THE COLUMBIA RIVER HIGHWAY NEAR VIENTO IN HOOD RIVER COUNTY. GRADED AND GRAVELED
IN 1917 AND 1918

DETAILED STATEMENT OF EXPENDITURES TO NOVEMBER 30, 1918—
GRADING AND BRIDGES—VIENTO SECTION

Engineering $ 4,513.24
Guarding O.-W. R. R. & N. Tracks 976.47
Guarding Western Union Telegraph Lines 184.64
Diverting Flume Lines 936.37
Reinforcing Steel Furnished by State 257.79
Contract Work as follows:
Common Excavation, 9,480.4 cu. yds. at 39c $ 3,697.35
Intermediate Excavation, 32,654.9 cu. yds. at 70c 22,858.43
Solid Rock Excavation, 54,031.9 cu. yds. at $1.10 59,435.09
Overhaul, per 100 lin. ft., 82,711 cu. yds. at 3c 2,481.33
12-inch Reinforced Concrete Pipe, 622 lin. ft. at $1.75 1088.50
18-inch Reinforced Concrete Pipe, 304 lin. ft. at $2.25 684.00
Class A Concrete, 62 cu. yds. at $20.00 1,240.00
Class C Concrete, 20.8 cu. yds. at $14.00 291.20
Placing Reinforcing Steel, 3,928 lbs. at .001⁄2 19.64
Rubble Masonry, 12 cu. yds. at $7.00 84.00
Catch Basins, one at $25.00 25.00
Gravel Backfill in Rock cut (Force Account) 181.77
Repairing Lindsay Creek Bridge (Force Account) 149.92
Private Road Approach (Force Account) 168.30
Clearing Rock from Mitchell Point Tunnel (Force Acc′t) 93.94
Viento Creek Bridge—
Class A Concrete, 62.7 cu. yds. at $20.00$ 1,254.00
Placing Reinforcing Steel, 3,800 lbs. at .001⁄219.00
Excavation for Footings (Force Account)128.27
Material furnished by State249.70
Total Cost of Viento Creek Bridge 1,650.97
Total Cost to November 30, 1918 $ 101,017.95
15 per cent Retained of Total Amt. ($93,899.74) Earned by Contractors 14,084.96
Total Paid Amount to November 30, 1918 $ 86,932.99

DETAILED STATEMENT OF EXPENDITURES TO NOVEMBER 30, 1918—
GRADING RUTHTON HILL SECTION

Engineering $ 4,074.19
Material furnished by State for Concrete Half Viaduct 200.50
Guarding O.-W. R. R. & N. Tracks 804.57
Contract Construction Work as follows:
Common Excavation, 2,669.5 cu. yds. at 39c$ 1,041.10
Intermediate Excavation, 17,109.4 cu. yds. at 70c11,976.58
Solid Rock Excavation, 79,213.3 cu. yds. at $1.0583,173.96
Overhaul per 100 lin. ft., 19,500 cu. yds. at 3c585.00
12-inch Reinforced Concrete Pipe, 536 lin. ft. at $1.75938.00
18-inch Reinforced Concrete Pipe, 140 lin. ft. at $2.25315.00
Class C Concrete, 15.4 cu. yds. at $14.00215.60
Rubble Masonry, 30 cu. yds. at $7.00210.00
Force Account—
Connecting road with Morton285.50
Covering sharp rocks with clay106.48
Reinforced Concrete Viaduct at Ruthton Hill1,362.51
$ 100,209.73
Less 15 per cent retained pending completion of
contract
15,031.46
Total payments to contractor to Nov. 30, 1918 $ 85,178.27
Total expended to November 30, 1918 $ 90,257.53

Macadamizing—Cascade Locks to Hood River