.00

December, January and February require: