The "Victoria" bridge at Montreal is a very different structure. A long sheet-iron box, 9,184 feet in length, with 26 piers 60 feet above the water level, and costing from first to last 2,000,000_l_. sterling. The burning of coal had begun to affect it; but Mr. Haunaford, the chief engineer of the Grand Trunk, has made some openings in the roof, which do not in any way reduce the strength of the bridge, and at the same time get rid of, at once into the air, the sulphurous vapours arising from coal combustion.

Mr. Peterson told me that their soundings in winter showed that ice thickened and accumulated at the bottom of the river. This would seem, at first sight, impossible. But experiment, Mr. Peterson said, had proved the fact, which was accounted for by scientific people in various and, in some cases, conflicting ways. May it not be that the accumulation is ice from above, loaded with earth or stones, which, sinking to the bottom by gravity, coagulates from the low temperature it produces itself? Mr. Peterson is not merely an engineer, and an excellent one, but an observant man of business. His views upon the all-important question of colonising the unoccupied lands of the Dominion seemed to be wise and far-sighted. He would add to the homestead grants of land, an advance to the settler—a start, in fact —of stock and material, to be repaid when final title to the property, were given.

Taking leave of my old friends, I left Montreal at 8 p.m. on the night of September 15th, in the ordinary "Pacific Express," on which was attached Mr. Van Horn's car, in charge of James French. I went by ordinary train because I was anxious to have an experience of the actual train-working. Mr. Edward Wragge, C.E., of Toronto, an able engineer of great experience, located now at Toronto, has sent me so concise an account of the journey of this train, and of the general engineering features of the line, that, anticipating his kind permission, I venture to copy it:—

"Leaving Montreal in Mr. Van Horn's car, the 'Saskatchewan,' by the 8 p.m. train on the 15th September, we passed Ottawa at 11.35 p.m.

"During the night we ran over that portion of the Canadian Pacific Railway which was formerly called the Canada Central Railway, and reached Callander (344 miles from Montreal), the official eastern terminus of the Canadian Pacific Railway, at 8.30 a.m. 13 miles from this, at Thorncliff is the junction with the Northern and Pacific Junction Railway, which forms the connection with Toronto and Western Ontario, being distant from Toronto 227 miles. At North Bay, which is a divisional terminus, the line touches Lake Nipissing, where there is a flourishing settlement, the land being of a fair quality. The line is laid with steel rails, about 56 lbs. to the lineal yard, and with ties about 2,640 to the mile. For the first 60 or 70 miles from Callander the line is ballasted entirely by sand, and, with the exception of a few settlements, is entirely without fencing. Most of the bridges are of timber; but there are one or two of the larger ones of iron or steel, with masonry abutments.

"At Sudbury is the junction with the Algama Branch, not yet opened for traffic. This is 443 miles from Montreal. After leaving Sudbury the character of the country changes, and is alternately swampy and wild rocky land. Numerous large trestles are necessary, which will eventually be filled in with culverts and earthwork. The schedule running time of the trains along this portion of the line is 24 miles per hour, including stoppages.

"At 8 p.m. Chapleau, another divisional terminus, was reached, and the schedule running time during the night from that point to Heron Bay, reached at 5.15 a.m. the following morning, is 20 miles an hour. At Heron Bay (802 miles from Montreal) the north shore of Lake Superior is first touched, and the line runs along it to Port Arthur, a distance of 993 miles from Montreal. The scenery here is very wild and picturesque. At one time the line runs along the face of the rock, with the lake from 50 to 100 feet below, the road-bed being benched out on the cliff, and at another time is away back among barren hills and rocks, crossing several large streams (with either bridges of iron and masonry or timber trestle work), which streams flow into the lake at the north end of deep indentations or arms of the lake. The line through this district is winding, having many sharp curves and steep grades. There are several short tunnels, all of them through rock, and not lined. The schedule time for trains on this portion of the line is 16 miles per hour. We were detained some little time near Jack Fish, owing to a slight land slide coming down in one of the cuttings.

"The Nepigon River is crossed at a high level with a steel trussed bridge, masonry piers and abutments, and there is an old Hudson's Bay settlement on the river a short distance above the bridge. Between Nepigon and Port Arthur the line runs through a country much more accessible for railways, and the schedule time here is at the rate of 24 miles an hour. We reached Port Arthur at 4 p.m. on the 17th. This is a flourishing town, situated at the head of Thunder Bay, a large bay on the north shore of Lake Superior, and has a population of four or five thousand at the present time. From the north shore of Lake Nipissing to this point, however, a distance of over 600 miles, the country may be said to be almost without inhabitants, except those connected with the working of the railway, squatters, and Hudson's Bay trappers and traders. The weather was chilly during the evening of this day, and a heavy sleet storm arose before arriving at Port Arthur. At night a fire had to be lighted in the car, as there was a sharp frost. During the night the train was detained for some little time east of Rat Portage, in consequence of a trestle having given way while being pulled in, and the train arrived at Rat Portage at 7.30 a.m., four hours, behind time.

"From Port Arthur the line westward is run upon the 24 o'clock system, commencing from midnight; 1 p.m. being 13 o'clock, 2 p.m. being 14 o'clock, and so on. The train arrived at Winnipeg at 12.45 on the 18th (1,423 miles from Montreal), and time was allowed to drive round the town, the train leaving again for the west at 13.30 o'clock. From Winnipeg westward the line runs through a prairie country, which extends without intermission to Calgary, a distance of 838 miles, and 2,261 from Montreal. At Winnipeg the Company have good machine shops, round houses, &c., and a large yard, and has acquired 132 acres of land for these purposes of working and repair and renewal.

"The country for three or four hundred miles from Winnipeg west is more or less settled; in some parts farms are quite numerous, and the land good and well cultivated. At Portage la Prairie the Manitoba and North- Western Line leaves the Canadian Pacific. It is being rapidly pushed forward, and 120 miles of it have already been completed through the 'Fertile belt.' It should have been mentioned that the line between Port Arthur and Winnipeg, a length of 430 miles, was constructed by the Government of Canada and given to the Canadian Pacific Railway Company free as a portion of their system. This part of the line is laid with 57 lbs. steel rails, and is well ballasted. The line is also ballasted east of Port Arthur, though in some places the ballast is of poor quality, and in others there is not sufficient of it. West of Winnipeg, however, there is no ballast across the prairie, except where the excavations through which the line goes afford ballast, it being simply surfaced up from side ditches with whatever the material may happen to be; but it is in good condition for a line of such a character, and the schedule time is 24 miles an hour, including stoppages.