HOOD RIVER COUNTY

Grading—Cascade Locks to Hood River

That section of the Columbia River Highway from the Multnomah County Line to Hood River passes through the narrowest part of the Columbia River Gorge through the Cascade Range. The steep river banks rise directly up from the water’s edge for a large part of the distance, so the space for both railroad and highway is necessarily restricted. At many points, the right of way of the railroad and highway is contiguous and construction under these conditions involved extremely heavy work which added materially to the cost.

THE COLUMBIA RIVER HIGHWAY WEST OF LINDSAY IN HOOD RIVER
COUNTY

Previous to 1915, there was no road through the County, but from the proceeds of a bond issue of $75,000, the County built on State standards a roadway to connect the uncompleted portions. In 1915, the State built about one mile, including the Mitchell Point Tunnel, one of the many scenic features of the Columbia River Highway. One mile of pavement adjoining the Multnomah County pavement was built in 1916 by Mr. S. Benson.

There remained about fourteen miles which require improvement, and on August 7, 1917, contracts were awarded to A. D. Kern for grading of these remaining sections to bring to standard grade and alignment. This improvement eliminated Ruthton Hill, with its narrow, steep grades, three railroad crossings, a narrow, steep grade near Wyeth and the improvement through the village of Cascade Locks to the end of the pavement. The work was divided as follows: Cascade Locks Section, 8.2 miles; Viento Section, 3.6 miles; Ruthton Hill Section, 4.2 miles. These contracts were completed in September, 1918. Due to the close proximity to the railroad tracks, the work required extreme care and watchfulness but was accomplished without accident and without delays to railroad traffic. The costs of construction for each of the three sections follows:

DETAILED EXPENDITURE STATEMENT—GRADING—CASCADE LOCKS
SECTION

Engineering $ 8,744.41
Construction—General—
Common Excavation, 60,660 cu. yds. at 42c $ 25,477.20
Intermediate Excavation, 50,645 cu. yds. at 75c 37,983.75
Solid Rock Excavation, 44,500 cu. yds. at $1.15 51,175.00
Overhaul, per 100 lin. ft., 133,229 cu. yds. at 3c 3,996.87
12-inch Reinforced Concrete Pipe, 1,102 lin. ft. at $1.75 1,928.50
18-inch Reinforced Concrete Pipe, 140 lin. ft. at $2.25 315.00
24-inch Reinforced Concrete Pipe, 284 lin. ft. at $3.00 852.00
30-inch Reinforced Concrete Pipe. 72 lin. ft. at $4.25 306.00
Class A Concrete, 80.86 cu. yds. at $20.00 1,617.20
Class C Concrete, 32.43 cu. yds. at $14.00 454.02
Placing Reinforcing Steel, 3,197 lbs. at .001⁄2 15.99
Catch Basins, 9 at $25.00 225.00
Extra Clearing and Grubbing, 5.79 acres at $200.00 1,158.00
Extra Clearing, 4.13 acres at $100.00 413.00
Herman Creek Bridge—
Class A Concrete, 137.61 cu. yds. at $20.00$ 2,752.20
Class C Concrete, 3.57 cu. yds. at $14.0049.98
Reinforcing Steel (Placing) 23,000 lbs
at.001⁄2
115.00
Reinforcing Steel furnished by State1,394.32
Removing old bridge and constructing
temporary bridge
426.00
Wet excavation for piers664.86
Concrete toe wall to protect fill1,547.98
Railing438.72
Total cost of Herman Creek Bridge 7,389.06
Gorton Creek Bridge—
Excavation for piers$ 483.44
Class A Concrete, 90.85 cu. yds. at $20.001,817.00
Placing Reinforcing Steel, 7,378 lbs.
at.001⁄2
36.89
Reinforcing Steel furnished by State447.27
Railing224.29
Rip-rap145.01
Total cost of Gorton Creek Bridge 3,153.90
Force Account Work as Follows—
Construction and Removal of temporary bridge over
Dry Creek
15.78
Removing Slide from O.-W. R. R. & N. Tracks 95.59
Gravel Surfacing—End of Pavement to Cascade Locks 2,418.55
Railing for Viento Creek Bridge 106.11
Excavating in water and placing Corrugated Iron Pipe 57.92
Excavation and placing drain tile in wet cuts 150.63
Excavation and placing box drain for form crossing 10.44
Riprap on slope to keep fill off O.-W. R. R. & N. Right
of Way
177.29
Water pipe and private road crossing 40.16
Sinking test holes in gravel pit at Cascade Locks 24.93
Road crossing for Herman Creek Ranger Station 167.38
Hauling dirt to cover boulders 264.40
Placing concrete pipe 59.03
Flagmen guarding track (Contractor’s force) 1,234.83
Miscellaneous Construction Items Paid Direct by State—
Replacing Fence 18.75
Reinforcing Steel for Concrete Culverts 193.77
Concrete Pipe furnished by State 71.50
Moving Building in Cascade Locks 1,400.00
Guarding O.-W. R. R. & N. Tracks (Ry. Co. Force) 1,343.69
Guarding Western Union Telegraph Line 498.01
Total Construction Cost $ 144,809.25
Grand Total Cost of Job 153,553.66
Deduction for Rental of State Cars and Track 648.81
Total Cash Expenditure $ 152,904.85